That the Cabinet agreed to: (1) enter into a lease agreement with BAR for the Camber site, on the terms set out in paragraph 3.3, together with any necessary associated agreements (2) authorise the City Solicitor and Head of Corporate Assets, Business & Standards in conjunction with the Cabinet Memer for Planning, Regeneration & Economic Development be authorised to complete all legal documentation in order to give effect to the above recommendation.
Word for word from the decision Portsmouth published for this meeting.Source: democracy.portsmouth.gov.uk
1.1The report is to advise the Cabinet of the opportunity to enter into a new lease on the Camber site (East Street) with Ben Ainslie Racing Ltd (BAR), allowing development of the site as a team base from which to launch a bid to contest the America's Cup; and to request authority to enter into the necessary legal and financial agreements with the proposed tenant, BAR.
Recommendations
2.1It is recommended that the Cabinet resolves to:
(a) enter into a lease agreement with BAR for the Camber site, on the terms set out in paragraph 3.3, together with any necessary associated agreements
(b) authorise the City Solicitor and Head of Corporate Assets, Business & Standards be authorised to complete all legal documentation in order to give effect to the above recommendation.
Background
3.1The City Council (PCC) is the freehold owner of the Camber site. As reported to the Corporate Projects Board on 30th April, early in 2014 Ben Ainslie Racing Ltd (BAR) approached PCC with a view to locating a team base on the site in order to develop and build a boat for the next Americas Cup challenge in 2017; and if successful to host the subsequent race in the UK based in Portsmouth. The team have been clear that the Camber is the preferred location for the BAR project and investment; their business plan indicates positive economic development benefits, including approximately 100 permanent jobs in the city, including in the maritime and technology sector, many more fixed-term jobs, together with supply chain benefit, and a significant boost to the regional economy through visitor spend. The project promotes sub-regional economic development objectives as set out by the Solent Local Enterprise Partnership (SLEP), and is specifically referenced in the Maritime Supplement 1 www.portsmouth.gov.uk commissioned by Government and produced for the SLEP by Rear Admiral Rob Stevens CB (retired). However, to achieve the challenging timescales for the project, building on site must commence June 2014. BAR have submitted an application to the Department of Business, Innovation and Skills (BIS) for exceptional Regional Growth Funding (eRGF) to support the scheme, and submitted a planning application to the city council as the Planning Authority.
3.2To facilitate the scheme as the landowner, and in recognition of the significant property and non-property benefits of the scheme to PCC, PCC have taken the necessary steps, including incurring some expenditure at risk, to ensure that vacant possession of the site immediately following granting of planning consent was a possibility. These items were reported to the Planning, Regeneration and Economic Development portfolio on 13th June 2014.
3.3Planning consent was granted on 18th June, and therefore Cabinet approval is now requested to enter into a new lease with BAR, with terms including: a term of 25 years for use as a boat building facility a rent free period whilst the property is used for the purpose of contesting the America's Cup in the event that the America's Cup ambition ceases then the rent free period will stop and open market rent will become payable with immediate effect, and subject to 5 yearly reviews Alternative use will be discussed should the America's Cup ambition cease BAR will build a new purpose built building and use all reasonable endeavours to nominate Portsmouth as the host city for any event for which it is entitled to choose the location as a result of sponsors or victors rights provided such is commercially, practically and economically viable. The built out headquarters/research unit, to revert to PCC at no cost on the termination of the lease.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.