Preparations for Developing a UTC (University Technical College) in Portsmouth
AgreedPlanning1 paper
Planning, Regeneration & Economic Development agreed this item on Wednesday 18 March 2015. Below is the council's own wording, with the papers it was decided on.
DECISION: That the Cabinet Member for Planning, Regeneration and Economic Development agrees (1) That delegated approval be given to the Director of Property and City Solicitor to conclude either a freehold transfer or the grant of a long lease of the land currently forming Hilsea Youth Club shown cross hatched in black on the plan in Appendix 1 ("the Property") to help facilitate the building of the new UTC for Portsmouth. (2) That the disposal be to either the Salterns Academy Trust or the UTC Trust as outlined in the report. That the City Solicitor be given delegated approval to complete the necessary documentation, subject to being satisfied as to terms and any relevant legal requirement.
Word for word from the decision Portsmouth published for this meeting.Source: democracy.portsmouth.gov.uk
Report to Planning, Regeneration & Economic Development
Agenda item:
Title of meeting: Planning, Regeneration & Economic Development Decision Making Meeting Date of meeting: 18 March 2015
Subject: Preparations for developing a UTC in Portsmouth
Report From: The Chief Executive
Report by: Paddy May, Corporate Strategy Manager
Wards affected: All
Key decision: No
Full Council decision: No
1. Purpose of report 1.1. To seek approval for the disposal of the land where the Hilsea Youth Club is currently sited, to facilitate the building of the new University Technical College (UTC) for Portsmouth. The land will be disposed of via either a freehold transfer for no consideration or a 125 year lease at a peppercorn rent.
2. Recommendations 2.1. That the Planning, Regeneration & Economic Development Portfolio Holder agrees that delegated approval be given to the Director of Property and City Solicitor to conclude either a freehold transfer or the grant of a long lease of the land currently forming Hilsea Youth Club shown cross hatched in black on the plan in Appendix 1 ("the Property") to help facilitate the building of the new UTC for Portsmouth. 2.2. That the disposal be to either the Salterns Academy Trust or the UTC Trust as outlined in the report. 2.3. That the City Solicitor be given delegated approval to complete the necessary documentation, subject to being satisfied as to terms and any relevant legal requirement.
3. Background 3.1. UTCs are schools that provide technical education for young people aged 14-19. UTCs are non-selective and engage employers in developing the curriculum and involve employers in providing technical opportunities for young people as part of their learning. On 12th March, Portsmouth heard that their application for developing a UTC was successful. The UTC should help ensure that young people have the technical skills needed for a thriving and growing economy.
1 www.portsmouth.gov.uk 3.2. Portsmouth City Council was a key part of a bidding process that proposed the development of a UTC in Portsmouth. The overall bid was led by the University of Portsmouth with significant project support provided by the Royal Navy and with the education advice provided by the Salterns Academy Trust. We have just heard that our proposal to develop a UTC has been approved nationally. 3.3. As part of the development of a UTC, a separate trust, UTC Portsmouth, has been set up and Portsmouth City Council, along with the Salterns Academy Trust, the Royal Navy and the University of Portsmouth are the founding members of this trust. It is proposed that the UTC will be built alongside the existing City of Portsmouth Boys School site (to be Trafalgar School). Portsmouth City Council owns a small parcel of land (currently the site of the Hilsea Youth Club shown crossed in black on the plan in Appendix 1) and this land will be needed for the development of the UTC.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Councillor Steve HastingsOpposition spokesperson, present
Hear about the next one first
Follow Planning, Regeneration & Economic Development at Portsmouth and we tell you when its next papers are published, before the meeting rather than after it.
Solent Recreation Mitigation StrategyDECISION: The Leader with responsibilities for Planning Regeneration and Economic Development: A. Approved and agreed...
Viability evidence in planning decisionsIt was agreed that a further report would be brought to PRED after Purdah. Meanwhile an additional decision would be ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies