Resolved
Agreed that – 1. the Value for Money report is noted. 2. a fuller Value for Money report on outstanding actions to come back to committee in December. (This item was moved up the agenda to facilitate good meeting management.)
Audit and Governance Committee agreed this item on Thursday 27 September 2012. Below is the council's own wording, with the papers it was decided on.
Resolved
Agreed that – 1. the Value for Money report is noted. 2. a fuller Value for Money report on outstanding actions to come back to committee in December. (This item was moved up the agenda to facilitate good meeting management.)
Value for Money – Follow up of Recommendations for 2010/11 VFM reviews Plymouth City Council September 2012
Barrie Morris Director T +44 117 305 7708E [email removed]
Geraldine Daly Senior Manager T + 44 0117 305 7784 E [email removed] Background Appendix A details each action plan and the resultant progress made. We have discussed these findings with the Assistant Director of Finance, Efficiencies and Assets. Our 2011/12 Audit Plan details the work that we have needed to complete in order to discharge our statutory responsibilities under the Audit We have noted that four recommendations made on the Procure to Pay Commission Code. As auditors we have to issue an opinion on the project review have yet to be implemented. financial statements for the year ended 31 March 2012 and an opinion on the Council's ability to achieve value for money. Good progress has been made in implementing the majority of recommendations agreed following the Project Management review. All As part of the value for money conclusion work this year, we have bar one have been fully implemented with the remaining recommendation followed up on the key recommendations made as part of the VFM work scheduled to be implemented by the end of September 2012. for 2010/11. Way Forward In 2010/11, we performed detailed reviews on two areas: We recommend that management review the Action Plan agreed following • the Procure to Pay project; and our review of the Procure to Pay process at the Council in 2011/12. We • Project Management in operation across the Council. would suggest that further consideration is given to all outstanding items. Summary of Findings.
We reviewed the action plans for each of these reports and discussed the progress with appropriate officers. We also obtained further evidence where we felt this was necessary. Grant Thornton UK LLP
Chartered Accountants Member firm within Grant Thornton International Ltd Grant Thornton UK LLP is a limited liability partnership registered in England and Wales: No.OC307742. Registered office: Grant Thornton House, Melton Street, Euston Square, London NW1 2EP A list of members is available from our registered office.
Grant Thornton UK LLP is authorised and regulated by the Financial Services Authority for investment business. Plymouth City Council Follow up- VFM Recommendations 2010/11 September 2012
Appendix A – Progress on 2010/11 VFM Recommendations
Procure to Pay
Rec Recommendation Priority Update September 2012 Implemented No. 1 P2P PID The P2P PID should be updated to reflect the revised project Medium Project Board report and Strategy document 1 July 2011 governance arrangements structure. show revised governance arrangements. Within this, category management has been scaled down to encompass a reduced number of areas. July 2012 progress update shows where key decisions are needed, and who by.
Recommendation met.
2 Project manager and work stream leads The Council should ensure that the Medium July 2012 progress update shows that March 2012 roles of P2P project manager and work stream leads should not be assigned to programme manager and theme leads are now the same individual. different people. The new separation of responsibilities occurred in March/April 2012 following the appointment of the new (interim) programme manager in February 2012.
Recommendation met.
3 Structure and governance The project structure and governance Medium Governance arrangements are clear and have July 2011 arrangements need to be re-defined in light of current circumstances, including been redefined following changes in the a Memorandum of Roles and Responsibilities of all key stakeholders involved in category management programme. Quarterly the project. meetings of internal stakeholders are held as end-users of the P2P initiative. No formal memoranda of roles and responsibilities have been devised. The interim programme manager
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
VALUE FOR MONEY REPORTReport | 170 KB | DownloadRead as text |
Follow Audit and Governance Committee at Plymouth and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 14 Jan 2025 | Committee Self-AssessmentIt was agreed that the terms of reference for the Committee would be shared along with the link to the self-assessment. | Agreed | Open |
| 28 Nov 2022 | Tracking DecisionsIt was agreed that a report would be submitted to the Audit and Governance Committee detailing work undertaken by int... | Agreed | Open |
| 28 Nov 2022 | Exempt BusinessAgreed that under Section 100(4) of the Local Government Act 1972, to exclude the press and public from the meeting f... | Agreed | Open |
| 29 Nov 2021 | Tracking DecisionsIt was agreed that the Chair and Vice Chair would discuss the issues surrounding the public availability of the Grant... | Agreed | Open |
| 11 Oct 2021 | Appointment of Chair and Vice ChairIt was agreed that Councillor Bingley is appointed as Chair, and Councillor Evans is appointed as Vice Chair for this... | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.