Planning, Regeneration & Economic Development approved this item on Friday 5 June 2015. Below is the council's own wording, with the papers it was decided on.
RESOLVED that, under the provisions of Section 100A of the Local Government Act, 1972 as amended by the Local Government (Access to Information) Act, 1985, the press and public be excluded for the consideration of the following item on the grounds that the appendix to the report contains information defined as exempt in Part 1 of Schedule 12A to the Local Government Act, 1972" An explanation of how the figures in the exempt appendix had been calculated was given by the Finance Manager. The meeting then moved back into open session . The Cabinet Member for PRED said that he would approve the recommendations in the report which he thought represented a very good deal and which showed one of the benefits Portsmouth was deriving from hosting the America's Cup. He said that the deal also meant that Portsmouth was associated with a very good brand and that the financial aspect of the deal would go some way towards making the savings that were necessary. The Deputy Chief Executive collected in all the exempt papers at the end of the meeting and everyone was reminded that the contents of the papers were to be kept confidential. DECISION: Subject to satisfactory Heads of Terms being agreed in accordance with Paragraph 3.8 of the report, 1. Agreed to Naming Rights for the Spinnaker Tower for a minimum period of five years. 2. Agreed to the financial proposition as set out in the exempt appendix. 3. Agreed to the branding of the Spinnaker Tower as set out in the exempt appendix to the report. 4. Agreed to the immediate painting and application of the proposed branding to the Spinnaker Tower. 5. Agreed to deliver the installation of branding, ground level signage and internal signage for the Spinnaker Tower no later than Friday 17 July 2015. The meeting concluded at 8.50am. …………………………………. Cabinet Member for PRED
Word for word from the decision Portsmouth published for this meeting.Source: democracy.portsmouth.gov.uk
Report to Planning, Regeneration & Economic Development
Purpose of report
To consider the financial proposal for the Naming Rights of the Spinnaker Tower.
Recommendations
Subject to satisfactory Heads of Terms being agreed in accordance with Paragraph 3.8 below.
2.1To agree to Naming Rights for the Spinnaker Tower for a minimum period of five years. 2.2 To agree to the financial proposition as set out in the exempt appendix. 2.3 To agree to the branding of the Spinnaker Tower as set out in the exempt appendix. 2.5 To agree the immediate painting and application of the proposed branding to the Spinnaker Tower. 2.6 To deliver the installation of branding, ground level signage and internal signage for the Spinnaker Tower no later than Friday 17 July 2015.
Background
3.1Since 2009, the City Council has been pursuing advertising and sponsorship opportunities to generate additional revenue by using the advertising potential of council-owned land and other assets.
3.2One of these assets, the Spinnaker Tower, is part of the portfolio of assets that belong to Portsmouth City Council.
3.3Like many local authorities, the city council are looking for commercial partners who want to invest in the rights to associated commercial sponsorship opportunities, including naming rights and branding options. 1 www.portsmouth.gov.uk 3.4 Following discussions with the Administration in 2012, Marketing & Business Development have been actively pursuing opportunities associated with the Tower.
3.5In 2013, a Spend to Save was supported and budget assigned to actively pursue a high-profile Naming Rights partner for the Tower.
3.6A Sports Sponsorship specialist, 'Eleven', was secured and have been working to a deadline of having a Naming Rights partner in place before the 10th anniversary celebrations for the Tower in 2015.
3.7Marketing and Business Development have worked alongside Eleven to identify suitable brands to approach with the city council's naming rights offer. 11 brands were shortlisted and approached, with one company ("the Company") taking negotiation through to a financial proposal for agreement.
3.8To enable this proposal to proceed within the agreed timeframe it is not possible at this time to present agreed Heads of Terms for approval. It is however proposed that these should be agreed by the City Solicitor and Section 151 officer in consultation with the Cabinet Member for PRED.
Reasons for recommendations
4.1The Company have indicated their desire to acquire the Naming Rights of the Spinnaker Tower on the proviso that branding and signage can be in situ in time for the start of the Americas Cup World Series 2015. In order to meet this deadline, painting of the Tower will need to take place with immediate effect. The financial deal proposed represents a very credible offer from a premium brand.
5. Equality impact assessment (EIA)
5.1Not applicable
Legal implications
6.1The proposed granting of the naming rights for the Tower is subject to certain property consents being obtained as set out in the exempt Appendix A (to follow). Negotiations to obtain the consents are progressing and an update on progress will be given to the Cabinet Member for PRED in the meeting. The proposed repainting of the tower does not in itself require planning permission and it can therefore proceed. However the display of the Company's name will amount to an advertisement and is subject to the need to obtain planning consent in respect of the proposed advertisement and this application will be made in the usual way at the appropriate time.
2 www.portsmouth.gov.uk 7. Finance comments
7.1The proposal will produce a net income for the Council, details of which are set out in the exempt appendix.
……………………………………………… Signed by:
Appendices: Exempt Appendix A (under Local Government Act 1972, Schedule 12A (as amended) Paragraph 3
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Councillor Colin GallowayOpposition spokesperson, present
Hear about the next one first
Follow Planning, Regeneration & Economic Development at Portsmouth and we tell you when its next papers are published, before the meeting rather than after it.
Solent Recreation Mitigation StrategyDECISION: The Leader with responsibilities for Planning Regeneration and Economic Development: A. Approved and agreed...
Viability evidence in planning decisionsIt was agreed that a further report would be brought to PRED after Purdah. Meanwhile an additional decision would be ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.