Cabinet: (1) Approved the strategic direction to PCC's Covid-19 transport response as set out in the draft Transport Recovery Plan; (2) Approved the delivery of the proposed temporary measures, and process for prioritising further measures as set out in the draft ; (3) Noted that the measures proposed within the draft are intended as temporary measures to be implemented quickly in response to public health concerns and to support the city's economic recovery. Therefore proposals will not be subject to the usual public consultation process prior to implementation; (4) Noted that proposals in the draft Transport Recovery Plan are conditional upon sufficient funding being provided secured through government's Emergency Active Travel Fund; (5) Gave delegated authority to the Assistant Director for Transport to amend the draft in line with the recommendations of Cabinet and in relation to the agenda item on LTP4 for this decision meeting.
Word for word from the decision Portsmouth published for this meeting.Source: democracy.portsmouth.gov.uk
1.1In response to the transport challenges faced by the Covid-19 pandemic, Portsmouth City Council has produced a draft Transport Recovery Plan, in line with government's recommendations for encouraging safe and sustainable travel as the city recovers from lockdown.
1.2This report outlines the content of the draft Portsmouth Transport Recovery Plan, including proposed temporary measures to assist with the economic recovery of the city. This report will also set out how the draft Transport Recovery Plan fits with the emerging Local Transport Plan 4 (LTP4) and the wider transport policy framework.
Recommendations
It is recommended that Cabinet:
2.1Approves the strategic direction to PCC's Covid-19 transport response as set out in the draft Transport Recovery Plan;
2.2Approves the delivery of the proposed temporary measures, and process for prioritising further measures as set out in the draft Transport Recovery Plan;
2.3Note that the measures proposed within the draft Transport Recovery Plan are intended as temporary measures to be implemented quickly in response to public health concerns and to support the city's economic recovery. Therefore proposals will not be subject to the usual public consultation process prior to implementation;
1 www.portsmouth.gov.uk 2.4 Note that proposals in the draft Transport Recovery Plan are conditional upon sufficient funding being provided secured through government's Emergency Active Travel Fund;
2.5Give delegated authority to the Assistant Director for Transport to amend the draft Transport Recovery Plan in line with the recommendations of Cabinet and in relation to the agenda item on LTP4 for this decision meeting.
Background
3.1Following the announcement from the Government in mid-May regarding the gradual easing of the lockdown restrictions implemented in response to the Covid-19 Pandemic, Local Transport Authorities were advised to commence planning to ensure that local transport networks were prepared for the change in travel demand.
3.2Since the government introduced lockdown measures, use of motorised traffic in the city has decreased to as low as 34% of pre-lockdown levels and cycling numbers have increased to as much as 156% compared to last year. However, as restrictions on movement are loosened traffic volumes are continuing to rise with 87% of pre-lockdown traffic now back on the main roads around the city.
3.3The Department for Transport has outlined a number of areas which need to be considered in preparation for the local transport restart, and in particular in response to the green and active travel agenda to ‘help embed altered behaviours and demonstrate the positive effects of active travel’ as requested by Transport Minister Grant Shapps: Collaboration Green Transport Restart and Recovery E-Scooters Data and Evidence Public Transport Travel Planning Role of the Car Transport Users Resources
3.4The Transport Recovery Plan seeks to address these points, setting out the transport measures that have been delivered and are proposed to help start the economic recovery of the city.
4.0Relationships with Local Transport Plan 4
4.1On 10th March 2020 Portsmouth City Council Cabinet considered and approved the draft vision and objectives for Local Transport Plan 4 (LTP4). The LTP sets out the transport strategy for the city and under the Transport Act 2000 as amended by Local Transport Act 2008 Portsmouth City Council has a statutory duty to produce a LTP for Portsmouth, and to keep it under review. LTP4 will 2 www.portsmouth.gov.uk replace the current LTP3 (2011-2031), presenting the strategic direction for transport policy in the city up until 2036.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.