Strategic Housing Land Availability Assessment 2014
ApprovedPlanning2 papers
Planning, Regeneration & Economic Development approved this item on Tuesday 2 December 2014. Below is the council's own wording, with the papers it was decided on.
DECISION: that the Cabinet Member 1. Approved the Strategic Housing Land Availability Assessment 2014 update (attached as Appendix A of this report) for publication. 2. Authorised the City Development Manager to publish appendix A of the Strategic Housing Land Availability Assessment 2014 update, containing detailed site profiles, in consultation with the Cabinet Member for Planning, Regeneration and Economic Development. Authorised the City Development Manager to make editorial amendments to the study (attached as Appendix A) prior to publication, in consultation with the Cabinet Member for Planning, Regeneration and Economic Development. These amendments shall be restricted to correcting errors and formatting text and shall not alter the meaning of the statement.
Word for word from the decision Portsmouth published for this meeting.Source: democracy.portsmouth.gov.uk
Report to Planning, Regeneration & Economic Development
Purpose of report
1.1Section 159 of the National Planning Policy Framework (NPPF) requires local planning authorities such as Portsmouth City Council to have a robust evidence base which sets out the supply of land for residential development. This must be done through a Strategic Housing Land Availability Assessment (SHLAA).
1.2The purpose of this report is to seek approval to publish the SHLAA 2014 update.
Recommendations
The Cabinet Member is recommended to: 1. approve the Strategic Housing Land Availability Assessment 2014 update (attached as Appendix A of this report) for publication. 2. authorise the City Development Manager to publish appendix 1 of the Strategic Housing Land Availability Assessment 2014 update, containing detailed site profiles, in consultation with the Cabinet Member for Planning, Regeneration and Economic Development. 3. authorise the City Development Manager to make editorial amendments to the study (attached as Appendix A) prior to publication, in consultation with the Cabinet Member for Planning, Regeneration and Economic Development. These amendments shall be restricted to correcting errors and formatting text and shall not alter the meaning of the statement.
1 www.portsmouth.gov.uk 3. Background 3.1 Portsmouth City Council published a SHLAA in September 2009. This study has been updated annually since then, which is a requirement of the NPPF in order to show a rolling supply of housing land.
3.2The SHLAA forms a key part of the evidence base for planning policy documents in the city. Policy decisions though will continue to be taken in such documents and not in the SHLAA. When investigating a site's potential for housing, developers should refer to the adopted development plan1 and relevant Supplementary Planning Documents rather than the SHLAA.
3.3Nothing in the SHLAA should be understood to pre-determine the outcome of planning applications for specific sites or proposals.
3.4A number of changes have been made to the study since the 2013 update was published. Of principal importance has been the publishing of the National Planning Practice Guidance. This updated the previous SHLAA guidance which was published in 2007. A number of changes have been made to the study to reflect the revised guidance. Of particular importance is the need to assess whether the city has met its housing target from the start of the Portsmouth Plan until today. Any shortfall must be accounted for in the first five years rather than spread across the remaining delivery period as has been the case in the past.
3.5Similarly important is that all of the potential housing sites which are considered to be deliverable2 and so have been phased in the first five years of delivery have been subjected to a viability assessment, which was carried out by District Valuer Services. The results of this background work are reflected in section 3 of the study.
3.6Finally, since the 2013 update was published, the joint City Deal between both Portsmouth and Southampton cities and the Government has been signed. This changes and revises the strategic sites in a number of ways, which is fully explained in section 3 of the study.
3.7More minor updates to the study include:
Completions that took place in the year 2013/14 have been included The sites in the planning system have been updated to include all outstanding applications which would result in residential completions at 1st April 2014.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Planning, Regeneration & Economic Development at Portsmouth and we tell you when its next papers are published, before the meeting rather than after it.
Solent Recreation Mitigation StrategyDECISION: The Leader with responsibilities for Planning Regeneration and Economic Development: A. Approved and agreed...
Viability evidence in planning decisionsIt was agreed that a further report would be brought to PRED after Purdah. Meanwhile an additional decision would be ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.