The Cabinet approved: (1) the appointment of the new designer, Haskoning DHV to continue to develop the project in the detailed design stages. (2) Haskoning are internationally recognised design consultants with expertise in the delivery of coastal flood defence schemes both in the UK and abroad. This work is already fully funded through the Council approved Capital Programme, with £2m provided by way of Portsmouth City Council contribution and a further £3.5m of Capital Funding provided by the Environment Agency. Contract value is expected to out-turn at circa £3.6m.
Word for word from the decision Portsmouth published for this meeting.Source: democracy.portsmouth.gov.uk
2.1For Cabinet Members to approve the appointment of the new designer, Haskoning DHV to continue to develop the project in the detailed design stages.
2.2Haskoning are internationally recognised design consultants with expertise in the delivery of coastal flood defence schemes both in the UK and abroad. This work is already fully funded through the Council approved Capital Programme, with £2m provided by way of Portsmouth City Council contribution and a further £3.5m of Capital Funding provided by the Environment Agency. Contract value is expected to out-turn at circa £3.6m.
3. Background Information
3.1The Southsea Coastal Scheme is a significant investment in the infrastructure of the City in order to reduce the risk of coastal flooding and erosion. The scheme covers 4.5km (2.8miles) of coastline from the Royal Garrison Church to the Royal Marines Museum. The scheme is designed to protect over 8,000 properties, 700 businesses, multiple heritage sites and key infrastructure from the risk of flooding. Approximately 4,000 of these properties are at risk of direct threshold inundation from flooding. The seafront, along with Southsea Common, is a focal point for recreation and tourism and is hugely important for the city as an asset and functioning flood defence.
3.2The Southsea Scheme has now completed the principal design and public consultation stages and is moving forward as agreed with the submission of a
1 www.portsmouth.gov.uk major planning application at the end of June. The procurement of a detailed design consultant to continue the good work carried out to date allows the project team maximum flexibility and value for money. The procurement also allows for early contractor involvement and keeps the programme on track for the proposed construction start date in 2020.
3.3Throughout this design process continued consultation will feature as an important element of the work as improvements and enhancements are added to the scheme detailed.
Reasons for recommendation
4.1To allow progression of detailed design, early contractor involvement and the submission of a Full Business Case in October to the Environment Agency, Defra and HM Treasury for approval of construction funding.
5. Equality Impact Assessment
An Equalities Impact Assessment has been undertaken for the scheme at Principal Design stage and further assessments will be undertaken during the Detailed Design process.
Legal implications
6.1The procurement was carried out in line with the Councils procurement code and legal advice received at the time. The reasoning for the recommendation is contained within the procurement gate reports.
7. Director of Finance's comments
7.1The costs of the recommendation within this report will be met from the approved cabinet programme and a grant from the Environment agency as set out in the recommendation of the report.
…………………………………………………………………… Signed by:- Tristan Samuels - Director Regeneration
Appendices
2 www.portsmouth.gov.uk Background list of documents: Section 100D of the Local Government Act 1972
The following documents disclose facts or matters, which have been relied upon to a material extent by the author in preparing this report:
Title of document Location Nil
The recommendation(s) set out above were approved/ approved as amended/ deferred/ rejected by
……………………………… on ………………………………
……………………………………………… Signed by:- Councillor Gerald Vernon - Jackson, Leader of the Council
3 www.portsmouth.gov.uk
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.