RECOMMENDED to Council that the following be approved: (1) The currently approved Capital Programme 2015/16 to 2020/21 is updated to include the capital scheme "Sports and Leisure Facilities Investment" at an estimated cost of £2.4m. (2) Following completion of a comprehensive financial appraisal, approved by the Director of Finance & S151 Officer demonstrating that the additional reduction in cost arising from the investment can significantly exceed the associated borrowing costs over the life of the contract, that the cost of the scheme be financed from Prudential Borrowing. (N.B. as this item is referred to Council for approval it is not subject to call-in)
Word for word from the decision Portsmouth published for this meeting.Source: democracy.portsmouth.gov.uk
1.1This report seeks approval for a capital scheme to be added to the Capital Programme approved by the City Council on 9th February 2016. This will enable various capital investment works and major repairs to the city's Sports and Leisure facilities to be undertaken after the commencement of the new Sports and Leisure contracts for which BH Live have recently been awarded preferred bidder status.
Recommendations
2.1That the following be approved:
i. The currently approved Capital Programme 2015/16 to 2020/21 is updated to include the capital scheme "Sports and Leisure Facilities Investment" at an estimated cost of £2.4m.
ii. Following completion of a comprehensive financial appraisal, approved by the Director of Finance & S151 Officer demonstrating that the additional reduction in cost arising from the investment can significantly exceed the associated borrowing costs over the life of the contract, that the cost of the scheme be financed from Prudential Borrowing.
Background
3.1On 3rd December 2015 Cabinet approved the "re-procurement" option for the Mountbatten Centre and other Leisure Sites Management Contracts for the provision of these facilities.
3.2The target contract start date is 1st February 2017 and a project team was formed in early 2016 to facilitate this.
1 www.portsmouth.gov.uk 3.3. The procurement project had a number of objectives including:
A review of the current contractor operation in order to develop a comprehensive understanding of existing delivery methodology
Development of a full understanding of the current contractual relationship with the incumbent operator
An assessment of the current and future requirements for sports and leisure facilities in Portsmouth
To have a clear understanding of the role Public Health plays in the provision of leisure facilities
An improvement in current service outcomes and an enhanced financial offer to the Council
3.4Following the advertisement of the contract to operate 6 of the City's Leisure facilities, a number of high quality bids were received. Each bid was comprehensively evaluated using criteria previously set out by the Council. As a result of this evaluation, BH Live were selected as the preferred bidder. BH Live consistently scored highly across all areas of the bid assessment criteria, and the Council was particularly impressed by their exciting development proposals for the facilities and the highly competitive and flexible membership packages that they proposed.
3.5The new contract is expected to provide considerable savings from 2018/19 onwards compared to current budgets whilst improving both the level of participation, and the overall customer experience.
3.6The successful bidders offer included the financing costs of their investment proposals assuming PCC undertook the borrowing to enable various building alterations including the following:
Wimbledon Park Sports Centre - Health and Fitness Extension
Mountbatten Centre - Improvement works to Entrance and Reception Area and Terrace Café, Soft Play and Multi Use Rooms. Provision of a Clip and Climb Facility
Significant Maintenance items including: Gym Centre car park replacement, Wimbledon Park Sports Centre internal and external redecoration and Mountbatten Gym Centre floor replacement
2 www.portsmouth.gov.uk 3.7. It is clear from the tender return that providing £2.4m of capital investment into the assets would result in a significant reduction in the management fee. This reduction is expected to more than cover the cost of repayment of the loan over the 10 year life of the contract.
3.8The initial contract term with the new operator is ten years. The repayment term of any Prudential Borrowing approved will be consistent with this contract term.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.