Resolved that – (1) the report is noted; (2) approval is given to prudential borrowing being sought from Plymouth City Council to meet balancing funding required for additional works arising from the capital project totaling £71,125 through annual repayment by the joint committee with effect from 2010-11; (3) approval is given to prudential borrowing being sought from Plymouth City Council to meet forecast cost of fitting out new facilities of £53,500 through annual repayment by the joint committee with effect from 2010-11.
Word for word from the decision Plymouth published for this meeting.Source: democracy.plymouth.gov.uk
Executive Summary: This report presents an update on the financial position of the Joint Committee for financial year 2009/10.
Corporate Plan 2009-2012 - Plymouth City Council: Corporate Improvement Priority 6: widening cultural and leisure opportunities Corporate Improvement Priority 14: value for money/effective long term budget/asset management.
Cornwall Council: (to be confirmed)
Implications for Medium Term Financial Plan and Resource Implications: Including finance, human, IT and land The overall effect of the variations against the revenue budget listed in the report has identified a further funding requirement in 2009/10. Ongoing additional costs have arisen as a result of the Job Evaluation exercise undertaken by Plymouth City Council, together with additional staffing requirements for the new trading operations. There are further costs coming through for utilities, a need to expand the marketing budget and produce new signage as a result of branding exercise. The level of reserves will also affect the level of funding available in future years and therefore, also the implications for the medium Term Financial Plan.
Financial Update 31~7~09(09~10 monitoring).DOC Other Implications: eg Section 17 Community Safety, Health and Safety, Risk Management, Equalities Impact Assessment, etc.
None.
Recommendations and Reasons for Recommended action:
1. It is recommended that:
(a) The report be noted. (b) To approve Prudential borrowing being sought from Plymouth City Council to meet balancing funding required for additional works arising from the capital project totalling £132,725 through annual repayment by the Joint Committee with effect from 2010/11. (c) To approve Prudential borrowing being sought from Plymouth City Council to meet forecast cost of fitting out new facilities of £177,500 through annual repayment by the Joint Committee with effect from 2010/11.
Alternative Options Considered & reasons for recommended action:
N/A.
Background Papers: Mount Edgcumbe Revenue Budget Financial update – March 2009.
Sign Off
Fin Leg HR AM IT Originating SMT Member
Financial Update 31~7~09(09~10 monitoring).DOC MOUNT EDGCUMBE JOINT COMMITTEE
Mount Edgcumbe Joint Committee – 31st July 2009
REVENUE AND CAPITAL BUDGET MONITORING
1. INTRODUCTION
1.1The purpose of this report is to present to the Joint Committee the latest Mount Edgcumbe revenue and capital monitoring position for 2009/10 detailing significant variations.
2. 2009/10 REVENUE MONITORING
2.1The Joint Committee’s revenue forecast for 2009/10 is projecting a shortfall of £196,000 broken down as follows: £ Job Evaluation 90,000 Additional staffing 38,000 Loss of funding Museum Development Officer 20,000 Additional Marketing budget 18,000 New signage 16,000 Inflationary increase 2009/10 budgets 13,000 Increase Utility tariff 12,000 Branding 10,000 Loss of income (facility inhouse)* 8,000 Increase insurance premium 7,000 Cremyll Ferry rent free period 5,000 Orangery fitting out 4,000 Total expenditure 241,000
Offset by income generated through soft launch (45,000) . Net deficit 196,000
2.2Income generation to the park for the first three months has been strong and funding options to meet this shortfall are currently being investigated by officers of the Constituent Authorities.
3. 2009/10 CAPITAL MONITORING
3.1Approval has been previously given by the Joint Committee for prudential borrowing to be sought from Plymouth City Council for the following three schemes:
Replacement Windows and heating at barrow park flats ~ £52,400
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.