Portsmouth City Council
Planning, Regeneration & Economic Development, Wednesday 13 July 2016 at 9.30am

Northern Quarter: Termination of Development Agreement

Agreed Planning 1 paper

Planning, Regeneration & Economic Development agreed this item on Wednesday 13 July 2016. Below is the council's own wording, with the papers it was decided on.

Item16

Resolved

DECISION: (1) To terminate the development agreement and agreement for lease. (2) That a report is prepared for the S151 Officer and Deputy Chief Executive for action in consultation with the Leader of the Council with responsibilities for PRED on: i. Any sums outstanding between the parties and the rights of recovery, ii. property implications regarding the transfer of titles or otherwise of the properties currently held in trust on behalf of Centros Portsmouth Partnership Limited.
Word for word from the decision Portsmouth published for this meeting. Source: democracy.portsmouth.gov.uk

Follow this further

Built from Portsmouth's papers

What the report saysPro

Report to Planning, Regeneration & Economic Development

Wards affected

Key decision: Yes

Full Council decision: No

Purpose of report

1.1To provide the background to the recommendation to terminate the development agreement and agreement for lease between Portsmouth City Council, and Centros Portsmouth Partnership Limited (CPLP).

Recommendations

2.1To terminate the development agreement and agreement for lease.

2.2That a report is prepared for the S151 Officer and Deputy Chief Executive for action in consultation with the Leader of the Council with responsibilities for PRED on:

i. any sums outstanding between the parties and the rights of recovery, ii. property implications regarding the transfer of titles or otherwise of the properties currently held in trust on behalf of CPLP.

Background

3.1The initial development agreement was entered into on 23 March 2004 which included a clause to recover the council's associated costs of up to £450,000. The development was not implemented, and the agreement documentation has undergone review, and amendment, aimed at facilitating the delivery of a scheme.

3.2Following the failure to implement the scheme which received planning permission in 2006 extensive work was undertaken by the Council and its advisory team to make further revisions to the development agreement at the request of CPLP, this

1 www.portsmouth.gov.uk included promoting a related City Centre Road scheme, and also considering options around a joint enterprise.

3.3This work was done at risk of costs, with significant payments due to be paid to the Council on the execution of the various legal documents effecting the amendments.

3.4CPLP declined to enter into the agreements at the point of execution, and there is no fit for purpose contractual apparatus to provide for the delivery of development in the city's northern quarter.

Planning Position

3.5The current Local Plan that allocates the land for development is now under review and the whole of the city centre is being re-examined with further development and growth opportunities identified. As the Local Plan will not go to Examination until late 2018 an early concept plan will be developed in the coming months to enable the whole area to be considered to avoid incremental development occurring that could undermine the future growth potential for the city centre This will be dealt with through a separate report from the Director of Culture and City Development.

Property Implications

3.6There are 5 commercial properties and 2 residential properties that are currently held in trust by the City Council on behalf of CPLP. Upon termination these properties will need to either be i. conveyed to CPLP with all management responsibility passing accordingly, or ii. retained by paying CPLP market value for these assets. These implications will be subject to a further report as detailed under recommendation 2.2 above.

Reasons for recommendations

4.1The Council and CPLP have sought to work together over an extensive period of time, but find that the opportunity to develop a scheme within the framework of the extant development agreement is not possible.

5.1The Council is entitled to terminate the development agreement on the giving of 10 days of notice. This arises as a result of the unconditional date having not occurred by the date which is 72 months after the date of the Agreement (being 23 March 2010). Either party may, whilst the relevant condition precedent or conditions precedent remain unsatisfied) give 10 working days' notice to the other terminating the development agreement.

5.2The Council is entitled to retain all monies paid to it up to the date of termination.

2 www.portsmouth.gov.uk 5.3 Any monies due to the Council up to the date of determination under the Agreement will be the subject of a further report as per 2.2 above.

6. Director of Finance's comments

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Northern Quarter: Termination of Development AgreementReport 104 KB DownloadRead as text

At this meeting

Whole meeting
13Victoria Park Action PlanOn the agenda
16Northern Quarter: Termination of Development AgreementThis decision

Who was there

3 of 4 attended
DJ
Councillor Donna JonesCabinet Member, present
YC
Councillor Yahiya ChowdhuryOpposition spokesperson, apologies
BD
Councillor Ben DowlingOpposition spokesperson, present
CG
Councillor Colin GallowayOpposition spokesperson, present

More from Portsmouth Planning, Regeneration & Economic Development

All decisions
MeetingDecisionOutcome
28 Feb 2018 Solent Recreation Mitigation StrategyDECISION: The Leader with responsibilities for Planning Regeneration and Economic Development: A. Approved and agreed... Approved Open
28 Feb 2018 Self-build and Custom Housebuilding Register Local Eligibility CriteriaDECISION: The Leader with responsibilities for Planning, Regeneration and Economic Development approved the introduct... Approved Open
28 Feb 2018 Viability evidence in planning decisionsIt was agreed that a further report would be brought to PRED after Purdah. Meanwhile an additional decision would be ... Agreed Open
28 Feb 2018 Authority Monitoring ReportDECISION: The Leader with responsibilities for PRED a pproved the AMR for publication on the council’s website Decided Open
21 Nov 2017 Houses in Multiple Occupation - Supplementary Planning Document (SPD)1.The SPD: Houses in Multiple Occupation 2017 be approved for adoption from immediate effect including the minor amen... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies