REPORT TO: PORTCHESTER CREMATORIUM JOINT COMMITTEE
ON: 24 JUNE 2019
REPORT OF: IAN COUSINS, PROPERTY MANAGER
SUBJECT: BUILDING WORKS REPORT
2017/18 Ref Item Description Status Budget Anticipated Variation Commentary £ Cost £ £ 1802 North Chapel refurbishment Design 205,000 154,855 -50145 Minor snagging items have now been completed and the final account has been agreed. 1803 Office Refurbishment On Site 15,000 15,000 0 Works currently on site.
2018 /19 Ref Item Description Status Budget Anticipated Variation Commentary £ Cost £ £ 1901 Glazing Repairs Ordered 25,000 25,000 0 Start date required.
1902 Vestry Refurbishment Feasibility 6,000 6,000 0 Works Programmed for Summer 2019
1903 Paving and Stonework Ongoing 5,000 5,000 0 Further works identified Cleaning programme 1904 Surfacing and Paving Repairs Ongoing 6,000 6,000 0 Works arranged for June or July 2019 programme 1905 Fencing Repairs Feasibility 5,000 5,000 0 Initial works completed
1906 External Redecoration Feasibility 3,000 3,000 0 No works identified at this time.
1907 Fire Precautions Upgrade Feasibility 5,000 5,000 0 Only minor works identified.
ICO 12.06.2019 2019 /20 Ref Item Description Status Budget Anticipated Variation Commentary £ Cost £ £ 2001 Reception Refurbishment Feasibility 5,000 5,000 0 Works due to commence June 2019
2002 Music Room Refurbishment Feasibility 1,000 1,000 0
2003 Book Room Refurbishment Feasibility 2,500 2,500 0
2004 South Chapel New Curtains Feasibility 12,000 12,000 0
2005 Conservatory Redecoration Feasibility 2,500 2,500 0
2006 Area of Contemplation - Feasibility 5,000 5,000 0 The requirement is being developed and a Water Feature Feasibility list of suitable designers is being prepared. 2007 Groundsman Building Repairs Feasibility 6,000 6,000 0
Note - Items previous reported as completed are not shown
Recommendation - That the report be noted
Ian Cousins Property Manager
Background List of Documents – Section 100D of the Local Government Act 1972 - None
ICO 12.06.2019
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Building Works ProgrammeReport | 95 KB | DownloadRead as text |
Follow Portchester Crematorium Joint Committee at Portsmouth and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 13 Dec 2021 | Minutes of the Meeting held on 20 September 2021RESOLVED that the minutes of the meeting held on the 20 September 2021 be signed as a correct record. | Decided | Open |
| 13 Dec 2021 | Finance Strategy and Budget for 2022/23RESOLVED (1) that the Finance Strategy 2022/23, attached as Appendix A to the report, be approved; (2) that the Finan... | Approved | Open |
| 13 Dec 2021 | Revenue Budget Report - 2022/23RESOLVED (a) That the capital works programme as detailed in Appendix D to the report be approved; (b) That the Joint... | Approved | Open |
| 13 Dec 2021 | Manager and Registrar’s ReportRESOLVED that the report be received and noted. | Noted | Open |
| 13 Dec 2021 | Building Repairs and Renewal ProgrammeRESOLVED that the contents of the report be noted and approved. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.