08/01365/FUL - French Farm French Drove Thorney Peterborough*

Refused Planning 2 papers

Planning and Environmental Protection Committee refused this item on Tuesday 7 July 2009. Below is the council's own wording, with the papers it was decided on.

Item51

Resolved

Resolved (8 for, 1 abstention) : To accept officer recommendations and reject the application. Reason for decision : The proposed wind turbine development would unacceptably affect Ministry of Defence radar systems to the degree that it would not, if the turbines were constructed, be possible to provide a safe and expeditious air traffic service to military and non-military aircraft in the area. The Ministry of Defence has advised that the applicant has failed to prove that the proposal would have no adverse impact on aviation interests as required in accordance with paragraph 25 of Planning Policy Statement 22 (PPS 22) – Renewable Energy which states; ‘It is the responsibility of developers to address any potential impacts, taking account of Civil Aviation Authority, Ministry of Defence and Department for Transport guidance in relation to radar and aviation, and the legislative requirements on separation distances, before planning applications are submitted. Local Planning Authorities should satisfy themselves that such issues have been addressed before considering planning applications’. and paragraph 96 of the Companion Guide to PPS 22 which states: Because topography, intervening buildings and even tree cover can mitigate the effect of wind turbines on radar, it does not necessarily follow that the presence of a wind turbine in a safeguarding zone will have a negative effect. However, if an objection is raised by either a civil aviation or Defence Estates consultee , the onus is on the applicant to prove that the proposal will have no adverse impact on aviation interests . Thus the proposal is contrary to the provisions of Planning Policy Statement 22.
Word for word from the decision Peterborough published for this meeting. Source: democracy.peterborough.gov.uk

Follow this further

Built from Peterborough's papers

What the report saysPro

Report to Planning and Environmental Protection Committee

P & EP COMMITTEE: 7 July 2009 ITEM NO 02

08/01365/FUL: ERECTION OF TWO WIND TURBINES WITH CONTROL BUILDING AND ANCILLARY WORKS AT FRENCH FARM THORNEY PETERBOROUGH VALID: 22 DECEMBER 2008 APPLICANT: CORNWALL LIGHT AND POWER LTD REFERRED BY: HEAD OF PLANNING SERVICES REASON: TO KEEP MEMBERS INFORMED IN VIEW OF PREVIOUS INTEREST DEPARTURE: NO CASE OFFICER: DALE BARKER TELEPHONE: 01733 454411 E-MAIL: [email protected]

1 SUMMARY/OUTLINE OF THE MAIN ISSUES

The main considerations are: i) Planning policy ii) The impact of the development on the character and appearance of the rural area iii) The cumulative impact of the proposed turbines with existing and potential turbines in the vicinity iv) Impact on Residential Amenity - Visual v) Impact on Residential Amenity - Noise vi) Aviation issues vii) Wildlife Implications viii) Highway Safety ix) Impact on National Gas Grid x) Trees xi) Other Issues - The Impact of the proposal on Agriculture, Property Values, Health, Shadow Flicker, Section 106 Obligation Implications

The Head of Planning Services recommends that the application is Refused.

2 PLANNING POLICY

City Centre Framework Implications: NONE

Village Design Statement Implications: NONE

Central Government Advice

• White Paper on Energy - May 2007 - Meeting the Energy Challenge

In summary the White Paper is seeking to tackle climate change by reducing carbon dioxide emissions both within the UK to ensure a secure, clean and affordable energy provision as the country becomes increasingly dependent upon imported fuel.

The White Paper expands on the need for the country to save energy whilst at the same time focusing upon Renewables as the key to the Government’s strategy to tackle climate change and deploy cleaner sources of energy.

The Governments target is to have renewable energy production to grow as a percentage of the country's electricity supply to 10% by 2010 with an aspiration for this level to double by 2020. The Renewables obligation is the main mechanism for promoting this growth. (The Government requires energy suppliers to provide a percentage of the energy they generate from renewable sources).

23 • White Paper - Planning for a Sustainable Future - 2007

The White Paper emphasises the need for an efficient and effective planning system. It emphasises the need for Local Authorities to make timely decisions whilst taking full account of representations from the public and those bodies consulted on an application. It sees that climate change is a key challenge facing this generation and that the targets that have been set by way of increasing percentages of renewable energy production are to be met. Applicants proposing renewable energy developments no longer have to justify a need for the proposal.

It makes reference to an emerging Planning Policy Statement on Climate Change where it will make it clear that the government will expect Local Authorities to look favourably upon proposals for renewable energy projects.

The Department of Trade and Industry published, in 1997, the Assessment and Rating of Noise from Wind Farms. To provide a framework for the measurement of turbine noise. It gives indicative noise levels thought to offer a reasonable degree of protection to wind farm neighbours. The report recommends:- o The control of wind farm noise by the application of external noise limits at the nearest noise sensitive premises o Setting limits relative to background noise o Setting separate daytime and night-time limits o Limits should be 5dB (a) above background o A noise rating and monitoring scheme for developer/Local Authority adoption

• Planning Policy Statement 22 (PPS22) - Planning for Renewable Energy

PPS22 and its companion guide outline 8 key principles in the Government’s approach to renewable energy. These are as follows:-

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
08/01365/FUL: French Farm French Drove Thorney Peterborough*Plan 159 KB Download
PDF
French Farm FinalReport 220 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

10 of 11 attended
NN
Councillor Nigel NorthChairman, present
MB
Councillor Michael Burton OBE FRINVice Chair, present
MT
Councillor Marion ToddCommittee Member, apologies
CA
Councillor Chris AshCommittee Member, present
CB
Councillor Colin BurtonCommittee Member, present
MP
Councillor Mrs Pam KrelingCommittee Member, present
SL
Councillor Stephen LaneCommittee Member, apologies, sent representative
PT
Councillor Paula Thacker MBECommittee Member, present
PW
Councillor Pamela WinsladeCommittee Member, present
MY
Councillor Mrs Yvonne LowndesCommittee Member, present
KS
Councillor Keith SharpReserve, present as substitute

More from Peterborough Planning and Environmental Protection Committee

All decisions
MeetingDecisionOutcome
1 Sep 2026 Minutes of the Meeting Held on 09 June 2026RESOLVED (unanimously) to approve the minutes of the meeting held on 09 June 2026 as a correct record and be signed b... Approved Open
1 Sep 2026 26/002478/HHFUL - 5 Park Lane, Peterborough PE1 5JHRESOLVED (6 For, 3 Against, 1 Abstention) to GRANT planning permission, with the final conditions delegated to office... Decided Open
9 Jun 2026 Minutes of the Meeting Held on 7 April 2026RESOLVED (unanimously) to approve the minutes of the meeting held on 7 April 2026 as a correct record and be signed b... Approved Open
7 Apr 2026 Minutes of the Meeting Held on 9 December 2025RESOLVED (unanimously) to approve the minutes of the meeting held on 9 December 2025 as a correct record and be signe... Approved Open
7 Apr 2026 26/00064/HHFUL - 579 Fulbridge Road, Peterborough, PE4 6SARESOLVED (9 For, 1 Against) to DEFER the application to the next meeting of 9 June 2026. Reasons for Decision To prov... Deferred Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies