Resolved
DECISION The Cabinet d elegated authority to the Director of Regeneration to enter into the construction contract for the , subject to prior approval by the Procurement Gateway Board.
Cabinet approved this item on Tuesday 9 July 2019. Below is the council's own wording, with the papers it was decided on.
Resolved
DECISION The Cabinet d elegated authority to the Director of Regeneration to enter into the construction contract for the , subject to prior approval by the Procurement Gateway Board.
2.1For Cabinet Members to delegate authority to the Director of Regeneration to enter into the Construction contract for the Southsea Coastal Scheme, subject to prior approval by the Procurement Gateway Board.
3. Background Information
3.1The Southsea Coastal Scheme is a significant investment in the infrastructure of the City to reduce the risk of coastal flooding and erosion at Southsea. The Scheme covers 4.5km (2.8miles) of coastline from the Royal Garrison Church to Eastney Barracks. The Scheme is designed to protect over 8,000 properties, 700 businesses, multiple heritage sites and key infrastructure from the risk of coastal flooding. Approximately 4,000 of these properties are at risk of direct inundation from flooding. The seafront, along with Southsea Common, is a focal point for recreation and tourism and is hugely important for the City as an asset and functioning flood defence.
1 www.portsmouth.gov.uk 3.2 The Scheme has completed the Principal Design stage and public consultation moving forward as agreed with the submission of a major planning application at the end of June 2019.
3.3Using the Principal Design, the team has begun a fully OJEU compliant procurement process to appoint a Construction Contractor. A short-listing process has been completed and 3 bidders have been invited to tender for the contract, they are, Van Ord, Bam Nuttall and Boskalis, three internationally recognised coastal flood defence contractors.
3.4Appointment of the Construction Contractor will allow a Full Business Case to be completed and submitted to the Environment Agency for approval to release funding for construction from central government.
3.5The construction contract has been written with a number of break clauses which limit financial commitment and allows the Council to terminate should either the funding not be made available from central government, or the costs of construction for a frontage is not demonstrating Best Value. Appointment of this contract is important to allow Early Contractor Involvement (ECI) work with the Designers to identify savings for the Scheme. This is critical for progression of the Scheme to construction in 2020.
The appointment of a construction contractor will allow Full Business Case completion and submission within the ambitious timescales of the project driven by the Environment Agency Capital programme.
4.1This authorisation allows for Early Contractor Involvement works to be undertaken between the Contractor and Design supplier.
4.2The appointment will identify savings and allow construction to commence in 2020 reducing the risk of flooding in Southsea.
5. Equality Impact Assessment
5.1An Equalities Impact Assessment has been undertaken for the scheme at Principal Design stage and further assessments will be undertaken during the Detailed Design process.
The delegation sought is sensible and the legal implications limited in that the functional decision to commit to contract is, as per the report to vest with the appropriate Director.
2 www.portsmouth.gov.uk 7. Director of Finance's comments
7.1The cost of appointing the contractor will be met from the Southsea Coastal defence capital scheme previously approved by Full Council. There will be no financial or contractual commitment to continue into construction until the Full Business Case has been approved by HM Treasury and Central Government Funding has been awarded. (See 3.5).
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Southsea Coastal SchemeReport | 90 KB | DownloadRead as text |
Follow Cabinet at Portsmouth and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 22 Sep 2026 | Housing & Social Care Scrutiny Panel review "Portsmouth Homes' compliance with the Transparency, Influence & Accountability Standard (Part of the Consumer Standards) - Response reportThanked the Housing and Social Care Scrutiny Panel for its work in undertaking the review and for the report; and 2. ... | Noted | Open |
| 22 Sep 2026 | Publicising Fly Tipping & Environmental Crime Cases PolicyApproved and adopted the Publicising Fly Tipping and Environmental Crime Cases Policy effective from 23 September 202... | Approved | Open |
| 21 Jul 2026 | Carbon Action PlansNoted the report which is for information and is not subject to call-in. | Noted | Open |
| 21 Jul 2026 | Education, Children & Young People Scrutiny Panel review "Increasing accessibility in Portsmouth's play parks" - Response reportThanked the panel for its work in undertaking the review. 2. Noted and considered the conclusions and recommendations... | Noted | Open |
| 21 Jul 2026 | Treasury Management Outturn Report 2025/2026Noted the actual prudential and treasury management indicators based on the unaudited accounts, as shown in Appendix ... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.