Agreed that a copy of the Assistant Director for Planning Services’ report be sent to the City’s Members of Parliament seeking their comments to be reported back to the panel in due course.
Customers and Communities Overview and Scrutiny Panel agreed this item on Wednesday 6 February 2013. Below is the council's own wording, with the papers it was decided on.
Resolved
Agreed that a copy of the Assistant Director for Planning Services’ report be sent to the City’s Members of Parliament seeking their comments to be reported back to the panel in due course.
PLANNING DEPARTMENT Customers & Communities OSP, 6th February 2013 Clause 5 of the Growth and Infrastructure Bill
Introduction
On 18th October 2012 the Growth and Infrastructure Bill was laid before Parliament. It makes provision for promoting growth and facilitating infrastructure. On 21st November 2012 the Growth & Prosperity Overview and Scrutiny Panel considered a report on the Government’s proposed reforms of the planning system. Amongst other matters the panel resolved to ask the Customer and Communities Overview and Scrutiny Panel to review the impact of Clause 5 (modification or discharge of affordable housing requirements secured through Section 106 agreements) in the Growth and Infrastructure Bill, to determine the impact this clause may have on local communities as a result of applicants applying to the local authority for modifications to or the removal of agreed Section106 agreements with respect to affordable housing where an authority fails to make a determination within the specified time or determines that no modification will be made, the applicant may appeal to the Planning Inspectorate.
Growth and Infrastructure Bill
The Bill is currently at Committee Stage in the House of Lords. Clause 5 inserts new Sections 106BA and 106BB into the Town and Country Planning Act 1990. Clause 5 allows for the modification or discharge of affordable housing requirements secured through Section 106 agreements attached to the grant of planning permission. Specifically it:
• Allows a developer to apply to change the affordable housing requirement, for it to be replaced with a different requirement, for it to be completely removed, or, where it is the only obligation, for it to be discharged – S.106BA (1) (2).
• Requires the Local Planning Authority to determine any application made to make the application viable if the cause of unviability was the affordable housing element –S.106BA (1) (3) (a) .
• Prevents any obligation changes being more onerous on the developer – S.106BA (1) (7).
• Requires Local Planning Authorities to have regard to any guidance issued by the Secretary of State – S.106BA (1) (8).
• Requires the Local Planning Authority to determine the application within a period to be prescribed by the Secretary of State – S.106BA (1) (9).
• Allows specifically for appeals to be made on affordable housing obligations only– S.106BB (1)
• Irrespective of what modifications may have been acceptable to the Local Planning Authority, the Secretary of State will determine any appeal as if were the original obligation - S.106BB (2)
Planning Department Briefing Note CONFIDENTIAL In its impact assessment on the Bill the Department for Communities and Local Government indicate that the strategic problem this clause is trying to address is the low levels of housing delivery and the high number of stalled sites. It states that the objective is to “unlock stalled development by allowing and encouraging applicants to renegotiate the level of affordable housing…” (My emphasis). It is envisaged that appeals determined by the Planning Inspectorate under these provisions will be valid for 3 years – thus providing an incentive to build out the development early.
Possible Impacts of Clause 5
Localism and Democracy
Clause 1 of the Growth and Infrastructure Bill, together with other clauses and various other implemented and proposed Government reforms to the planning system, enable greater central control and direction over local decision-making. Clause 1 would remove planning powers from local authorities that the Government declares as poorly performing and Clause 5 would allow by- passing of agreed affordable housing provisions to be determined by unelected Planning Inspectors. Both are inherently undemocratic and therefore fundamentally flawed provisions. The implicit encouragement to developers to renegotiate agreed affordable housing requirements undermines current Core Strategy policy and the targets based on it.
Unintended Delays in Development
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
CLAUSE 5 OF THE GROWTH AND INFRASTRUCTURE BILLReport | 77 KB | DownloadRead as text |
Follow Customers and Communities Overview and Scrutiny Panel at Plymouth and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 3 Apr 2013 | MINUTESAgreed the minutes of the meeting held on 6 February 2013. | Agreed | Open |
| 3 Apr 2013 | Library modernisation task and finish group reportAgreed the report is referred to the Overview and Scrutiny Management Board for approval. | Agreed | Open |
| 6 Feb 2013 | MINUTESAgreed the minutes of the meeting held on 7 November 2012. | Agreed | Open |
| 6 Feb 2013 | Police and crime panel minutesAgreed that – (1) a link to the minutes of the Devon and Cornwall Police and Crime Panel would be circulated to membe... | Agreed | Open |
| 7 Nov 2012 | MINUTESAgreed the minutes of the meeting held on 12 September 2012. | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.