DECISION: That 1) the content of this report be noted. 2) the completion of the WiFi to Public Buildings stage of the project be approved and the installation of access points at 79 sites versus the original agreement of 49 sites be noted 3) the potential opportunities afforded by My City WiFi for sensory applications with the express objective of providing efficiency savings for the Council and its public sector partners be investigated
Word for word from the decision Portsmouth published for this meeting.Source: democracy.portsmouth.gov.uk
2.1To update the Cabinet Member on the Super Connected Cities Programme and the potential opportunities afforded by the new WiFi infrastructure deployed in the City.
Recommendations
3.1The content of this report be noted.
3.2To approve the completion of the WiFi to Public Buildings stage of the project and noting the installation of access points at 79 sites versus the original agreement of 49 sites
3.3To investigate the potential opportunities afforded by My City WiFi for sensory applications with the express objective of providing efficiency savings for the Council and its public sector partners.
1 www.portsmouth.gov.uk 4. Background
4.1There were three main goals for the Super Connected City programme:
• To support economic growth innovation and enterprise in Portsmouth • To enhance the competitiveness of our city • To aid digital inclusion.
The Super Connected City programme was seen as a key enabler to these three overarching goals, which are firmly rooted in local circumstance, culture, need and aspiration, are the building blocks of an achievable and sustainable city future and provide benefits that enhance quality of life for everyone.
5. Progress to Date
5.1WiFi to public buildings
The main objective for the public building wifi project was to provide high-speed, high quality, secure, free wifi access in public buildings across the city to as many residents and visitors as possible.
During the programme the approach changed from upgrading 'Fibre to the Cabinet (FTTC)', to 'Fibre to the Premise (FTTP)' largely as a consequence of state aid issues. The change in approach however, allowed more direct and measureable impact on business growth.
Initially the bid awarded was for £1,875,000 to provide WiFi to 49 public buildings including key public buildings with high footfall (such as the Portsmouth Ferry Port) and strategically placed buildings that would reduce the European Commission category of areas without 'Next Generation Access' to broadband (NGA white areas) in the city.
In December 2014 we took the opportunity and applied to the DCMS to increase the free public WiFi roll out to a further 62 public buildings focussing on those delivering adult social care. This was facilitated by reallocating £1,380,600 to the public wifi scheme from the initial allocation to the voucher scheme (see below). At the conclusion of the scheme it was only possible to rollout Public Access WiFi to a total of 79 sites, albeit in a very short timescale. Early feedback from various sites including Libraries and Community Centres is generally positive and we continue to monitor performance through the control system (CISCO Meraki Analytics) which enables us to produce a series of reports showing usage. This will enable us to tune the system to ensure the facility meets demand.
The DCMS agreement was to fund all installations that were successfully completed and operational by 31st March 2015, PCC requested approval to complete a further 14 sites by 30th June 2015 which was agreed. Therefore this stage is now considered closed as all sites are now operational with no further funding available from the DCMS.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
International Relationship StrategyThe Cabinet Member for Resources (1) Adopts this proposed International Relationship Strategy 2020 - 2025. (2) Agrees...
Provision of Community FuneralsDECISION: The Cabinet Member (1) Approved the manner in which community funerals are delivered, as outlined in Sectio...
Volunteering Strategy 2018-2021DECISION: The Cabinet Member for Resources gave approval to implement the Volunteering Strategy attached as appendix ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.