North Chapel Refurbishment

Approved Committee 1 paper

Portchester Crematorium Joint Committee approved this item on Monday 26 June 2017. Below is the council's own wording, with the papers it was decided on.

Item738

Resolved

RESOLVED (1) That RBA Architects Ltd be thanked for the presentation of their proposals for the refurbishment of the North Chapel and that the design principles, taking into account the observations and comments of members, be approved. (2) That RBA Architects Ltd be appointed to progress the design scheme on appropriate terms and conditions to be settled by the Engineer and Surveyor after consultation with the Clerk to the Joint Committee and the Treasurer. (3) That financial provision of £205,000 plus professional fees and VAT for the estimated cost of implementing the scheme be made in the Joint Committee’s budget for 2017/18. (4) That authority be given for the scheme to be supervised by Fareham Borough Council’s Building Services. (5) That authority be given to appoint artec3 as lighting consultants. (6) That authority be given to appoint RBA Architects Ltd as “Principal Designer” in respect of the requirements of the Construction (Design and Management) Regulations. (7) That authority be given to appoint a specialist structural engineer as a separate design service.
Word for word from the decision Portsmouth published for this meeting. Source: democracy.portsmouth.gov.uk

Follow this further

Built from Portsmouth's papers

What the report saysPro

Report to Portchester Crematorium Joint Committee

REPORT TO: PORTCHESTER CREMATORIUM JOINT COMMITTEE – 26 JUNE 2017

REPORT OF: THE ENGINEER AND SURVEYOR

SUBJECT: NORTH CHAPEL REFURBISHMENT

1.0Purpose of this Report

1.1To seek the Committee’s approval to proceed with a scheme to refurbish the Crematorium’s North Chapel. Issues requiring approval include:  Concept scheme design  Appointment of consulting personnel  Budget provision

2.0Introduction

2.1At the last meeting of the Joint Committee a report was received advising that RBA Architects Ltd, (RBA), had agreed to produce a concept design for refurbishing the North Chapel. RBA were the architect engaged on the successful refurbishment of the South Chapel.

3.0Concept Design

3.1RBA have been invited to attend the meeting to present their concept design and to enable members to ask questions on any aspect of the design before this is progressed further.

3.2In summary the concept design includes the following works:

(i) Removal of the existing ceiling in order to increase the volume of the chapel and create a more spacious appearance. Works would include cladding the existing hidden roof trusses.

(ii) Improving the natural light levels by the provision of new high level windows, with “obscure” glazing, in the side walls.

(iii) Introduction of low energy feature lighting similar to that used in the South Chapel.

(iv) Introducing wooden cladding to the walls. This would be similar to that used in the South Chapel and would create a significant unifying theme.

TCG 14.06.2017 (v) Improvement to the heating and ventilation by the introduction of air conditioning to replace the existing under floor heating.

(vi) Removal of the wooden pews and their replacement with linked individual chairs. This could enable the chapel seating to be reconfigured to provide an intimate space more appropriate to smaller funerals

(vii) Possible reconfiguration of the curtains in the committal area

4.0Appointment of consulting personnel

4.1It is recommended that subject to the normal checking process that RBA, the main designers responsible for the South Chapel, be appointed to implement this project. They have already offered to work on the same terms and conditions that applied to the South Chapel refurbishment.

4..2 The lighting consultant used on the South Chapel has moved to another company and RBA have indicated a wish to use the same person on this scheme. It would therefore be necessary to engage a different company namely artec3 in order to achieve the same person working on this project.

4.3It is necessary to appoint a “Principal Designer” in respect of the requirements of the Construction (Design and Management) Regulations. This role is separate from that of the main design and on a job of this nature can be undertaken by RBA as an additional role.

4.4There is an element of structural work design work required at the design stage and it is proposed that this is undertaken by a specialist structural engineer as a separate design service.

5.0Budget Provision

5.1RBA have engaged the services of a quantity surveying company on the Joint Committee’s behalf in order to provide an initial budget figure. They estimate the cost of the scheme to be £205,000 excluding VAT and professional fees. This cost can be met within the Committee’s finances.

6.0Other Matters

6.1The works to the South Chapel were awarded following a tendering procedure. It is my intention to present a report to the September meeting of the Joint Committee on the procurement process to appoint a main contractor. This will include the possibility of a negotiated tender process.

6.2The services of Fareham’s Building Control Service were previously utilised for the South Chapel and it is recommended that the same procedure be adopted on this project.

TCG 14.06.2017 7.0 Recommendations

7.1That RBA Architects Ltd be thanked for the presentation of their proposals for the refurbishment of the North Chapel and that the design principles be approved.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
North Chapel RefurbishmentReport 247 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

6 of 11 attended
FJ
Councillor Frank Jonas BEM Portsmouth City CouncilChair, present
SB
Councillor Susan Bell Fareham Borough CouncilVice-Chair, apologies
TB
Councillor Tony Briggs Havant Borough CouncilCommittee Member, present
JC
Councillor June Cully Gosport Borough CouncilCommittee Member, present
KE
Councillor Keith Evans Fareham Borough CouncilCommittee Member, present
DG
Councillor David Guest Havant Borough CouncilCommittee Member, apologies
RN
Councillor Robert New Portsmouth City CouncilCommittee Member, absent
AS
Councillor Alan Scard Gosport Borough CouncilCommittee Member, present
JH
John HaskellClerk, present
TG
Terry Garvey Portchester Crematorium Joint Committee (Engineer & Surveyor)Officer
AW
Andy Wannell Portchester Crematorium Joint Committee (Treasurer)Officer

On this subject at Portsmouth

Search all
  1. North Chapel RefurbishmentThis decision
  2. Date of Next Meeting - Monday 24 June 2019 at 2pm in the North Chapel, Portchester CrematoriumDecided
  3. North Chapel RefurbishmentNoted
  4. North Chapel RefurbishmentNoted
  5. North Chapel RefurbishmentNoted
  6. North Chapel RefurbishmentNoted

More from Portsmouth Portchester Crematorium Joint Committee

All decisions
MeetingDecisionOutcome
13 Dec 2021 Minutes of the Meeting held on 20 September 2021RESOLVED that the minutes of the meeting held on the 20 September 2021 be signed as a correct record. Decided Open
13 Dec 2021 Finance Strategy and Budget for 2022/23RESOLVED (1) that the Finance Strategy 2022/23, attached as Appendix A to the report, be approved; (2) that the Finan... Approved Open
13 Dec 2021 Revenue Budget Report - 2022/23RESOLVED (a) That the capital works programme as detailed in Appendix D to the report be approved; (b) That the Joint... Approved Open
13 Dec 2021 Manager and Registrar’s ReportRESOLVED that the report be received and noted. Noted Open
13 Dec 2021 Building Repairs and Renewal ProgrammeRESOLVED that the contents of the report be noted and approved. Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies