Resolved
DECISION Agreed that the CCTV operators be brought in-house on their current terms and conditions on 1 August 2017.
Environment & Community Safety agreed this item on Thursday 23 March 2017. Below is the council's own wording, with the papers it was decided on.
Resolved
DECISION Agreed that the CCTV operators be brought in-house on their current terms and conditions on 1 August 2017.
1.2This report is to review the options available to Portsmouth City Council when the CCTV Monitoring Contract, currently managed by Keyline Chartered Security Limited ends on the 31st July 2017. The options available are to extend the contract by one year or employ the operators in-house. There is a third option to re-tender the contract, but that process would require the 1 year extension to be agreed to meet timescales.
2.1The Cabinet Member for the Environment and Community Safety agree that the CCTV operators be brought in-house on their current terms and conditions on the 1st August 2017.
3.1The CCTV Control Room and the equipment within it is owned by Portsmouth City Council (PCC). The CCTV Operations Manager is a PCC employee so oversees the CCTV Operator Contract, but the operators are employed by Keyline Chartered Security Ltd.
3.2The CCTV Control Room has two operators on duty for 365 days a year, 24 hours each day on a rota system. There is currently a supervisor and officer on duty at all times. The current number of staff required to meet this demand is four supervisors and four officers, working on a rota system.
3.3The CCTV Operator Contract has always been managed by an external company and on the 1st August 2013 the current contractors Keyline Chartered Security Ltd were awarded the contract following a re-tendering exercise. The existing operator team was previously managed by the
1 www.portsmouth.gov.uk outgoing contractor Mitie Security and the operators became Keyline employees by way of TUPE.
3.4The current contract is for four years with the option to extend by an additional one year. The four year element of the contract ends on the 31 st July 2017.
3.5A working group was formed to review the options and it was agreed to recommend the options to bring the operators in-house and this will likely be by way of a TUPE transfer.
3.6If it is agreed to bring the contract in-house 15 weeks' notice is required to formally end the contract to enable a start date of the 1 st August 2017 for the new way of working.
4.1Bringing in the operators in-house should achieve a saving but more importantly give direct control of the operators to the CCTV Operations Manager. This will assist our plans in the future to identify income opportunities and enable closer synergy with the Traffic Management Control Centre as co-location is currently being progressed.
4.2The Keyline contract (providing for living wage requirements) has recently been increased to £212,000 per year. The proposed in-house TUPE is estimated to cost £173,000 per year, and provides for pension access. This would contribute to the CCTV savings target for 2017/18.
4.3Should all staff convert to Portsmouth City Council's terms and conditions it is estimated that this could cost in the region of £209,000 per annum based on current pay rates and anticipated pay banding. An upgrade by one pay band would increase this cost to some £229,000. However these costs could be mitigated in a number of ways including changing contracts e.g. removing the need for a shift element to ensure that budget pressures would be met.
4.4However, these terms are unlikely to be applicable in the short term as TUPE is applied and, should a vacancy arise in one of these posts, it would be intended to appoint an apprentice to the role. This would assist in maintaining financial stability and in meeting the budget target.
4.5The operators are currently on an hourly rate above the living wage and predicted to be so until at least 2020. Therefore it is not expected to need to harmonise or change contracts for those that TUPE across for several years.
4.6There remains the option to re-tender in the future.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
CCTV Operator Report.Report | 130 KB | DownloadRead as text |
Follow Environment & Community Safety at Portsmouth and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 28 Feb 2019 | Separate Food Waste Collection TrialDECISION:The Cabinet Member approved the proposal for a food waste collection trial. | Approved | Open |
| 28 Feb 2019 | Illicit tobacco and alcohol harm reductionThat the Cabinet Member for Environment and Community Safety: a) acknowledged that t he trade in illicit tobacco and ... | Approved | Open |
| 28 Feb 2019 | Community crime reduction grantRESOLVED That the Cabinet Member approved: a) The establishment of a £90k community crime reduction fund for three ye... | Approved | Open |
| 5 Feb 2019 | Update on the recent changes to refuse collectionDECISION The Cabinet Member noted the progress made in making the changes to the refuse collection service and the ea... | Noted | Open |
| 7 Nov 2018 | Public Spaces Protection Order (Dog Controls)DECISION The Cabinet Member for Environment & Community Safety agreed: 1) The two proposed variations to the existing... | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.