DECISIONS - The Cabinet: (1) Noted the cross directorate engagement undertaken to identify the five sites and the officer recommendations. (2) Approved the principle of redevelopment of the five sites for the purposes of housing delivery, subject to a planning permission being granted. (3) Delegated to the Section 151 Officer, in consultation with the Leader, Cabinet Member for PRED, Cabinet Member for Housing and Director of Regeneration, to agree the development strategy and preferred delivery route for each site, subject to a business case review, with a view to maximising affordable housing across the 5 sites to meet local housing need. (4) Delegated authority to the S151. Officer to lend monies to the Arms-Length Development Company (ALDC from hereon in referred to as Ravelin ) within the limits of the Council's treasury Management Strategy and following production of a full and proper financial appraisal demonstrating viability of each project. (5) Approved in principle the appropriation of land between the Council and Ravelin , to deliver the five site projects. The transfer of land will be delegated to the relevant Cabinet Member dependant on the site ownership and the Section 151 Officer with the timing of this subject to a final project specific business case being approved. All transfer will be carried out in line with treasury guidance using red book valuations.
Word for word from the decision Portsmouth published for this meeting.Source: democracy.portsmouth.gov.uk
1.1The purpose of this report is to seek agreement from the Cabinet, to proceed with the recommendation of officers, to redevelop five Council-owned sites.
1.2The report proposes that the Council takes a pro-active approach to developing underused council assets in line with its corporate objectives, to support the physical, social, cultural and economic regeneration of the City.
Recommendations
2.1It is recommended that the Cabinet:
2.2Note the cross directorate engagement undertaken to identify the five sites and the officer recommendations.
2.3Approve the principle of redevelopment of the five sites for the purposes of housing delivery, subject to a planning permission being granted.
2.4Delegate to the Section 151 Officer, in consultation with the Leader, Cabinet Member for PRED, Cabinet Member for Housing and Director of Regeneration, to agree the development strategy and preferred delivery route for each site, subject to a business case review.
2.5Delegate authority to the S151. Officer to lend monies to the Arms-Length Development Company (ALDC from hereon in referred to as Ravelin) within the limits of the Council's treasury Management Strategy and following production of a full and proper financial appraisal demonstrating viability of each project.
2.6Approve in principle the appropriation of land between the Council and Ravelin, to deliver the five site projects. The transfer of land will be delegated to the relevant Cabinet Member dependant on the site ownership and the Section 151 Officer with the timing of this subject to a final project specific business case being approved. All transfer will be carried out in line with treasury guidance using red book valuations. 1 www.portsmouth.gov.uk 3. Background
3.1The Council recognises that it has under-utilised and vacant property that could be put to better use.
3.2A cross-directorate Development Programme Enabling Board (DPEB) has been established to create a pipeline of development projects to make best use of this land to support the Council's ambitions for physical, social and economic regeneration of the City. All directorates are invited to put forward their requirements for consideration when new strategic development opportunities are identified.
3.3The first DPEB took place on the 23rd July 2018 and Board Members supported the following recommendations (see Appendix A) for residential development across five sites.
3.4These first five sites have been selected for their individual attributes including simplicity, planning status, location, availability and timely deliverability. However these sites are still subject to ongoing design, planning and viability testing.
3.5The first five sites are to be determined as a portfolio in conjunction with the recommendations herein. The recommendations for these five sites will not necessarily be a pattern for all future development opportunities. Future projects will consider and deliver other uses such as adult social care, education, culture and leisure, employment etc. This list is not exhaustive.
3.6Feasibility work has been undertaken on each of the five sites. Table 1 provides an overview of the five sites; where the asset is held; anticipated housing delivery numbers and development costs. Appendix A provides more detailed businesses justification commentary on each of the five sites.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.