Resolved
Agreed that an update on the Transformation Programme would be provided to the Audit Committee in the future.
Audit and Governance Committee agreed this item on Thursday 26 March 2015. Below is the council's own wording, with the papers it was decided on.
Resolved
Agreed that an update on the Transformation Programme would be provided to the Audit Committee in the future.
This paper provides the Audit Committee with a summary of the management measures that the Portfolio Office is taking to control the risk to the delivery of the financial benefits for Plymouth City Councils transformation.
As described in the Medium Term Financial Plan the Transformation programme represents the proactive plan to bridge the funding gap and to radically change the way that services are delivered in order to further reduce costs in future years.
The challenge set was to achieve the delivery of the following financial benefits over the first three years:
Financial Year 2014 /2015 £6.768M forecasted outcome is £7.180M Financial Year 2015 /2016 £13.611M Financial Year 2016 /2017 £8.818M
Alongside this there are significant non-financial benefits that are aligned to the Programmes and projects but are not covered in this report.
Methodology
The Portfolio Office is implementing a methodology known as Portfolio Management to deliver the transformation programme which is seen as ‘industry best practice’ and is sponsored by the Cabinet Office. This discipline is endorsed and regularly reviewed by The National Audit Office who has highlighted the importance of the methodology and its ability to successfully deliver and realise benefits. This methodology better coordinates investment in programmes and projects improving the management of risk, encouraging collaborative working and by providing accurate, timely information that enhances management decision making and enables Plymouth to:
• Invest in the right programmes and projects • Ensure successful delivery in terms of time, quality, budgets and benefits
The Portfolio Office implements standards and processes which apply to all Projects, Programmes and Portfolio (P3M). In simple terms the Portfolio Office manages a hierarchy of selected programmes and projects (Figure 1) that will deliver benefits to Plymouth City Council. These benefits either have a financial impact, social impact or an efficiency improvement. In general given the main aim of reducing operational cost to support service delivery the programmes will aim to increase income, remove, reduce, avoid or share cost.
Version 0.01 PLYMOUTH CITY COUNCIL
Figure 1: The Hierarchy of Portfolio, Programme and Project Management (P3M)
This hierarchical system allows Projects to be managed by Programmes and Programmes to be managed by The Portfolio. These all link together using common practices, technology, language, rules and processes. This best practice framework is depicted in Figure 2.
Figure 2: Cabinet Office endorsed best practice.
The Portfolio, Programme and Project Maturity Model (P3M3) shown in Figure 2 is a standardised maturity assessment that is available to be purchased through Government procurement frameworks. Thus far in the UK the industry has seen 220 completed and added to the database of standards. The scoring results against each section are on a 1 to 5 sliding scale. Thus far no one in the UK has achieved level 5 maturity. In November 2014 PCC commissioned its first Portfolio, Programme and Project Maturity Model (P3M3) and gained an overall rating of 1.6 which for its embryonic state is a very sound result. A further audit is booked for September 2015 and March 2016 with the aim of achieving levels two and three respectively. If achieved this would place PCC alongside some of the highest in the UK. Interestingly PCC scored 3 on risk management in November 2014.
In summary, Plymouth City Council are following and improving within the industry best practice to achieve the benefits that it needs to achieve. The methodology effectively spreads the risk of non- delivery of financial benefits by breaking it up, making it more achievable and easier to deliver. This removes reliance on a single solution and allows flexibility to achieve the target given that some may under or over achieve.
Governance
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
RISKS OF DELIVERY OF THE TRANSFORMATION PROGRAMMEReport | 116 KB | DownloadRead as text |
Follow Audit and Governance Committee at Plymouth and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 14 Jan 2025 | Committee Self-AssessmentIt was agreed that the terms of reference for the Committee would be shared along with the link to the self-assessment. | Agreed | Open |
| 28 Nov 2022 | Tracking DecisionsIt was agreed that a report would be submitted to the Audit and Governance Committee detailing work undertaken by int... | Agreed | Open |
| 28 Nov 2022 | Exempt BusinessAgreed that under Section 100(4) of the Local Government Act 1972, to exclude the press and public from the meeting f... | Agreed | Open |
| 29 Nov 2021 | Tracking DecisionsIt was agreed that the Chair and Vice Chair would discuss the issues surrounding the public availability of the Grant... | Agreed | Open |
| 11 Oct 2021 | Appointment of Chair and Vice ChairIt was agreed that Councillor Bingley is appointed as Chair, and Councillor Evans is appointed as Vice Chair for this... | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.