Agreed that – (1) Philip Heseltine, Head of Transport Strategy and Julie Wileman , Major Schemes Project Officer, would organise a meeting with members from the Sutton and Mount Gould ward in order that local issues could be communicated; (2) Transport Officers are requested to review the traffic arrangements at Heles Terrace to improve and attempt to avoid issues of congestion; (3) Transport Officers are requested to investigate ways to consult with the wider public and as to how councillors can assist in gathering intelligence and feeding through to the Transport Department; (4) a future report is submitted to the panel early in 2013 following the evaluation programme.
Word for word from the decision Plymouth published for this meeting.Source: democracy.plymouth.gov.uk
Report to Growth and Prosperity Overview and Scrutiny Panel
CITY OF PLYMOUTH
Subject: East End Transport Scheme: Monitoring and Evaluation
Committee: Growth & Prosperity Overview & Scrutiny Panel Date: 1 August 2012 Cabinet Member: Councillor Coker, Cabinet Member for Transport CMT Member: Director for Place Author: Juli Wileman, Major Schemes Project Manager Contact: Tel: 01752 307703 e-mail:. [email protected] Ref:
Key Decision: No Part: Part 1
Introduction The anticipated outcomes of the East End Transport Scheme (EETS), which opened on 1st November 2011, are as follows:
• Improved journey times for all traffic • Improved bus journey times relative to car journey times • Improved bus service reliability and punctuality • Increase in number of cyclists • Improved air quality • Reduced traffic on inappropriate roads • Improved public realm
Monitoring Programme
Prior to construction commencing in June 2010 a number of traffic surveys were undertaken to understand the pre-scheme conditions. Surveys to understand the post-scheme conditions, and to determine whether the anticipated outcomes have been achieved, should be taken a year after scheme opening, to allow traffic patterns to settle down. However, due to the proposed works to the Finnigan Road/Laira Bridge Road junction this autumn, it is proposed to undertake the traffic surveys in January 2013. Pedestrian counts and off-highway cycle counts, however, will be undertaken in October/November 2012.
It is also proposed to undertake a sample survey of bus drivers, passengers, local residents and businesses to understand their views of how the scheme is working.
Anecdotal reports are that the scheme is performing well. A month after scheme opening we received some feedback from Plymouth Citybus that they had experienced a reduction in late running bus services. They stated that “It would be fair to say that the scheme has done what is set out to do and has reduced the congestion through the East End and has had a positive effect on reliability for our services”.
A final report could be provided to the Growth and Prosperity Scrutiny in early 2013, following analysis of the traffic surveys.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Growth and Prosperity Overview and Scrutiny Panel at Plymouth and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.