Resolved
Agreed that consideration of the report be deferred to the next meeting when the action plan would be more fully completed to include details of responsible officers, details of progress made and implementation dates.
Audit and Governance Committee agreed this item on Friday 23 July 2010. Below is the council's own wording, with the papers it was decided on.
Resolved
Agreed that consideration of the report be deferred to the next meeting when the action plan would be more fully completed to include details of responsible officers, details of progress made and implementation dates.
A Action Plan
© 2010 Grant Thornton UK LLP. All rights reserved Plymouth City Council - Project Management Arrangements 1
1 Introduction and background
1.1Sound performance management and reporting arrangements are integral to the proper management of a business and are an essential contribution to ensuring proper use of resources and the achievement of objectives. Performance management information is fundamental to ensure that this informs decision making, business planning, budget setting, and strategic development within an organisation.
1.2Performance management may have a number of components, including monitoring progress against corporate objectives, budgetary control and the arrangements in place for managing the workforce. While the Council recognises that it is everyone's job to engage in performance management, it is for the Council's leadership to lead the way in driving improvements in the performance culture, and to ensure that the performance framework is applied at all levels.
1.3The Council has been engaged in a continuous development of its performance management arrangements over the last three to four years and previous reviews of local arrangements, including work undertaken by the Audit Commission, have identified that corporate arrangements for managing and reporting on key targets and priorities have been developing well and that performance management has now become much more a part of the corporate culture.
1.4We recognise the significant input made across the Council into developing its performance management arrangements. Our review has focused on the development of the corporate performance and finance reporting arrangements and some of the processes that support that. In completing our review, we have undertaken interviews with key senior staff , reviewed background documentation provided to us and also reviewed some of the data on the corporate management information system, ePerform.
© 2010 Grant Thornton UK LLP. All rights reserved Plymouth City Council - Project Management Arrangements 2
2 Key findings
Introduction
2.1The Council's Corporate Plan 2009-12 is the focal point for its strategic direction and focuses on, amongst other issues, an assessment of its current performance and its three-year corporate priorities. The Plan also highlights the processes by which the Council will monitor its progress, including project and programme management.
2.2The Council continues to develop its performance management arrangements, with a particular focus on the 14 corporate improvement priorities (CIPs) and the detailed indicators that underpin them, whilst recognising other key influences on performance, for example, the effect of the economic situation and the demands of the local health inequalities agenda.
2.3The CIPs are broad statements of intention (for example, CIP 4 is entitled "reducing inequalities between communities") and underpinning each CIP is one or more key improvement areas and, for each improvement area, one or more key performance measures (which may be either national or local indicators) as well as key actions and "milestones" (key delivery points within each project, and on which the success of each project is dependent) . The Plan also includes the Local Area Agreement (LAA) indicators.
2.4The CIPs are allocated across the service departments and each CIP is led by a head of service who has principal responsibility for its delivery. Currently, Children and Young People's Services has responsibility for three CIPs, Community Services has four, Development and Regeneration has three, Corporate Support has three and the Chief Executive's office has one.
Corporate performance management arrangements
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
EXTERNAL AUDIT: PERFORMANCE MANAGEMENT ARRANGEMENTSReport | 126 KB | DownloadRead as text |
Follow Audit and Governance Committee at Plymouth and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 14 Jan 2025 | Committee Self-AssessmentIt was agreed that the terms of reference for the Committee would be shared along with the link to the self-assessment. | Agreed | Open |
| 28 Nov 2022 | Tracking DecisionsIt was agreed that a report would be submitted to the Audit and Governance Committee detailing work undertaken by int... | Agreed | Open |
| 28 Nov 2022 | Exempt BusinessAgreed that under Section 100(4) of the Local Government Act 1972, to exclude the press and public from the meeting f... | Agreed | Open |
| 29 Nov 2021 | Tracking DecisionsIt was agreed that the Chair and Vice Chair would discuss the issues surrounding the public availability of the Grant... | Agreed | Open |
| 11 Oct 2021 | Appointment of Chair and Vice ChairIt was agreed that Councillor Bingley is appointed as Chair, and Councillor Evans is appointed as Vice Chair for this... | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.