Peterborough Limited (OSA) integration Progress Report

Decided Scrutiny 1 paper

AI summaryScrutiny committee reviews progress on in-sourcing services from Peterborough Limited, with about 380 staff posts set to transfer on 1 April 2026 under TUPE arrangements.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeDecidedReviewed OSA insourcing update and provided feedback to officers
Money£1.9m cost pressuresProvisionally included in 2026/27 budget working drafts
What happens nextDetailed budget by year endExit agreement being drafted; full EIA pending scope decision
Who it affects~380 transferring staffPL and Aragon posts; sub-contractor employee details not yet known

What was decided

The committee reviewed the progress report on the in-sourcing of services from Peterborough Limited and provided feedback to officers. Report 4.1

Members noted that 12 months' notice to terminate the OSA has been given, with the last day of the agreement being 31 March 2026, and no phased or earlier termination agreed. Report 7.2

Why

The update relates to the Cabinet decision of 11 March 2025 to in-source the services covered by the Operational Services Agreement and end the agreement with Peterborough Limited. Report 4.1, 5.1, 13.1

Officers say regular updates are appropriate so the scrutiny committee can be kept informed and able to input into the process. Report 11.1, P25

What happens next

Officers will continue developing the detailed in-house budget, with the process not expected to conclude until at least the end of the calendar year. Report 5.2

Peterborough Limited will lead staff consultation with the council actively participating, and the council will continue gathering information on assets, contracts and sub-contractor staffing. Report 4.2, 7.3, 7.8

An exit or termination agreement between the council and Peterborough Limited is being drafted to capture asset lists and contractual arrangements. Report 7.5

The money

  • £1.9m Revised estimate of overall cost pressures from insourcing, provisionally included in 2026/27 budget working drafts Report 5.2

Options considered

  • Rejected: Not provide updates to the committee. It is appropriate for members to be updated and to input into the process Report P25
  • Rejected: Provide only written updates. Officers welcome discussion with members to explore specific elements in more detail Report P26

Implications

  • Financial: An initial assessment of insourcing financial implications was set out in the 11 March 2025 Cabinet report, with revised cost pressure estimates of £1.9m provisionally included in 2026/27 budget drafts. Report 5.1, 5.2
  • Legal: Full exit planning information under the OSA has not yet been received, and consideration of third-party contract novation has not yet been undertaken. Report 7.2, 7.3
  • Legal: An exit or termination agreement is being drafted to capture asset lists and contractual arrangements and mitigate the risk of missing information. Report 7.5
  • Staffing: Approximately 380 posts are expected to transfer from Peterborough Limited and Aragon, with offers of day one council terms and conditions, but full details of sub-contractor employees subject to TUPE are not yet known. Report 7.8, 8.1
  • Equalities: A comprehensive Equality Impact Assessment cannot yet be completed because the scope of the transfer has not been finalised and full staff data is not available. Report P21, P22
  • Risk: The full impact on Peterborough Limited and its subsidiary PCHLL is not yet known, and the viability position remains unclear. Report 7.6
  • Other: Several other home to school transport contracts between the council and Peterborough Limited will also expire on 31 March 2026 and be in-sourced to align with the OSA in-sourcing. Report 7.9

Who and where

  • Around 380 staff transferring from Peterborough Limited and Aragon Report 8.1
  • Sub-contractor employees whose details are not yet known Report 7.8, 8.1
  • Peterborough Limited and its subsidiary PCHLL Report 7.6
  • Third-party contractors and commercial clients of Peterborough Limited whose arrangements are being reviewed for novation or continuation Report 7.3

Timeline

  • 11 March 2025: Cabinet decision to in-source services and terminate the OSA Report 5.1, 13.1
  • 7 July 2025: Previous Peterborough Limited (OSA) integration report to Shareholder Cabinet Committee Report 13.2
  • 13 November 2025: Progress report considered by Sustainable Future City Council Scrutiny Committee Report 4.1
  • 31 March 2026: Last day of the OSA, with home to school transport contracts also expiring Report 7.2, 7.9
  • 01 April 2026: Anticipated TUPE transfer date for OSA Peterborough Limited staff Report P22
  • End of the calendar year: Detailed in-house budget expected to be concluded Report 5.2

Plain English for the jargon

  • OSA: Operational Services Agreement, the contract between the council and Peterborough Limited covering operational services
  • PL: Peterborough Limited, the council's arms-length company that delivers services under the OSA
  • PCHLL: A subsidiary of Peterborough Limited, details of whose activities are not yet known
  • TUPE: Transfer of Undertakings (Protection of Employment) regulations that protect staff when services transfer to a new employer
  • ELI: Employee Liability Information, data provided by the outgoing employer about transferring staff
  • MTFS: Medium Term Financial Strategy, the council's multi-year budget planning document
  • EIA: Equality Impact Assessment, an assessment of how a policy or change may affect different groups
  • Novation: The process of transferring contractual rights and obligations from one party to another
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item23

Resolved

RESOLVED to review the report and provided feedback to officers.
Word for word from the decision Peterborough published for this meeting. Source: democracy.peterborough.gov.uk

Follow this further

Built from Peterborough's papers

What the report saysPro

Report to Sustainable Future City Council Scrutiny Committee

13 November 2025 Item 7 Sustainable Future City Council Scrutiny Committee

Peterborough Limited (OSA) integration Progress Report

Report author: Charlotte Palmer, Service Director for Environment and Climate Change

Responsible Director: Adrian Chapman, Executive Director for Place and Economy

Cabinet Member(s) Cllr Angus Ellis, Cabinet Member for responsible: Environment and Transport

Executive Summary: The purpose of this report is to provide an update to the committee detailing progress made against the council’s decision relating to its Operational Services Agreement (OSA) with Peterborough Limited, namely, the in- sourcing of those services and the termination of the OSA (KEY/10MAR25/01, linked below).

Recommendations: The Committee is asked to review this report and provide feedback to officers as necessary.

1. Purpose

1.1The purpose of this report is to provide an update to the committee detailing progress made against the council’s decision relating to its Operational Services Agreement (OSA) with Peterborough Limited, namely, the in- sourcing of those services and the termination of the OSA (KEY/10MAR25/01, linked below).

2. Background and key issues

2.1Peterborough Limited (PL) is a limited company, wholly owned by the council. It was formed as a “Teckal” compliant company, which allows contracts for works, services and goods to be awarded by the council to PL without the need for a competitive procurement exercise. PL commenced service delivery in February 2019 by virtue of an Operational Services Agreement (OSA) between the council and PL. PL uses a trading name of ‘Aragon’ in relation to the services provided under the OSA. A decision was taken by Cabinet on 11 March 2025 to terminate the council’s OSA with Peterborough Limited and the in-sourcing of those services on or before 31 March 2026 (KEY/10MAR25/01, linked below). Peterborough Limited

15 13 November 2025 Item 7 Sustainable Future City Council Scrutiny Committee (and/or its subsidiary Peterborough Culture, Heritage, Learning and Leisure Ltd (PCHLL)) continue to provide other services to the council, including culture and leisure services.

2.2The Cabinet decision taken on 11 March 2025, detailed above, included the following commitment: to support the smooth transition of services, officers will report progress regularly to the council’s Shareholder Cabinet Committee. This will support officers by guiding the implementation process and reviewing and commenting on progress as and when appropriate. One such progress report has been made to Shareholder Cabinet Committee (linked below) and further such reports will be provided in due course.

2.3Implementation date. The Cabinet decision taken on 11 March 2025, detailed above, committed to ‘the in-sourcing (or cessation) of the services thereunder on or before 31 March 2026. Whilst every effort has been made to implement this decision as soon as possible, it is clear that the process is complex and it has not been possible to bring this date forward. A ‘go-live’ date of 1 April 2026 has now been communicated to the programme team and staff at Peterborough Limited/Aragon. Although the project involves a wide range of workstreams, the focus is that the project delivers the following four objectives: • Deliver services legally; • Deliver services safely; • Ensuring staff are paid, and all of the wider details that entails; • Ensure there is no disruption to frontline services.

2.4Leadership Team. Following the council’s decision to bring OSA/Aragon services in-house, there have been changes within Peterborough Limited’s leadership team. Several senior post holders have left the organisation, including the Director of Operations, the Managing Director, and the Director of Business and Strategy. To ensure stability and continuity, the company has appointed an Interim Chief Operating Officer who will guide Peterborough Limited through this transition and support the ongoing delivery of PCHLL services.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Peterborough Limited (OSA) integration Progress ReportReport 267 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

8 of 19 attended
PG
Councillor Polly GeraghtyChair, present
SB
Councillor Simon BarkhamVice Chair, absent
AD
Councillor Alan DowsonCommittee Member, present
GE
Councillor Gavin ElseyCommittee Member, expected
QF
Councillor Qaiser FaridCommittee Member, present
SH
Councillor Sarah HillierCommittee Member, present
JH
Councillor John HowardCommittee Member, present
AI
Councillor Amjad IqbalCommittee Member, expected
AJ
Councillor Alison JonesCommittee Member, present
JM
Councillor Jason McNallyCommittee Member, present
RR
Councillor Rylan RayCommittee Member, expected
PC
Parish Councillor Alex BowerbanksCo-Optee, present

All 19 on the meeting page

On this subject at Peterborough

Search all
  1. Peterborough Limited (OSA) integration Progress ReportThis decision
  2. Reserved Matters Peterborough LimitedAgreed
  3. Peterborough Limited Reserved Matters - Grazing Licence relating to the area known as land adjacent to Flag Fen, Northey Road, PeterboroughApproved
  4. Peterborough Limited – Reserved Matters - RecruitmentAgreed
  5. Structural Change – TUPE Transfer of Peterborough Limited Staff into the Place and Economy DirectorateDecided

More from Peterborough Sustainable Future City Council Scrutiny Committee

All decisions
MeetingDecisionOutcome
23 Jul 2026 Minutes of the previous Committee meeting held on 19 March 2026The minutes of the meeting held on 19 March 2026 were agreed as an accurate record. Agreed Open
23 Jul 2026 Appointment of Co-opted Members 2026-2027The Sustainable Future City Council Scrutiny Committee: Appointed Parish Councillor Henry Clark as an Independent Co-... Decided Open
23 Jul 2026 Forward Plan of Executive DecisionsThe Sustainable Future City Council Scrutiny Committee: Considered and noted the current . The new Forward Plan would... Noted Open
23 Jul 2026 Work Programme 2026-2027Members noted the Scrutiny Committee work programme as it stands, with the understanding that it would be updated fol... Noted Open
12 Jan 2026 Exclusion of Public and PressRESOLVED that the press and public be excluded from part or all of the meeting in order to discuss sensitive informat... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies