(1) That the Economic Development, Culture & Leisure (EDCL) Panel be thanked for its work in undertaking the review; (2) That the EDCL Scrutiny Panel's recommendations be approved in line with the responses noted in section 4 of the response report by the Port Director.
Word for word from the decision Portsmouth published for this meeting.Source: democracy.portsmouth.gov.uk
The Economic Development Culture and Leisure Scrutiny Panel conducted a review into Portsmouth International Port set by the panel in 2017 and completed in Feb 2019, therefore crossing the municipal years 2017-18 and 2018-19.
Purpose of report
The purpose of the report is to respond to the Economic Development Culture and Leisure Scrutiny Panel in respect of the recommendations outlined in the final report.
Recommendations
(1) That the Panel is thanked for its work in undertaking the review:
(2) That the Economic Development Culture and Leisure Scrutiny Panel's recommendations be approved in line with the responses noted in item 4 below.
Background
The Economic Development Culture and Leisure Scrutiny Panel set the objectives noted below.
Objective 1 – To consider business development, including cruise market ambitions, linking with Council’s tourism and marketing strategies and developments to attract new business.
1 www.portsmouth.gov.uk Objective 2 – To examine the importance of the port locally.
Objective 3 – To investigate the challenges and opportunities of the European trading negotiations/Brexit.
Objective 4 – To consider the issue of unaccompanied minors located at the port and to ensure there is a timely response to secure their safety.
Objective 5 – To hear of recent and future investment plans for the port (and funding implications for the City Council).
5. Panel’s recommendations and response
Recommendation 1:
Capital improvement works be continued, subject to finances, to enhance facilities to bring these up to a competitive standard and pursue the new passenger boarding tower as part of the Transformation Plans to help reach the target of over 100 cruise calls per annum.
Response:
I am pleased to advise that the port’s capital programme (2018/19 bids approved - £6m for the passenger boarding tower and £12.7m for Cruise Expansion) has commenced with the development of the cruise berth commencing November 2019. Cruise development works are expected to be completed by Spring 2021. Furthermore, the port’s significant customer Brittany Ferries extended their agreement to 31st December 2031 which helps underpin part of the investment in the passenger boarding tower which is expected to be completed in 2022. Additionally, most recently, a new long term agreement has been achieved at Portico Shipping Ltd which will see the return of Geest Line to the port from January 2020. A loan facility for Portico of £15 million was agreed by Council in Feb 2019 subject to long-term sustainable agreements helping to underpin investments.
Recommendation 2:
Air quality at PIP should continue to be monitored as this is essential for the city and campaigns take place to tackle vehicle emissions on-site.
Response:
Air Quality Action Plan being delivered as part of the Clean Maritime Plan, to be submitted to the DfT by July 2020.
2 www.portsmouth.gov.uk Capital funding will need to be identified to assist with the action plan. Although voluntary at this stage, Portsmouth International Port will commit to the Clean Maritime Plan with the intention of being the first zero emission major port in the UK.
Recommendation 3:
Sustainable links should continue to be investigated for cruise passengers to use such as a water bus routes as well as shuttle buses. Response:
New bus contract at port is due for renewal in 2020 and will have as a minimum euro 6 compliant vehicles.
Water shuttles are being offered to visiting cruise vessels the cost of which is taken from the port’s budget.
Recommendation 4:
Use the knowledge being obtained from local market focus groups in the wider region to publicise the advantages of travelling from Portsmouth as a local port.
Response:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
8Directors' Response report to the Economic Development, Culture & Leisure (EDCL) Scrutiny Panel's review of Portsmouth International PortThis decision
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.