Children & Education Decision Meeting approved this item on Thursday 5 December 2013. Below is the council's own wording, with the papers it was decided on.
DECISION that the recommended option be approved and undertaken in three phases: Phase 1 (to be completed for September 2014) · Purchase the existing double unit · Provide covered link between both Year R classrooms · Manage and bring back into the use the southern wild area by installing new trim trail equipment and safety surface · Remove existing equipment in preparation for the next stage Phase 2 (to be completed for September 2015) · Provide 1 additional temporary classroom on a hire for 24 months between September 2015 and September 2017 · Provide new tarmac play-court on site of under-used play structure Phase 3 (to be completed for September 2017) · Remove the additional temporary classroom · Relocate the double unit at Goldsmith to Westover
Word for word from the decision Portsmouth published for this meeting.Source: democracy.portsmouth.gov.uk
1.1At the Joint Portfolio Holder meeting on 29 July 2013 (Cabinet Members for Children and Education & Culture, Leisure and Sport) option 7 was approved i.e. to refurbish the community centre but at a reduced cost (two options put forward – 2e and 2f); and relocate the Association to a mobile unit behind the existing Centre (£350,000 - £300,000)
1.2This option, however, was not supported by the school. As a result a number of other options have been discussed culminating in the recommended option that is set out in paragraph 5.4. This option does not affect Baffins Community Association and therefore does not require the approval of the Cabinet Member for Culture.
Recommendation
2.1That the Cabinet Member approves the recommendation set out in paragraph 5.4.
Background
Original proposal
3.1The Council is working with Westover Primary School to increase the capacity of the School from a 1.5 to 2 form entry, increasing the Published Admission Number (PAN) from 45 to 60 through the addition of three classrooms creating an additional 105 school places overall.
1 www.portsmouth.gov.uk 3.2 The proposal forms part of the Capital Sufficiency Programme that was approved by Full Council on 12 February and was to be completed in two phases: Phase 1 - reconfiguration of existing space in the School in order to create an additional classroom (Year R accommodation) - estimated cost of £106,000; Phase 2 - undertake a new build extension to provide an additional two classrooms - estimated cost of £600,000.
3.3£706,000 was provisionally allocated to this scheme based on an estimate of costs provided by Housing & Property Services, but was approved on the basis that further work would need to be done to investigate the feasibility of refurbishing the Baffins Community Centre which is located on the same site and which could result in a less expensive scheme.
Additional costs incurred
3.4Additional costs have been incurred due to delays to programme which has resulted in the installation of a double temporary modular unit in order to accommodate 60 Year R pupils from September 2013 (cost of £129,000 + £71,342 to cover furniture, fees, planning application, drainage, distribution board upgrade). The total cost incurred so far is £200,342.
3.5Notionally, the remaining capital budget for this project after these costs are taken into account is £505,658. However, the latest forecast for the capital sufficiency programme confirms the only £455,158 of uncommitted funding remains. All the other eight projects that form part of the capital sufficiency programme are on track.
Baffins Community Association
3.6Discussions were held at an early stage with Baffins Community Association about the potential re-location of Community Centre services to other locations in the local community. The proposal was been rejected by the Association. Other options have been explored including the potential use of the double unit that will be installed for September 2013 (discounted due to access, safeguarding and security issues and planning considerations) and the installation of a temporary unit or modular unit that could be used by the Association.
Options
3.7A number of options for phase 2 of the works were considered by Members at the Joint Portfolio Holder meeting on 29 July 2013 (Cabinet Members for Children and Education & Culture, Leisure and Sport) supported by some high level estimates of costs.
3.8The options cover three building types:
New Building: a traditional bespoke building providing exactly the specification and layout required by the client (education services) and
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Children & Education Decision Meeting at Portsmouth and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.