Zero Trust Network Access Broker

Decided Key decision Committee 1 paper

AI summaryCabinet Member for Resources and Deputy Leader authorises procurement of Zscaler secure connectivity and cyber security services, delegating contract award to the Head of IT Services.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeDecidedAuthority delegated to Head of IT Services
MoneyNot stated in main reportThree year contract cost in Appendix 1
What happens nextProcure and award contractDirect award under KCS framework
Who it affectsCouncil IT users and systemsOfficers and future LGR arrangements

What was decided

The Cabinet Member authorised procurement of Zscaler secure connectivity, access and cyber security services from a suitable supplier. Report P2

Authority to award the contract was delegated to the Head of IT Services, in line with the recommendation. Report P2

Why

The existing contract with Softcat PLC for Zscaler Internet Access and Zscaler Private Access expires on 26 December 2026 and needs to be renewed. Report P3

Zscaler services strengthen the Council's cyber security posture, blocking malicious traffic and restricting users to entitled applications, and are becoming an industry standard. Report P4

The services support Local Government Reorganisation by enabling secure access across multiple environments and providing flexibility for future organisational change. Report P4

What happens next

The service area intends to direct award a new three year call off contract under the Kent Commercial Services Software Products and Associated Services framework, reference Y23065. Report P6

Legal Services will prepare the necessary contract documentation, with the award to comply with the Public Contracts Regulations 2015 and the framework's rules. Report P6

A budgetary pressure is anticipated in 2027/28 and will need to be addressed within the budgetary cycle. Report P5

The money

  • estimated cost of a three year contract (figure in Appendix 1) Zscaler secure connectivity, access and cyber security services, charged to IT Service cost centre R41000 Report P5

Options considered

  • Chosen: Direct award under the KCS Software Products and Associated Services framework Y23065. Compliance with PCR 2015 Regulation 33(8) and the framework's user guide, and continuity of a deployed platform Report P6

Implications

  • Financial: A pressure is anticipated in 2027/28 and will need to be addressed within the budgetary cycle to maintain the overall position. Report P5
  • Legal: Award to comply with the Public Contracts Regulations 2015, the Council's Contract Procedure Rules and the KCS framework user guide. Report P6
  • Risk: Renewal mitigates significant cyber and operational risks while maintaining a proven platform already deployed across the organisation. Report P7
  • Other: New contractual terms will need to accommodate changes arising from Local Government Reorganisation, including organisational boundaries, user numbers and service requirements. Report P4

Who and where

  • Council officers using OCC devices to access the internet, council applications and internal resources Report P4
  • IT Service, with the contract charged to cost centre R41000 Report P5
  • Future unitary authorities and shared service arrangements created through Local Government Reorganisation Report P4

Timeline

  • 2019: Cabinet approved the 2019 to 2024 IT Strategy committing to Zero Trust connectivity, and Softcat PLC was appointed to provide Zscaler ZIA and ZPA services. Report P3
  • 26 December 2026: Current contract with Softcat PLC expires. Report P3
  • 2027/28: A budgetary pressure is anticipated and will need to be addressed within the budgetary cycle. Report P5

Plain English for the jargon

  • ZIA: Zscaler Internet Access, a service that inspects internet traffic and blocks malicious or inappropriate activity.
  • ZPA: Zscaler Private Access, software on end user devices that allows officers to connect only to the applications they are entitled to use.
  • Zero Trust: A connectivity approach that checks every user and device before granting access, removing the need for a traditional Wide Area Network.
  • LGR: Local Government Reorganisation, the restructuring of councils in Oxfordshire into new unitary authorities.
  • KCS: Kent Commercial Services, which established the Software Products and Associated Services framework reference Y23065.
  • PCR 2015: Public Contracts Regulations 2015, the procurement rules governing how public bodies award contracts.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item9/25

Resolved

Resolved to: a. Authorise the procurement of Zscaler secure connectivity, access and cyber security services from a suitable supplier; and b. Delegate authority to the Head of IT Services to award a contract in accordance with recommendation (a).
Word for word from the decision Oxfordshire published for this meeting. Source: mycouncil.oxfordshire.gov.uk

Follow this further

Built from Oxfordshire's papers

What the report saysPro

Report to Resources and Deputy Leader

Recommendation

The Cabinet Member is RECOMMENDED to:

a. Authorise the procurement of Zscaler secure connectivity, access and cyber security services from a suitable supplier; and b. Delegate authority to the Head of IT Services to award a contract in accordance with recommendation (a).

Executive Summary 1. Originally introduced as part of a Cabinet-approved strategy in 2019 (the “2019-24 IT Strategy”), the Council appointed Softcat PLC to provide Zscaler Internet Access (ZIA) and Zscaler Private Access (ZPA) services, enabling officers to securely access the internet, council applications and internal resources in support of the Council’s Technology Strategy 2025-2028. 2. In the 2019–24 IT Strategy, OCC committed to using Zero Trust as the preferred method for connectivity, allowing the removal of the Wide Area Network and the use of cheaper, faster internet services. Zscaler enabled the delivery of this approach. 3. The current contract with Softcat PLC will expire on 26 December 2026. Therefore, this key decision seeks to obtain authority to procure and award a contract for the Zscaler secure connectivity, access and cyber security services from a suitable supplier, with contract value as specified in Appendix 1.

Local Government Reorganisation implications 4. The Zscaler services support Local Government Reorganisation (“LGR”) by enabling secure access across multiple environments and providing a flexible foundation for collaboration, federation, shared services and wider organisational change. Consideration will need to be given to the new contractual terms and the extent to which they can accommodate changes arising from LGR, including changes to organisational boundaries, user numbers and service requirements. Any such changes will need to be managed in compliance with all relevant legislation and the Framework’s rules. Scope of the Zscaler Services 5. Zscaler services are already deployed across OCC devices to provide secure access to the internet, council applications and internal resources. 6. Zscaler ZIA inspects internet traffic and blocks malicious or inappropriate activity. Zscaler ZPA is installed on every end-user device and allows officers to connect only to the applications they are entitled to use. This reduces the risk of lateral movement across the network, a technique commonly used by attackers to compromise traditional environments. 7. The current use of ZIA and ZPA has strengthened OCC’s security posture and mitigates many of the cyber security risks associated with traditional environments. This approach is increasingly becoming an industry standard.

Financial Implications 8. The estimated cost of a three-year contract is included in the medium-term financial plan for the IT Service cost Centre R41000 and detailed in Appendix 1. 9. It is now anticipated a pressure will occur in 2027/28 and will need to be addressed within the budgetary cycle to maintain the overall position. Comments checked by: Drew Hodgson, Finance Business Partner (Resources), [email protected]

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Zero Trust Network Access BrokerReport 104 KB DownloadRead as text

At this meeting

Whole meeting
8/25Minutes of the Previous MeetingOn the agenda
9/25Zero Trust Network Access BrokerThis decision

Who was there

1 of 2 attended
NF
Councillor Neil FawcettCommittee Member, present
JA
Jack AhierSecretary, expected

More from Oxfordshire Resources and Deputy Leader

All decisions
MeetingDecisionOutcome
19 May 2026 Children and Adults Social Care System Maintenance and SupportRESOLVED to: a) Retrospectively authorise the Head of IT to procure the Support and Maintenance agreement with Liquid... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies