The Cabinet: (1) Agreed to the progression and conclusion of the procurement to secure the framework Contractor as outlined above. (2) Delegated authority to the Director of Regeneration to allow contracts to be let up to the value of £1m within this framework with the successful contractor. In addition to this Delegated Authority was granted for contracts to be entered into between £1m and £5m to the Director of Regeneration following with the approval of Project Board, chaired by the Leader of the Council, and Section 151 Finance Officer. (Anything above this will necessitate further Cabinet approval.)
Word for word from the decision Portsmouth published for this meeting.Source: democracy.portsmouth.gov.uk
1.1This report seeks approval to progress and conclude the appointment of a Design & Build Partner Contractor to be used to deliver the new road and highways infrastructure required to deliver the wider redevelopment of the City Centre.
1.2The recommendations in this report should be considered as the first step in the Council plans to facilitate the Cultural Regeneration of the City Centre. This report is aligned with other key work streams such as the refreshing of the City Centre masterplan and Supplementary Planning Document (SPD), the delivery of key infrastructure to support growth in the City and the revitalisation of Commercial Road. All need to come together to deliver regeneration and growth for the City Centre and Portsmouth as a whole.
1.3Officers are conscious that sites in the City Centre have not progressed for some time due to market factors. Officers are confident that once developed, the increased activity will bring people back to Commercial Road and this will be the catalyst required to bring forward development to the surrounding areas however this does need a development of scale to go first.
1.4Officers are clear that any proposal must deliver outcomes in line with the Council Plan and the council's Cultural Regeneration aspirations, whilst being a viable commercial prospect.
1.5The Council is in the final stages of an OJEU advertised Public Contracts Regulations (2015) compliant procurement process to secure a contractor to work alongside the Council in developing this area.
1 www.portsmouth.gov.uk 1.6 Subject to approval by the Council's Procurement Gateway Board, approval by Cabinet and completion of the statutory standstill period without challenge from unsuccessful bidders the successful Contractor should be secured in mid-February 2019.
1.7The Contractor will be secured on the basis of a nil value framework agreement which will allow the Council to draw down works and services on an incremental phased basis.
1.8Establishment of the framework agreement will place no obligation on the Council to enter into draw down contracts.
1.9The framework agreement has no defined end date other than expiry at completion of the project and may be terminated unilaterally by the Council at any point.
1.10The framework agreement may be used to commission a broad scope of activities which include but are not limited to:
Early contractor involvement activities Assisting the Employer in identifying and securing grant funding and other sources of finance Design co-ordination and progression Engagement with Portsmouth City Council Highways PFI Maintenance Contractor Surveys Capacity modelling Planning application activities Enabling works Stakeholder management Communications Programming & phasing Cost development and control Sub-contract / supply chain engagement and involvement Obtaining required statutory approvals Construction Traffic management Defects management on design & build basis Further maintenance activities as required and agreed
1.11Activities may be sourced via separate contracts using the appropriate NEC4 form of contract or may be grouped together at the Council's option to ensure that the right balance is made in respect of commerciality and risk exposure. 2 www.portsmouth.gov.uk 1.12 Approval is also sought for delegated authority to enable the commencement of initial activities.
Recommendations
The report is looking for Cabinet to:
2.1Agree to the progression and conclusion of the procurement to secure the framework Contractor as outlined above.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.