Eastney Beach Habitat Restoration Plan draft Supplementary Planning Document
ApprovedPlanning2 papers
Planning, Regeneration & Economic Development approved this item on Tuesday 7 October 2014. Below is the council's own wording, with the papers it was decided on.
DECISION: That the Cabinet Member 1. approved the Eastney Beach draft Management Plan SPD (appendix A) for consultation 2. authorised the City Development Manager to make editorial amendments to the draft management plan prior to consultation, in consultation with the Cabinet Member for Planning, Regeneration and Economic Development. These changes will not alter the meaning of the document and will be restricted to grammatical and typographical errors.
Word for word from the decision Portsmouth published for this meeting.Source: democracy.portsmouth.gov.uk
Portsmouth City Council provides the Ordnance Survey mapping included in this publication under license from the Ordnance Survey in order to fulfil its public function as a planning authority. Persons viewing this mapping should contact Ordnance Survey copyright for advice where they wish to license Ordnance Survey map data for their own use.
Consultation Arrangements The draft SPD is available for consultation until 5th November. Please send any comments in writing to [email protected] or City Development (Planning Policy) Portsmouth City Council Civic Offices Guildhall Square Portsmouth PO1 2AU
If you have any questions about this consultation, please call the planning policy team on 023 9268 8633.
i Section 1: Introduction 1.1 Eastney Beach is a designated Local Wildlife Site (LWS) as the beach is home to a large amount of vegetated shingle, which is a priority habitat. The Portsmouth Plan sets out a policy framework to ensure that any impacts to LWS and the habitats they support are properly considered during the planning process.
1.2The Seafront Masterplan was adopted in April 2013 with ambitious proposals to develop and enhance the seafront. The Masterplan recognises that the vegetated shingle at Eastney Beach supports a wide variety of species and is highly valued by those who use it and by the large number of residents and visitors who visit every day. The area is also identified for a number of development opportunities in the future which, together with others along the seafront, will maximise the potential of the seafront as a whole.
1.3Beaches along the Seafront are regularly and heavily used by a wide range of residents for a variety of purposes, and the different sections of the Seafront offer a welcome variety of experiences, from the more managed, open, beach west of the Pier, to the more semi-natural, ‘wilder’ sections further towards Eastney. To continue to be able to provide residents with this diversity of choice and to enhance it, this Plan should be used to clearly define the different areas of provision and management of the different sections of the Seafront. Figure 1: The valuable habitat at Eastney Beach. From the top: Sea 1.4 These twin aspirations of conserving Holly, Eryngium maritimum, Yellow Horned Poppy Glaucium flavum and Sea Beet Beta vulgaris subsp. maritima. and enhancing the biodiversity of Eastney Beach and maintaining and
2 enhancing diversity and quality of choice are clearly consistent with the Seafront Masterplan and Policy PCS9 ‘The Seafront’ of the Portsmouth Plan. This Restoration and Management Plan will therefore be an essential part of the successful implementation of the Seafront Masterplan.
1.5It is likely that developments in this area identified in the Seafront Masterplan will results in adverse impacts on the LWS and habitats within it unless mitigation measures are used to remove this impact. Developers may well find it difficult to address the impacts that their scheme would cause on an individual basis, particularly in the case of smaller developments. This may be due to the costs involved, the difficulties of co-ordination of a number of smaller projects by different organisations and due to impacts being occurring on land outside the applicant’s control.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Planning, Regeneration & Economic Development at Portsmouth and we tell you when its next papers are published, before the meeting rather than after it.
Solent Recreation Mitigation StrategyDECISION: The Leader with responsibilities for Planning Regeneration and Economic Development: A. Approved and agreed...
Viability evidence in planning decisionsIt was agreed that a further report would be brought to PRED after Purdah. Meanwhile an additional decision would be ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.