Resolved
The Cabinet Member authorised that no action be taken regarding the LB zone (zone continues unchanged).
Traffic & Transportation decided this item on Thursday 18 February 2016. Below is the council's own wording, with the papers it was decided on.
Resolved
The Cabinet Member authorised that no action be taken regarding the LB zone (zone continues unchanged).
To re-present the information on LB zone, enabling the decision taken at the 26 November 2015 Traffic & Transportation meeting to be reviewed, as per the Scrutiny Management Panel decision made on 17 December 2015.
That the Cabinet Member authorises either:
2.13-week consultation on the LB zone via a permanent TRO on amending and reducing the size of the LB zone (while the zone remains in place) or 2.2 6-month consultation on the LB zone via an experimental TRO on amending and reducing the size of the LB zone (while the zone is suspended) or 2.3 That no action is taken regarding the LB zone (zone continues unchanged)
(Larger plan available at Appendix A)
1 www.portsmouth.gov.uk 3. Background
3.1At the Traffic & Transportation meeting held on 26 November 2015, the decision was taken to suspend the majority of the LB zone, due to its impact on residents of neighbouring roads. 3.2 That decision was called in and subsequently evaluated by the Scrutiny Management Panel on 17 December 2015. The decision was referred back to the Traffic & Transportation Portfolio Holder for review.
3.3Legal Services confirmed in the 26 November 2015 report the two types of Traffic Regulation Orders (TRO) that are relevant to the recommendations - permanent and experimental: both involve public consultation before any permanent action is taken.
- Permanent TRO: a 21-day public consultation takes place on proposals before deciding whether or not to permanently implement the measures;
- Experimental TRO: a 6-month public consultation takes place on proposals put in place simultaneously, before deciding whether or not to permanently implement those measures.
3.4The decision to suspend the LB zone reflected the latter option (experimental TRO) to be consistent with suspending the MB and MC zones previously. A public consultation would take place simultaneously during the first 6 months to provide the opportunity for local people to comment on the effects of the suspension.
4.1Following the decision by the Scrutiny Management Panel in December 2015 a review has been undertaken of earlier consultation within LB zone which is reflected in this report.
4.2The March/April 2015 consultation "Have Your Say - Residents' Parking" asked residents of all 35 parking zones whether or not they would like to keep their zones, in light of the £30 charge for a first permit. It indicated that the remaining zones (the zones residents would like to keep) would be reviewed to ensure they operate as effectively and efficiently as possible. Further details can be viewed in the report to the Cabinet Member for Traffic and Transportation on 15 July 2015.
4.3Of those who responded from LB zone to the March/April 2015 consultation on the £30 charge for the first Resident permit:
69% voted to keep the zone and 31% voted to remove the zone, representing just under 20% of LB Resident permit holders.
Those who voted to remove the zone equated to 51 individuals, out of a total of 829 permit holders.
4.4There is an opportunity to improve the effectiveness of the LB zone's operation, whilst potentially reducing the impact of displaced parking on adjacent roads that are outside the zone.
2 www.portsmouth.gov.uk 4.5 A petition signed by 97 residents was submitted to the Council requesting a separate zone for residents living in the 'square' of roads made up of Livingstone Road, Lorne Road and Havelock Road. These were previously included as part of the MC zone but not geographically linked to it. The parking problems have been caused by the introduction of the LB zone, contributing to the recommendation within the report of 26 November 2015 to amend that zone to reduce the level of displaced parking.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
LB Zone Residents' Parking Zone (RPZ)Report | 920 KB | DownloadRead as text |
Follow Traffic & Transportation at Portsmouth and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 23 Mar 2023 | Local Transport Plan 4 - Implementation Plan 2022 to 2025 - Year 2 annual reviewDecision The Cabinet Member: Approved and adopted the Local Transport Plan (LTP4) funded schemes 2023/24 as part of P... | Approved | Open |
| 23 Mar 2023 | Tertiary Roads Inspection and RepairDecision The Cabinet Member: 1. Approved that the plans and timings of inspections of the tertiary road network are s... | Approved | Open |
| 23 Mar 2023 | Active Travel Improvements - TRO 206/2022 Isambard Brunel RoadDecision The Cabinet Member: 1. Approved the implementation of TRO 206/2022 for the introduction of the bus, taxi and... | Approved | Open |
| 23 Mar 2023 | TRO 24/2023 - Walmer Road, Renny Road and Proctor Lane - one way except cyclesDecision The Cabinet Member: 1. Approved the implementation of TRO 24/2023, to implement a series of one-way streets ... | Approved | Open |
| 23 Mar 2023 | St Jude's School Streets permanent infrastructureDecision The Cabinet Member: 1. Approved creating a School Street via the installation of resident only access signs ... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.