Resolved
Agreed that a briefing on the back up arrangements for the data system to be circulated with the minutes.
Audit and Governance Committee agreed this item on Thursday 13 March 2014. Below is the council's own wording, with the papers it was decided on.
Resolved
Agreed that a briefing on the back up arrangements for the data system to be circulated with the minutes.
Audit Committee Update New Data Centre
Plymouth City Council March 2014
Auditing for achievement Delays at the New Data Centre at Windsor House In response to questions raised at the December 2013 Audit Committee, it was requested that more information regarding delays at the Windsor House Data Centre be reported to members. An overview of key milestones, factors contributing to delays in meeting communicated timelines, and a position statement is provided below.
Chronological Overview
2011 ICT work through a range of potential delivery solutions concluding the implementation will be performed by a third party with dedicated independent project management and minimal input from PCC ICT staff.
Dec 2011 Capital Delivery Board approves £1.3 million investment, project delivery estimated as 9 months.
Apr 2012 Formal procurement process resulted in three companies selected for interview and preferred supplier chosen.
Jul 2012 Supplier submits first draft of technical design.
Aug 2012 Project put on hold to review options and change of scope. ICT Programme Board brings forward the work to replace legacy equipment within the Civic Centre data centre reducing future rework and impact. Total spend increased to £1.6million.
Sept 2012 Data Centre room build started as part of the Corporate Accommodation Strategy building work at Windsor House.
Dec 2012 Backup facility moved to Midland House and Pearl Assurance closed on time to meet savings projections. Data Centre room handed over by contractors late, due to supply issues and water leak.
Jan 2013 Installation of hardware commences on site at Windsor House.
Jan 13 Technical design work, installation and configuration of onwards equipment completed and migrations started. Contributory Factors for Delays Contributory factors impacting upon the ability to deliver new data centre include:
• Unrealistic timelines due to the failure to fully understand the considerable technical complexities at the project outset; • Data Centre build – delays due to water ingress at Windsor; • Low levels of satisfaction around delivery by key suppliers and technical issues leading to rework; • Delays in installation of key links between Civic, Windsor and Midland – problems with permission to close Tavistock Road; • Additional reliance on internal resources in project management, technical solutions, and supplier management; • Issues with filling key project roles due to sickness, service re-structuring, capability and recruitment of suitably skilled staff; • Conflict/contention of key PCC technical resources as a result of running concurrent critical ICT projects – Integration of Public Health, Shared services initiative with PCC/NHS working out of Windsor House, Corporate Accommodation Strategy, and other high priority projects; • Management of the financial constraints; Budget pressures so having to do much of work in-house to keep costs down.
Current Position
The need for the Data Centre is undeniable in both strategic and operational terms. Internal Audit have been reporting on the importance of greater ICT resilience for a number of years and, as services and customer engagment become more reliant on technical business solutions, so the importance of this increases.
Whilst the completion of the new Data Centre has sufferred a number of delays, the project is on course to deliver the required outcomes and will provide the Authority with a more robust and resiliant platform from which its ICT business solutions will be delivered.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
UPDATE ON DATA SYSTEM AT WINDSOR HOUSEReport | 232 KB | DownloadRead as text |
Follow Audit and Governance Committee at Plymouth and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 14 Jan 2025 | Committee Self-AssessmentIt was agreed that the terms of reference for the Committee would be shared along with the link to the self-assessment. | Agreed | Open |
| 28 Nov 2022 | Tracking DecisionsIt was agreed that a report would be submitted to the Audit and Governance Committee detailing work undertaken by int... | Agreed | Open |
| 28 Nov 2022 | Exempt BusinessAgreed that under Section 100(4) of the Local Government Act 1972, to exclude the press and public from the meeting f... | Agreed | Open |
| 29 Nov 2021 | Tracking DecisionsIt was agreed that the Chair and Vice Chair would discuss the issues surrounding the public availability of the Grant... | Agreed | Open |
| 11 Oct 2021 | Appointment of Chair and Vice ChairIt was agreed that Councillor Bingley is appointed as Chair, and Councillor Evans is appointed as Vice Chair for this... | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.