Resolved
Agreed that – 1. the Risk Management Annual report is noted. 2. the Audit Committee will receive a briefing note on why the vehicle scissor lift was not replaced sooner.
Audit and Governance Committee agreed this item on Thursday 21 June 2012. Below is the council's own wording, with the papers it was decided on.
Resolved
Agreed that – 1. the Risk Management Annual report is noted. 2. the Audit Committee will receive a briefing note on why the vehicle scissor lift was not replaced sooner.
This report summarises the work carried out during 2011/12 to develop the Council’s approach to risk management and covers: • Corporate and Operational Risk Management Groups • Risk Registers • Challenge Reports and Business Planning • Annual Governance Statement • Risk Management and the Competency Framework • Partnerships Governance • Intranet Risk Management Guidance • Information Lead Officer Group (ILOG) • ALARM/Cipfa Benchmarking Club 2012 • Risk Champion Training • Review of Major Incidents/Business Continuity • Focus for 2012/2013
Corporate Plan 2012-2015:
Maintaining sound systems of internal control and risk management enables the Council to monitor and review the key risks that may prevent it from achieving its corporate and service objectives.
Implications for Medium Term Financial Plan and Resource Implications: Including finance, human, IT and land
None arising specifically from this report.
Other Implications: e.g. Child Poverty, Community Safety, Health and Safety, Risk Management and Equality, Diversity and Community Cohesion: The Risk Management Strategy specifically supports the Council’s overall governance arrangements.
Recommendations & Reasons for recommended action:
The Audit Committee is recommended to: • Note the Annual Report.
Alternative options considered and reasons for recommended action:
Not applicable.
Background papers: Strategic and Operational Risk Registers Previous Audit Committee Reports
Sign off:
Fin DJN1 Leg LT14 HR Corp IT Strat 213.0 937 Prop Proc 07 Originating SMT Member: Tim Howes, Asst Director, Democracy and Governance Have you consulted the Cabinet Member(s) named on the report? Yes 1. Introduction
1.1This report summarises the work carried out during 2011/12 to further develop the Council’s approach to risk management.
1.2The review covers:
• Corporate and Operational Risk Management Groups • Risk Registers • Challenge Reports and Business Planning • Annual Governance Statement • Risk Management and the Competency Framework • Partnerships Governance • Intranet Risk Management Guidance • Information Lead Officer Group (ILOG) • ALARM/Cipfa Benchmarking Club 2012 • Risk Champion Training • Review of Major Incidents/Business Continuity • Focus for 2012/13
2. Corporate and Operational Risk Management Groups
2.1Members will be aware that the risk management strategy involves a two tier approach.
2.2The Corporate Management Team (CMT) acts as the Corporate Risk Management Group (CRMG) with responsibility for the Strategic Risk Register and the overall risk management strategy.
2.3CRMG has met four times in the past twelve months to receive and approve monitoring reports and to consider strategic risk issues prior to Cabinet Planning giving approval for reports to be presented to Audit Committee.
2.4Directors have engaged fully in the risk management process in taking ownership of the Strategic Risk Register both formally at CRMG meetings and throughout the year in proposing amendments to the Register in line with changing circumstances and priorities for the Council.
2.5As a result the Strategic Register has now been through 19 revisions since it was first drawn up nine years ago which is good evidence of the dynamic nature of the risk management process and its embeddedness at a strategic level.
2.6Portfolio-holders at meetings of Cabinet Planning have also been engaged in considering and challenging risk management monitoring reports.
2.7Matters of day to day operational risk management are the responsibility of the Operational Risk Management Group (ORMG) which is chaired by the Head of Corporate Risk & Insurance and comprises Risk Champions from each Directorate and/or Service.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
RISK MANAGEMENT: ANNUAL REPORTReport | 93 KB | DownloadRead as text |
Follow Audit and Governance Committee at Plymouth and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 14 Jan 2025 | Committee Self-AssessmentIt was agreed that the terms of reference for the Committee would be shared along with the link to the self-assessment. | Agreed | Open |
| 28 Nov 2022 | Tracking DecisionsIt was agreed that a report would be submitted to the Audit and Governance Committee detailing work undertaken by int... | Agreed | Open |
| 28 Nov 2022 | Exempt BusinessAgreed that under Section 100(4) of the Local Government Act 1972, to exclude the press and public from the meeting f... | Agreed | Open |
| 29 Nov 2021 | Tracking DecisionsIt was agreed that the Chair and Vice Chair would discuss the issues surrounding the public availability of the Grant... | Agreed | Open |
| 11 Oct 2021 | Appointment of Chair and Vice ChairIt was agreed that Councillor Bingley is appointed as Chair, and Councillor Evans is appointed as Vice Chair for this... | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.