Planning and Environmental Protection Committee refused this item on Tuesday 22 September 2009. Below is the council's own wording, with the papers it was decided on.
Subject to the imposition of the conditions, the proposal was acceptable having been assessed in the light of all material considerations, including weighting against relevant policies of the development plan and specifically: · The proposed ‘Home Zone’ design was considered acceptable because all cars and other vehicles such as emergency and refuse vehicles could easily come and leave from the proposed development and the sign post allowing a maximum speed of 10 mph would assist in preventing the creation of a rat run from the street to other nearby roads. Given the traffic speed that was in place, it would assist to safeguard pedestrian movement and other road users. This was acceptable and in accordance with policies T1, ... view the full minutes text for item 6.
Word for word from the decision Peterborough published for this meeting.Source: democracy.peterborough.gov.uk
Report to Planning and Environmental Protection Committee
P & EP Committee: 22 SEPTEMBER 2009 ITEM NO 5.1
08/00292/FUL: DEMOLITION OF EXISTING WAREHOUSE, ERECTION OF 132 DWELLINGS, 5 X LIGHT INDUSTRIAL UNITS, AND 4 X WORKSHOPS, EXTENSION TO EXISTING OFFICES AT SHREWSBURY AVENUE, WOODSTON (AMENDMENT TO HIGHWAY LAYOUT) VALID: 25 MARCH 2008 APPLICANT: CKHD DEVELOPMENTS LTD AGENT: ARCHITECTS DESIGN CONSORTIUM LTD REFERRED BY: HEAD OF PLANNING SERVICES REASON: A DIFFERENT METHOD OF TRAFFIC CALMING IS PROPOSED TO THAT RESOLVED BY THE PLANNING COMMITTEE
CASE OFFICER: EMMANUEL ALLANAH TELEPHONE: 01733 454413 E-MAIL: [email protected]
1 SUMMARY/OUTLINE OF THE MAIN ISSUES
The main considerations are:
• The impact of the proposal upon traffic and the surrounding area.
The Head of Planning Services recommends that the application is APPROVED subject to a Section 106 Agreement being entered into in order to secure financial contributions to meet the affordable housing, educational capacity, and community centre needs of the area.
For the avoidance of doubt, this is not a new planning application but a revision to the 2008 application which has not been issued because of the need to address concerns relating to traffic impact and the need to resolve a Section 106 obligation.
2 PLANNING POLICY
In order to comply with section 38(6) of the Planning and Compulsory Purchase Act 2004 decisions must be taken in accordance with the development plan policies set out below, unless material considerations indicate otherwise.
Development Plan Policies
Relevant policies are listed below with key policies highlighted.
The Peterborough Local Plan (First Replacement)
T1 Transport implications of New Development – planning permission will only be granted if the development would provide safe and convenient access to the site and would not result in an adverse impact on the public highway. The amended highway design changes will not adversely affect traffic in the area, hence it is considered acceptable.
T8 Connections to the Existing Highway Network- planning permission will only be granted for development if vehicular access is on to a highway whose design and function is appropriate for the level of vehicular traffic likely to be generated by the proposed development. Proposed traffic design scheme will improve vehicular access to the approved scheme.
7 T10 Car and Motorcycle Parking Standards- planning permission will only be granted if the development would provide adequate parking provision in accordance with approved parking standards. The amended traffic scheme will not affect proposed car and motorcycle parking standards.
Material Planning Considerations
Planning Policy Statement 1 – Delivering Sustainable Development Planning Policy Guidance 13 - Transport
3 DESCRIPTION OF PROPOSAL
The proposal is an amendment to the highway design in connection with the planning application that was considered by Members on 29 July 2008 which they resolved to approve subject to a condition requiring no through route to Lansdowne Way and a Section 106 obligation as set out above. The idea behind the no through route to Lansdowne Way was to prevent traffic driving through the development to avoid congestion at the Lansdowne Way / Shrewsbury Avenue junction. This change would have made the development a cul-de-sac served from Shrewsbury Avenue. Had it been implemented the layout of the development would have to be changed with the loss of some dwellings in the area where it abuts Lansdowne Way in order that a turning head could be provided. As an alternative to this, it is now proposed that the development will continue to have a through link between Lansdowne Way and Shrewsbury Avenue but that it will be significantly traffic calmed using ‘homezone’ principles. The principle of this has been agreed by Cllr Scott (Local Ward Councillor).
4 DESCRIPTION OF SITE AND SURROUNDINGS
Please see the attached committee report dated 29 July 2008 registered as 08/00292/FUL. Annexe 1A
5 PLANNING HISTORY
None.
6 CONSULTATIONS/REPRESENTATIONS
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Planning and Environmental Protection Committee at Peterborough and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.