Cabinet, Tuesday 25 August 2026 at 2.00pm

Approval to deliver the construction phase of the sports quarter leisure development

Approved Executive 3 papers

AI summaryPeterborough Cabinet approves acceptance of £20m government grant and recommends extra £5.9m to push sports quarter leisure centre build cost envelope to £43m, with construction aimed to finish by September 2028.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedConstruction phase go-ahead for Sports Quarter leisure centre
MoneyUp to £43,000,000 total budget£20m grant plus up to £5.9m extra council budget
What happens nextFull Council to consider extra budgetPlus planning decision expected October 2026
Who it affectsPeterborough residents and ARU PeterboroughNew 8-lane pool, teaching pool, jobs and skills

What was decided

Cabinet approved acceptance of a £20,000,000 Growth Mission Fund grant from the Department of Business and Trade for the Sports Quarter leisure development. Report P8

Cabinet recommended Full Council approve an additional budget and contingency of up to £5.9 million for 2026/27, lifting the overall envelope to £43 million, with £23 million funded by borrowing. Report 7.2

Subject to Full Council approval of the extra budget and planning consent, Cabinet authorised award of contracts to Alliance Leisure Services Limited for early works, main construction and design and build development management, and delegated authority to finalise deals with ALS and M Group Highways Limited and to procure an operator. Report 2.15, 2.17

Why

The latest cost assessment at RIBA stage 3 came in at £40,031,000 including a 7% contingency, above the £37.1m Full Council approved in February 2026, mainly because of extra highway works and construction market volatility. Report 2.7, 2.8, 2.9, 7.1

Officers wanted to keep the programme on track for a September 2028 opening, which requires an early works contract in October 2026 and main construction starting in early 2027. Report 2.11, 2.12, 2.15

Officers argued the chosen UK Leisure Framework route with ALS as delivery partner and Willmott Dixon as Principal Contractor is the quickest compliant delivery method, with cancellation inadvisable given £2.5m already spent on design. Report 2.6, 3.2, 3.3

What happens next

Seek Full Council approval of the £5.9m uplift and the associated borrowing changes at the next meeting. Report 7.2

Enter into the grant agreement with the Department of Business and Trade, expected on non-negotiable terms. Report 2.20, P16

Run a competitive procurement in 2027 to appoint an operator for the new centre, aiming for about 12 months to award with mobilisation before the September 2028 opening. Report 2.17, 2.18

The money

  • £20,000,000 Growth Mission Fund grant from Department of Business and Trade Report P8
  • £5.9 million Additional budget and contingency to recommend to Full Council for 2026/27 Report 7.2
  • £43 million Proposed total project budget envelope including additional contingency Report 2.10, 7.2
  • £37,100,000 Original budget approved by Full Council in February 2026 Report 2.7, 7.1
  • £38,240,000 RIBA stage 2 cost plan received March 2026, including 8.5% contingency Report 2.7
  • £40,031,000 RIBA stage 3 updated cost assessment, including 7% contingency of £2,515,000 Report 2.8, 7.1
  • £40.135m Council's overall budget after adding statutory fees, technical support and contingencies Report 7.1
  • £5,462,000 Value assigned by Willmott Dixon to high and moderate project risks Report 2.10
  • £23m Amount of the £43m envelope that would be funded by borrowing Report 7.2
  • £1.635m Maximum estimated annual revenue cost of the borrowing Report 7.2
  • £0.420m Currently unbudgeted revenue cost linked to the £5.9m capital uplift Report 7.2
  • £2,500,000 Estimated design spend by end of RIBA 4 already invested by the Council Report 3.3
  • £99,000 PV surplus identified to add more rooftop solar on the building Report 5.2

Options considered

  • Chosen: Delivery Partner model via UK Leisure Framework with ALS (chosen). Compliant procurement with the quickest route and single point of accountability, keeps programme on track for September 2028 Report 3.1, 3.2, 2.6
  • Rejected: Multi-disciplinary design team and contractor via mini competition on a framework. Already considered previously and not the preferred route Report 3.1
  • Rejected: Traditional tender for both design team and contractor. Already considered previously and not the preferred route Report 3.1
  • Rejected: Two-stage design and build contract, contractor led. Already considered previously and not the preferred route Report 3.1
  • Rejected: Cancel the project. Unadvisable because the project is fully funded and the Council has already spent around £2.5m on design Report 3.3

Implications

  • Financial: Borrowing of £23m is built into the £43m envelope, with a maximum £1.635m annual revenue cost of which £0.420m is unbudgeted, not expected to hit the 2026/27 revenue budget. Report 7.2
  • Legal: Council has a discretionary power to provide indoor recreational facilities under section 19 of the Local Government (Miscellaneous) Act 1976, and the contract was procured in line with the Public Contracts Regulations 2015.
  • Equalities: Design follows industry and British Standards with accessibility embedded throughout to ensure the centre is inclusive for all users; key user groups were engaged. Report 9.1, 9.2
  • Climate: Building will use electric air source heat pumps with no direct fossil fuel use; expected annual electricity use is 1,673 MWh and embodied carbon in construction is estimated at 4,688 to 5,518 tonnes CO2e. Report 5.2
  • Climate: Rooftop solar panels will be installed, with an extra £99,000 of PV surplus earmarked to expand the on-site generation. Report 5.2
  • Risk: High and moderate risks are valued at £5,462,000 and the RIBA 3 contingency of £2,515,000 is judged sufficient at this stage, with the extra budget envelope covering the gap. Report 2.10, 7.2
  • Legal: Local Government Reorganisation may lead to a client name change and contract rectification, and the new authority will need to consider operator contracts when the current one ends in March 2029. Report 4.1, 4.2
  • Staffing: Social value commitments from the Principal Contractor include apprenticeships, school engagement, care leaver mentoring, local employment opportunities and use of local contractors where value allows. Report 5.3, P63

Who and where

  • Peterborough residents and leisure centre users Report 5.1, 9.1
  • ARU Peterborough students and staff (course expansion and attractiveness of the university) Report 5.1
  • Construction trainees, apprentices and care leavers engaged through social value initiatives Report 5.3, P63
  • Local contractors and employees where good value can be offered Report 5.3, P63
  • The new unitary authority taking over services, which will need to re-let the operator contract from March 2029 Report 4.1, 4.2

Timeline

  • January 2022: ALS appointed to UK Leisure Framework following competitive procurement Report 2.5
  • 20 February 2026: Green Book business case submitted to Government Report 2.3
  • 25 February 2026: Full Council approved £37.1m project budget Report 2.4, 2.7
  • March 2026: RIBA stage 2 cost plan received at £38,240,000 Report 2.7
  • 9 March 2026: RIBA stage 3 commenced Report 2.8
  • 12 May 2026: Internal Property Board consulted Report 6.1
  • 19 May 2026: Meet the Design Team public event, 10am to 7pm Report 6.3
  • 29 June 2026: Sports Quarter Board consulted Report 6.1
  • 22 July 2026: Economy, Inclusive Growth and Environment Scrutiny Committee invited to share views Report 6.4
  • 24 July 2026: Planning application submitted Report 2.13, P10
  • August 2026: Care leaver employment, skills and mentoring initiative to commence Report P63
  • 11 August 2026: Corporate Leadership Team consulted Report 6.2
  • 12 August 2026: Cabinet Policy Forum consulted Report 6.2
  • 25 August 2026: Cabinet decision taken to approve construction phase and recommend extra budget Report P1
  • October 2026: Planning application expected to be determined; early works contract targeted for entry Report 2.13, 2.11, P11
  • December 2026: RIBA stage 4 expected to conclude with fixed cost Report 2.14
  • Early 2027: Main construction contract expected to commence Report 2.15, P13
  • 2027: Competitive procurement for leisure centre operator to run for around 12 months Report 2.17
  • September 2028: Target opening of the new leisure facility Report 2.11, 2.17
  • March 2029: Current operator contract expires; new authority will need to consider options Report 4.2

Plain English for the jargon

  • DMA (Development Management Agreement): A contract under which a development manager oversees and coordinates design and build of a project on behalf of the client.
  • RIBA stages: The Royal Institute of British Architects' work stages that a building project moves through, from concept (stage 2) to detailed design and construction.
  • Green Book business case: A UK government business case using the five-case model to appraise options, costs, benefits and risks for public investment.
  • Growth Mission Fund: A UK government fund announced in the spending review, administered by the Department for Business and Trade, providing external grant funding to growth-focused projects.
  • S151 Officer: The local authority officer with statutory responsibility for the proper administration of its financial affairs.
  • LGR (Local Government Reorganisation): The process of restructuring local councils, which here is expected to create a new unitary authority for Peterborough.
  • UK Leisure Framework: A compliant procurement framework used to appoint leisure development partners and contractors.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item10

Resolved

Cabinet unanimously RESOLVED to: 1. Approve acceptance and use of the £20,000,000 grant from the Department of Business and Trade for this project. 2. Delegate authority to the Executive Director for Place and Economy in consultation with the Director of Legal and Governance, Executive Director – Corporate Services S151 Officer and Cabinet Member for Communities and Public Safety to enter into the Grant Agreement with the Department of Business and Trade. 3. Recommend to Full Council to approve an additional budget and contingency of up to £5.9 million to the Capital Programme in 2026/27 increasing the overall budget envelope to £43 million, including any associated treasury management (borrowing) changes required. 4. Subject to Full Council approving the additional budget and planning permission being granted, to authorise the award of contracts to Alliance Leisure Services Limited for the provision of early works, the main construction contract and design and build development management services within the approved budget envelope 5. Delegate authority to the Executive Director for Place and Economy in consultation with the Director of Legal and Governance and Cabinet Member for Communities and Public Safety to enter into the necessary legal agreement(s) with Alliance Leisure Services Limited and M Group Highways Limited under the Council’s Highways Services Contract relating to the recommendations set out in this report. 6. Delegate authority to the Executive Director for Place and Economy in consultation with the Director of Corporate Services, S151 Officer, Monitoring Officer and Cabinet Member for Communities and Public Safety to approve any variations required to the contracts with Alliance Leisure Services Limited and M Group Highways Limited, and to manage cost variations and the project contingency spend. 7. Delegate authority to the Executive Director for Place and Economy in consultation with the Director for Corporate Services, S151 Officer, Monitoring Officer and Cabinet Member for Communities and Public Safety to procure an operator for the Council’s leisure centre provision and award a contract, subject to approval by legal, finance and procurement services. 8. Note the Green Book business case outcome at para 2.8 and revised financial implications set out within this report.
Word for word from the decision Peterborough published for this meeting. Source: democracy.peterborough.gov.uk

Follow this further

Built from Peterborough's papers

What the report saysPro

Report to Cabinet

Agenda Item 10 25 August 2026 Cabinet

Development Management Agreements to deliver the new Sports Quarter Leisure Development

Report author: Ian Phillips, Head of Communities and Chris Pike, Principal Development Surveyor Responsible Director: Adrian Chapman, Executive Director for Place and Economy Cabinet Member(s) Councillor Zameer Ali – Cabinet Member for responsible: Communities and Public Safety

Key Decision: Yes - I033837

Exempt: Partially exempt

Exemption Paragraph: Exemption Paragraphs3 Information relating to the financial or business affairs of any particular person (including the authority holding that information).

There is an Exempt Annex to this report which is not for publication in accordance with Paragraph 3 of Schedule 12A of Part 1 to the Local Government Act 1972 because it relates to financial and business affairs of the Council. The information contained in this Exempt Annex should not be disclosed because the information may prejudice the commercial interests of other parties involved. Executive Summary:

The report seeks Cabinet approval for Peterborough City Council to accept a £20 million Growth Mission Fund grant from the Department for Business and Trade (DBT) and to enter into two Development Management Agreements (DMA) with Alliance Leisure Services Limited (ALS) to deliver the Sports Quarter leisure development, including early works and main construction.

The project will provide a new leisure facility, including an eight-lane 25 metre swimming pool and teaching pool. It supports the council’s priorities for economic growth, health and wellbeing, skills development and community investment.

Since Full Council approved the £37.1 million budget in February 2026, the project has progressed through RIBA stages 2 and 3, with planning submitted on 24 July 2026. The latest cost estimate is set out within Section 7 of this report.

To maintain the programme for completion by the end of Summer 2028, approval is sought to enter into the necessary legal documentation with ALS for the early

375 25 August 2026 Cabinet

works in October 2026 ahead of the main construction works commencing in early 2027.

ALS has been appointed through the UK Leisure Framework and will manage the build process through the appointment of Willmott Dixon as the Principal Contractor, providing a compliant, efficient delivery route and a single point of accountability.

The project offers significant benefits, including improved leisure provision, health & wellbeing, job creation, support for ARU Peterborough’s growth, and wider regeneration outcomes.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Site Plan and ImagesAppendix 1 1.5 MB Download
PDF
Supporting InformationAppendix 2 217 KB Download
PDF
Approval to deliver the construction phase of the sports quarter leisure developmentReport 214 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

11 of 14 attended
DS
Councillor Dr Shabina Qayyum Leader of the CouncilChair, present
NB
Councillor Neil Boyce Deputy Leader and Cabinet Member for Adult ServicesVice Chair, present
ZA
Councillor Zameer Ali Cabinet Member for Communities and Public SafetyCommittee Member, present
KC
Councillor Katy Cole Cabinet Member for Children and Young PeopleCommittee Member, present
AE
Councillor Angus Ellis Cabinet Member for TransportCommittee Member, present
CH
Councillor Christian Hogg Cabinet Member for Regulatory Services and EnforcementCommittee Member, present
NA
Councillor Numan Ali Iqbal Cabinet Member for Growth and RegenerationCommittee Member, present
MJ
Councillor Mohammed Jamil Cabinet Member for Finance & Corporate GovernanceCommittee Member, present
AS
Councillor Ann Shaheed Cabinet Member for Public Health, Homelessness and PovertyCommittee Member, present
CW
Councillor Chris WigginCommittee Member, expected
JS
Councillor Jade SeagerAdvisory Member, present
KT
Councillor Kevin TigheAdvisory Member, present

All 14 on the meeting page

More from Peterborough Cabinet

All decisions
MeetingDecisionOutcome
25 Aug 2026 Peterborough Local Plan Proposed Submission Version - Key/06APR26/01Cabinet unanimously RESOLVED to: 1. Approve the Proposed Submission (‘Publication Draft’) Local Plan as attached at A... Approved Open
25 Aug 2026 Youth Guarantee TrailblazerCabinet unanimously RESOLVED to: 1. Approve acceptance of £600,000 grant funding from the Cambridgeshire and Peterbor... Approved Open
25 Aug 2026 Care and Repair - Cabinet Report for a New Open Framework for the Delivery of Disabled Facilities Grants (DFG), Minor and Major Home Adaptations, and the Provision of Aids and Adaptations under the Care Act 2014Cabinet unanimously RESOLVED to: (1) Approve the award of framework agreements under the new Care and Repair Open Fra... Approved Open
25 Aug 2026 Goods Shed (Fletton Quays) DisposalCabinet unanimously RESOLVED to: 1. Authorise the disposal of the Goods Shed on the terms set out in Exempt Annex 2 o... Agreed Open
25 Aug 2026 Medesham Homes Financial Statements 2025/26Cabinet unanimously RESOLVED to approve and ratify the Shareholder Cabinet Committee’s recommendation to delegate aut... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies