Resolved
RESOLVED that the recommendations set out in paragraph 4 of the report relating to Appendices A and B be noted.
Governance & Audit & Standards Committee noted this item on Thursday 26 September 2013. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED that the recommendations set out in paragraph 4 of the report relating to Appendices A and B be noted.
The Chartered Institute of Public Finance and Accountancy’s (CIPFA) Prudential Code requires local authorities to calculate prudential indicators before the start of and after each financial year. Those indicators that the Council is required to calculate at the end of the financial year are contained in Appendix A of this report.
The CIPFA Code of Practice on Treasury Management also requires the Section 151 Officer to prepare an annual report on the outturn of the previous year. This information is shown in Appendix B of the report.
The purpose of this paper is to report on:
The outturn Prudential Indicators for 2012/13
The Treasury Management decisions taken over the course of 2012/13
1 3. Background
The Local Government Act 2003 requires local authorities to have regard to the Chartered Institute of Public Finance and Accountancy’s (CIPFA) Prudential Code for Capital Finance in Local Authorities.
The Prudential Code requires local authorities to adopt the CIFPA Code of Practice for Treasury Management in the Public Sector, which the City Council originally adopted in April 1994. Under the Code of Practice for Treasury Management an Annual Policy Statement is prepared setting out the strategy and objectives for the coming financial year. The Cabinet approved the policy statement for 2012/13 on 20 March 2012.
The Code of Practice also requires the Section 151 Officer to prepare an annual report on the outturn of the previous year. This information is shown under Appendix B of the report.
This report is based on the Council’s unaudited draft accounts as the audit is not due to be completed until the end of September. Basing the report on the unaudited draft accounts will enable the report to be considered in the September / October meeting cycle rather than in November.
That the following recommendations relating to Appendices A and B of this report be approved:
Appendix A - That the following actual prudential indicators based on the unaudited draft accounts be noted:
(a) The actual ratio of non Housing Revenue Account (HRA) financing costs to the non HRA net revenue stream of 12.0%;
(b) The actual ratio of HRA financing costs to the HRA net revenue stream of 14.1%;
(c) Actual non HRA capital expenditure for 2012/13 of £36,783,000;
(d) Actual HRA capital expenditure for 2012/13 of £18,559,000;
(e) The actual non HRA capital financing requirement as at 31 March 2013 of £278,198,000;
(f) The actual HRA capital financing requirement as at 31 March 2013 of £142,010,000;
(g) Actual external debt as at 31 March 2013 was £450,283,442 compared with £455,731,045 at 31 March 2012. 2 Appendix B - That the following actual Treasury Management indicators for 2012/13 be noted:
(a) The Council’s gross debt less investments at 31 March 2013 was £204,215,000;
(b) The maturity structure of the Council’s borrowing was
Under 1 to 2 3 to 5 6 to 10 11 to 20 21 to 30 31 to 40 41 to 50 1 Year Years Years Years Years Years Years Years
Actual 4% 1% 3% 5% 9% 13% 11% 54%
(c) The Council’s sums invested for periods longer than 364 days at 31 March 2013 were:
Actual
£m
31/3/2013 100
31/3/2014 39
31/3/2015 19
(d) The Council’s fixed interest rate exposure at 31 March 2013 was £258m, ie. the Council had net fixed interest rate borrowing of £258m
(e) The Council’s variable interest rate exposure at 31 March 2013 was (£146m), ie. the Council had net variable interest rate investments of £146m
5. Implications
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Treasury Management Outturn 2012/13Report | 266 KB | DownloadRead as text |
Follow Governance & Audit & Standards Committee at Portsmouth and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 25 Jun 2026 | Audit Planning Report (Draft) Year ending 31 March 2026RESOLVED that the committee NOTED the report. | Noted | Open |
| 25 Jun 2026 | Constitutional Changes to respond to the Discharge of Local Planning Authority Functions Regulations 2026RESOLVED that the committee RECOMMENDED to Full Council that Full Council: (i) note the intended change to national l... | Noted | Open |
| 25 Jun 2026 | Draft Annual Governance StatementRESOLVED that the comments of the committee and the draft Annual Governance Statement 2025/26 be NOTED. | Noted | Open |
| 25 Jun 2026 | Treasury Management Outturn ReportRESOLVED that the committee NOTED the actual prudential and treasury management indicators based on the unaudited acc... | Noted | Open |
| 25 Jun 2026 | Internal Audit Performance Status Report to 8th June 2026 & Annual Audit Opinion 2025/26RESOLVED that the committee NOTED: (i) the audit performance and results for 2025/26 to 8 June 2026; (ii) the areas o... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.