Cabinet, Monday 24 August 2026 at 2.00pm

Civic Centre Phase 1 Contract Award and City College Agreement to Lease

Approved Executive 3 papers

AI summaryCabinet awards Morgan Sindall a £6,488,753.43 contract for Phase 1 of Plymouth Civic Centre redevelopment, reprofiles £7.2m of capital funding, agrees a 125-year lease with City College Plymouth, and adds £600,000 to refurbish the Civic Square Pond.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedTo Morgan Sindall and City College Plymouth respectively
Money£6,488,753.43 plus £7.2m reprofile plus £600,000Contract sum, reprofiled borrowing, and pond funding
What happens nextPhase 1 works start September 2026Phase 2 tender around April 2027
Who it affectsNot stated

What was decided

Cabinet awarded Morgan Sindall a £6,488,753.43 contract to deliver Phase 1 works, reprofiled £7.2m of approved capital borrowing, and accepted the risk that the Homes England Gateway Review may not be successfully concluded. Report P40, P46, P47

Cabinet approved a 125-year conditional agreement for lease with City College Plymouth covering the basement, ground floor and first floor for a Blue Green Skills Hub, and added £600,000 to the capital programme for the Civic Square Pond funded by corporate borrowing. Report P62, P63, P71

Why

Officers said the phased approach was needed because the Civic Centre is a Higher Risk Building under the Building Safety Act, and Phase 1 surveys are required to inform the Gateway 2 submission and the Phase 2 tender. Report P1, P30, P31

The report said reprofiling was required so that construction works can start immediately, with the council spending its own money at risk on Phase 1 ahead of the Homes England Gateway Review off-ramp decision. Report P46, P48, P49

What happens next

Phase 1 works, including scaffolding, cladding removal, asbestos removal and demolition, are programmed to start in September 2026, with the Civic Square Pond works aiming to start on site on 7 December 2026 and reach practical completion by 5 April 2027. Report P27, P69

Phase 2 tendering and a fixed price are expected around April 2027, ahead of construction starting in June 2027, subject to BSA Gateway 2 approval and the Homes England Gateway Review. Report P28, P44, P45, P51

The money

  • £7.2m Reprofiled Plymouth City Council capital funding for Phase 1 Report P40, P47, P49
  • £6,488,753.43 Contract sum awarded to Morgan Sindall for Phase 1 works
  • £6.4m Negotiated Phase 1 contract cost Report P40
  • £1.3m Amount Phase 1 negotiated cost exceeded the cost plan, covered by contingency Report P40
  • £600,000 Additional capital programme sum for Civic Square Pond refurbishment, funded by corporate borrowing Report P71
  • £1,553,770 Homes England enabling funding accessible before the Gateway Review Report P43
  • £16,832,508 Remaining Homes England funding not yet accessible Report P44
  • £18.4m Total Homes England funding secured for the project Report P22
  • £10.4m Project-wide contingency, most sitting in Phase 2 Report P53, 5.0
  • £6.5m Possible new funding the council aims to apply for in Q3 2026 Report 5.0
  • £525,000 Estimated capitalised undervalue of the City College Plymouth lease over 25 years Report P64
  • £2million General Disposal Consent undervalue threshold Report P63, P64

Options considered

  • Chosen: Award Phase 1 contract to Morgan Sindall, reprofile funding and proceed. Needed to comply with Building Safety Act, avoid 12 month delay and £2m inflationary risk, and keep tenants and grant funding Report P31, P48
  • Rejected: Do not proceed and stop all works to the Civic Centre. Building would further deteriorate, blight the area, and an application to delist it would be required

Implications

  • Legal: Award and lease must comply with the Council's Constitution, Contract Standing Orders, the Building Safety Act for Higher Risk Buildings, section 123 Local Government Act 1972, the General Disposal Consent (England) 2003, and the Subsidy Control Act 2022. Report P1, P63
  • Financial: The council is committing £7.2m at risk before the Homes England Gateway Review off-ramp decision; if the review fails, the council will have spent £7.2m on enabling works and would have to consider alternative delivery or disposal options. Report P46, P47
  • Risk: Phase 2 carries uncosted risk on war-related fuel and material cost increases, asbestos discovery, structural condition behind cladding, BSA Gateway 2 delays, and supply lead-in periods for the facade. Report P51, P56, P57
  • Staffing: Portfolio risks include reputational damage, the loss of City College Plymouth as tenant, and a change of developer away from Capital & Centric. Report P58
  • Climate: Where possible, including the Civic Centre, existing buildings will be refurbished to reduce the carbon used to provide new homes, and new homes are intended to be connected to the city centre's district heat network. Report P3

Who and where

  • Residents of Plymouth, including future occupants of 144 build-to-rent homes in the Civic Centre tower Report P6, P7
  • City College Plymouth students, with up to 2,000 learners a year across more than 60 courses at the new Blue Green Skills Hub Report P16, P62
  • Capital & Centric, the residential development partner Report P7, P58
  • Homes England as funder and joint venture partner Report P14, P22, P45
  • Morgan Sindall as appointed Phase 1 main contractor Report P33

Timeline

  • June 2025: Phase 0 asbestos removal began, contractor Gwella appointed Report P25
  • 20th March 2026: Revised planning application and listed building consent submitted Report P22
  • 30th July 2026: Planning approval and Listed Building Consent granted Report P22
  • 31 July 2026: Final negotiated offer for Phase 1 received from Morgan Sindall Report P39
  • 24th August 2026: Cabinet decision to award Phase 1 contract and approve City College Plymouth lease
  • September 2026: Phase 1 works programmed to start Report P27
  • 14/09/2026: Civic Square Pond client team appointment Report P69
  • 16/10/2026: Civic Square Pond planning application and Listed Building Consent submission Report P69
  • 30/11/2026: Civic Square Pond contractor appointment Report P69
  • 07/12/2026: Civic Square Pond start on site Report P69
  • c April 2027: Phase 2 fixed price expected Report P51
  • 05/04/2027: Civic Square Pond practical completion Report P69
  • June 2027: Phase 2 works programmed to start Report P28

Plain English for the jargon

  • BSA: Building Safety Act, regime covering Higher Risk Buildings with gateway approvals
  • Higher Risk Building (HRB): A building under the Building Safety Act subject to additional gateway controls during design and construction
  • Gateway 1: Planning submission stage for Higher Risk Buildings, already achieved for the Civic Centre
  • Gateway 2: Pre-construction approval stage requiring a RIBA 4 design and evidence of building regulations and fire safety compliance
  • Homes England Gateway Review: Funding off-ramp decision point where Homes England checks affordability, developer funding and lease terms before releasing further grant
  • RIBA 4: Stage 4 of the Royal Institute of British Architects' design stages, providing the level of detail needed to apply for Gateway 2
  • BTR (Build to Rent): Purpose-built residential accommodation built specifically for the rental market
  • SCF (Southern Construction Framework): Procurement framework used to appoint Morgan Sindall with open-book pricing
  • PCSA (Pre-Construction Services Agreement): Agreement under which a contractor provides early design, pricing and planning support before a main construction contract
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item155

Resolved

Purpose of report The purpose of the report is to award the phase 1 contract for the Civic Centre works and to reprofile the £7.2m of approved corporate borrowing to allow construction works to progress immediately given the requirements of the Building Safety Act (BSA). This will also include the Civic Square pond being moved into the project. To also approve the terms for an agreement to lease of parts of the basement, ground floor and first floor spaces to City College Plymouth (CCP) for a blue green skills hub. Decision Cabinet agreed: To proceed with the phase 1 works to the Civic Centre on the basis of the cost profile set out in this report; To approve the reprofiling of Plymouth City Council (PCC) capital funding of £7.2m to enable the appointment of the Phase 1 contractor whilst remaining within the approved cost envelope; To award a contract to Morgan Sindall to deliver the phase 1 works in the sum of £6,488,753.43; To accept the risks highlighted in this report particularly the Homes England Gateway Review in relation to proceeding to the phase 2 works; To enter a long lease with City College Plymouth (CCP) on the terms set out in this report; To add £600,000 to the capital programme in order to undertake works to the Civic Square Pond as part of the Civic Centre Project. Funded utilising corporate borrowing budgeted within the capital pipeline. Reasons for decision To enable the timely commencement of the approved Civic Centre redevelopment programme and secure delivery of Phase 1 works within the established financial framework, ensuring the building is brought forward for occupation and future phases of the project; To align the timing of capital expenditure with project delivery requirements, allowing the contractor to be appointed and works to commence whilst remaining within the approved cost envelope.; To appoint a suitably qualified and procured contractor capable of delivering the Phase 1 works, providing certainty on programme, cost and delivery arrangements and enabling project mobilisation; To acknowledge and formally accept the identified project risks in order to allow the project to progress, recognising that mitigation measures are in place and that delaying decisions could adversely impact programme delivery, funding and strategic objectives; To establish the legal and operational framework required for City College Plymouth's occupation of the Civic Centre, supporting the viability of the redevelopment project and contributing to the building's long-term use and sustainability; To ensure the Civic Square Pond is refurbished and integrated into the wider Civic Centre regeneration scheme, improving the public realm, addressing asset condition requirements and delivering a cohesive and high-quality environment as part of the overall project. Alternative options considered and rejected Option 1 - Do not proceed and stop all works to the Civic Centre. The Civic Centre would remain undeveloped and would further deteriorate, blighting the surrounding area and detracting from the image of the city. An application could be made to the Secretary of State to delist the building and if successful demolition ...
Word for word from the decision Plymouth published for this meeting. Source: democracy.plymouth.gov.uk

Follow this further

Built from Plymouth's papers

What the report saysPro

Report to Cabinet

OFFICIAL

Cabinet

Date of meeting: 24 August 2026 Title of Report: Civic Centre Phase 1 works contract Award and City College Agreement to Lease Lead Member: Councillor Matt Smith (Cabinet Member for Housing, City Centre Regeneration and Events) Lead Strategic Director: Glenn Caplin-Grey (Strategic Director for Growth) Author: Emma Wilson Contact Email: [email protected] Your Reference: EW260824 Key Decision: Yes Confidentiality: Part I - Official

Purpose of Report The purpose of the report is to award the phase 1 contract for the Civic Centre works and to reprofile the £7.2m of approved corporate borrowing to allow construction works to progress immediately given the requirements of the Building Safety Act (BSA). This will also include the Civic Square pond being moved into the project. To also approve the terms for an agreement to lease of parts of the basement, ground floor and first floor spaces to City College Plymouth (CCP) for a blue green skills hub.

Recommendations and Reasons 1. To proceed with the phase 1 works to the Civic Centre on the basis of the cost profile set out in this report. 2. To approve the reprofiling of Plymouth City Council (PCC) capital funding of £7.2m to enable the appointment of the Phase 1 contractor whilst remaining within the approved cost envelope. 3. To award a contract to Morgan Sindall to deliver the phase 1 works in the sum of £6,488,753.43 4. To accept the risks highlighted in this report particularly the Homes England Gateway Review in relation to proceeding to the phase 2 works. 5. To enter a long lease with City College Plymouth (CCP) on the terms set out in this report 6. To add £600,000 to the capital programme in order to undertake works to the Civic Square Pond as part of the Civic Centre Project. Funded utilising corporate borrowing budgeted within the capital pipeline.

Alternative options considered and rejected Option 1 - Do not proceed and stop all works to the Civic Centre. The Civic Centre would remain undeveloped and would further deteriorate, blighting the surrounding area and detracting from the image of the city. An application could be made to the Secretary of State to delist the building and if OFFICIAL PLYMOUTH CITY COUNCIL successful demolition could be an option. The Secretary of State can only consider a building’s architectural and historic interest when considering an application for de-listing. An application for de- listing may be made because new evidence is available about the lack of special architectural or historic interest of the building, or a material change of circumstances. It is unlikely that a de-listing application would be successful. This option would result in PCC handing back the grant funding secured from Homes England of circa £18.4m. It would not achieve the growth and market-making ambitions of the project.

Option 2- Do not award the phase 1 contract and await a single price to complete the shell and core works in 12 months' time. The BSA requires detailed designs to RIBA 4 to pass through Gateway 2. If a single stage contract was awarded it would take a further 12 months to reach this stage. This would result in a delay to opening the Civic from 2030 to 2031 and likely additional cost price inflation of circa £2m. There is a risk that our future tenants decide not to proceed with the project and fit out as timetables would slip significantly.

Relevance to the Corporate Plan and/or the Plymouth Plan One of the key ambitions of the Plymouth Plan is to be a “Growing City”. The Council’s work with Homes England supports this ambition by unlocking the delivery of stalled housing sites and accelerating the delivery of new homes across the city.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Civic Centre: Cabinet ReportReport 646 KB DownloadRead as text
PDF
Climate AssessmentReport 152 KB Download
PDF
EIAReport 106 KB Download

At this meeting

Whole meeting

Who was there

9 of 10 attended
TE
Councillor Tudor Evans OBEChair, present
JL
Councillor Jemima LaingVice-Chair, present
TB
Councillor Tom Briars-DelveMember, apologies
ML
Councillor Mark LowryMember, present
CP
Councillor Chris PenberthyMember, present
JS
Councillor John StephensMember, present
KT
Councillor Kate TaylorMember, present
TB
Councillor Tess BlightMember, present
ML
Councillor Maria LawsonMember, present
MS
Councillor Matt SmithMember, present

On this subject at Plymouth

Search all
  1. Civic Centre Phase 1 Contract Award and City College Agreement to LeaseThis decision
  2. 26/00424/FUL - Civic Centre, Armada Way, Plymouth, PL1 2AAAgreed
  3. 26/00425/LBC - Civic Centre, Armada Way, Plymouth, PL1 2AAAgreed
  4. City Centre, Homes England and Civic Centre Strategic UpdateAgreed
  5. Civic Centre - 19/00439/FULRefused
  6. Civic Centre - 19/00440/LBCDecided

More from Plymouth Cabinet

All decisions
MeetingDecisionOutcome
14 Sep 2026 Net Zero Action Plan 2026-29Purpose of report The report seeks the approval of the Net Zero Action Plan (NZAP) 2026 - 2029 prior to publication, ... Approved Open
14 Sep 2026 Proposed Public Spaces Protection Order (PSPO) for Alcohol Restriction, linked to Anti-Social Behaviour (ASB) within the CityPurpose of report The purpose of this report is to seek approval to extend the City-Wide Public Spaces Protection Ord... Approved Open
24 Aug 2026 Local Government Association Corporate Peer ChallengePurpose of report The Council commissioned the Local Government Association (LGA) to undertake a Corporate Peer Chall... Decided Open
24 Aug 2026 SEND Sufficiency Strategy and Delivery PlanPurpose of report This report presents the SEND Sufficiency Strategy for Plymouth and seeks approval for the next pha... Approved Open