Footpaths and Cycle routes in Rural Areas

Agreed Committee 2 papers

Rural Communities agreed this item on Monday 19 September 2011. Below is the council's own wording, with the papers it was decided on.

Item4

Resolved

Decision Notice. The Transport Planning Officer provided an update to Members on the Local Transport Plan and the three capital budgets, which was used to set out the spending across project areas for improvements for the next five years. Members also received an update from the Highway Maintenance Manager, on the work being conducted on Rights of Way improvements by the Highway Maintenance Team, once the budgets had been agreed. Members were advised that the Rights of Way scheme had been included in the Local Transport Plan Two document and would continue to be delivered until 2016. Key points highlighted were: · Public rights of way scheme; · Statements of action; · Adequate sign posting; · Maintenance work; and · Values within the rights of way improvement plan capital budget. Members were advised that the Transport Asset Management Plan (TAMP) detailed how the Highways Team would deal with asset management and that it would be used as a gap analysis to identify the work needed for the plan, and identified priorities. Questions and observations were made around the following areas: · Members commented about the improvement plans that the Transport and Engineering Team had set out within their policy documents and that consideration was required for the deepest rural areas in order to provide adequate footpaths, improve existing pathways and make provision to inform villagers where footpaths were available between villages. · Members commented that existing footpaths within the City were not being maintained to an adequate standard and that the Local Transport Plan funding was ring fenced for new projects. Members added that the money received from the Local Transport Plan could be spent more wisely on improving the existing footpaths. · Members also commented that the River Nene was being poorly maintained by the Environment Agency. It was thought that the maintenance problems were due to funding issues and that the Council may wish to consider contacting the appropriate Government Department to raise the issue with them. · Members sought clarification over what improvements had been made for cycling over the last year within the rural areas? T he Climate Change Team Manager advised Members that villagers had been consulted recently about what cycle improvements, they would like to see. A good response had been received from Glinton and had resulted in a cycle park being installed. Unfortunately there had been a poor ... view the full minutes text for item 4.
Word for word from the decision Peterborough published for this meeting. Source: democracy.peterborough.gov.uk

Follow this further

Built from Peterborough's papers

What the report saysPro

Report to Rural Communities

Recommendations

2.1Note the content of the presentation and discuss a way forward.

3. LINKS TO THE SUSTAINABLE COMMUNITY STRATEGY

3.1How does the report link to the Sustainable Community Strategy?

Peterborough’s Long Term Transport Strategy, Local Transport Plan 3, Transport Asset Management Plan and Rights of Way Improvement Plan are all Peterborough City Council documents that are in place and set out the Council’s vision, objectives and strategy for transport improvements.

These documents share common aspirations and contribute to varying degrees towards the Sustainable Community Strategy goals to:

• Create opportunities – tackling inequalities • Create strong and supportive communities • Create UK’s environment capital • Deliver substantial and truly sustainable growth

What National Indicators does the report help to achieve?

Improvements to footpaths, rights of way and general accessibility in rural areas can contribute to improvements to the following National Indicators :

• NI47 Total killed and seriously injured • NI48 Child killed and seriously injured • NI177 Public transport patronage • NI175 Access to services • NI198 Mode share journeys to school • BVPI 187 Footway condition

4. BACKGROUND A number of documents outline the way in which decisions regarding potential improvements to footpaths and cycle routes in the rural area of Peterborough can be taken forward by the city council. The purpose of the presentation to the Scrutiny Commission for Rural Committee is to discuss a way forward regarding potential improvements to the infrastructure in rural areas.

4.1Long Term Transport Strategy and Local Transport Plan 3 The Council adopted Peterborough’s LTTS and LTP3 in April 2011. 5 The LTTS (2011-2026) is the 15 year plan of how transport provision can support the authorities sustainable growth agenda. This strategy was developed by assessing the Peterborough Core Strategy and producing the Integrated Development Programme (IDP).

The LTP3 (2011-2016) is a statutory document that the city council produces every five years. The LTP3 covers the short-term period set out in the LTTS and sets out the authorities transport policy and strategy for Peterborough.

The two documents combine to create an ambitious transport vision for Peterborough that can meet the following goals:

• Tackle climate change • Support economic growth • Improve quality of life and promote a health natural environment • Contribute to better safety, security and health • Promote equality of opportunity

LTP3 identifies the strategy items by mode, and details the slightly different approaches that are most appropriate for different areas of the city including rural areas.

A capital budget is allocated annually for integrated transport. The schemes delivered each year are identified via a number of means for the capital programme of works (please see Appendix 1)

Transport Asset Management Plan

The Transport Asset Management Plan (TAMP) demonstrates how an effective approach to asset management, can help us to maintain the highway network in a condition to enable the safe passage of the travelling public.

Asset Management is defined as:

“Asset management is a strategic approach that identifies the optimal allocation of resources for the management, operation, preservation and enhancement of the highway infrastructure to meet the needs of current and future customers.”

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Scrutiny Report Rural Footpaths and Cycleways Development of Capital ProgrammeAppendix 1 45 KB Download
PDF
Footpaths and Cycle routes in Rural AreasReport 69 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

6 of 12 attended
DO
Councillor David OverChairman, present
GN
Councillor Gul NawazVice Chair, present
RD
Councillor Ray DobbsCommittee Member, absent
DS
Councillor David SandersCommittee Member, present
DH
Councillor David HarringtonCommittee Member, present
EM
Councillor Ed MurphyCommittee Member, apologies
AS
Councillor Asif ShaheedCommittee Member, present
NS
Councillor Nabil ShabbirReserve, present as substitute
PF
Paulina FordOfficer, expected
JH
Jenny Harris Legal ServicesNotify
RL
Ruth Lea Legal ServicesNotify
AD
Alex DaynesNotify

More from Peterborough Rural Communities

All decisions
MeetingDecisionOutcome
12 Jan 2015 Work ProgrammeAGREED ACTION The Commission noted and agreed the 2014/2015 work programme. Agreed Open
17 Nov 2014 Work ProgrammeAGREED ACTION Members noted the work programme and agreed for the Cabinet Member for Housing and planning Services, w... Agreed Open
20 Oct 2014 Work ProgrammeAGREED ACTION Members noted the work programme and agreed for the Cabinet Member for Housing and planning Services, w... Agreed Open
1 Sep 2014 Work ProgrammeAGREED ACTION Members noted the work programme and agreed for the following items to be added to the : · The Flood Ri... Agreed Open
7 Jul 2014 Work Programme 2014-2015AGREED Members considered the Commission’s Work Programme for 2014 - 15 and agreed to the following items for inclusi... Agreed Open