Resolved
Agreed to request that Councillor Lowry provide further evidence on how Member involvement could be built into the process.
Support Services Overview and Scrutiny Panel agreed this item on Monday 19 November 2012. Below is the council's own wording, with the papers it was decided on.
Resolved
Agreed to request that Councillor Lowry provide further evidence on how Member involvement could be built into the process.
Capital Scheme Approval Process
Initial Project Mandate (IPM) Approval of initial project idea to be progressed to IPP
Initial Project Proposal (IPP) Project added to Projects Under Development (PUD) list
Capital Programme Business Case Project added to Capital (CPBC) Programme
Capital Programme Approval Form Authority to enter contract and (CPAF) proceed with works Initial Project Mandate (IPM)
Initial Project Mandate (IPM) Approval of initial project idea to be progressed to IPP
1st Stage of Process Very little detail but outlines initial proposal for DMT to accept or reject Initial Project Proposal (IPP)
Initial Project Proposal (IPP) Project added to Projects Under Development (PUD) list
2nd Stage of Process If DMT are happy with the proposal then more detail is required for the IPP that is then taken to Capital Delivery Board (CDB) This often gives approval to bid for resources When agreed at CDB it can then be worked up to next stage Capital Programme Business Case (CPBC)
Capital Programme Business Project added to Capital Case (CPBC) Programme
3rd Stage of Process Business Case is much more detailed and gives all details of the scheme or project to be worked up incl detailed funding, cashflow etc. CPBC taken back to CDB and, if approved there, is added to the capital programme awaiting approval at next Cabinet / Full Council No capital spend until CPAF received and approved Capital Programme Approval Form (CPAF)
Capital Programme Approval Authority to enter contract and Form (CPAF) proceed with works
Final Stage of Process Once tender prices have been received then the CPAF is completed and taken back to CDB for approval to start with the project. At this stage the project or scheme is given a capital code and capital expenditure can then be charged against it.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
GOVERNANCE OF THE CAPITAL PROGRAMMEReport | 73 KB | DownloadRead as text |
Follow Support Services Overview and Scrutiny Panel at Plymouth and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 15 Apr 2013 | MINUTESAgreed the minutes of the meeting held on 4 March 2013. | Agreed | Open |
| 15 Apr 2013 | Revenues and benefits performance updateAgreed that the Chair would write a letter to the Revenue and Benefits department thanking staff for their hard work ... | Agreed | Open |
| 4 Mar 2013 | MINUTESAgreed that the minutes of the meeting held on 19 November 2012. | Agreed | Open |
| 4 Mar 2013 | 'the view from you' employee survey resultsAgreed to request the officers to provide the panel with an update on the employee survey results action plan every s... | Agreed | Open |
| 4 Mar 2013 | Social media updateAgreed that the officer explores social media training for members. | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.