(1) The Cabinet Member for Housing approved Capital Expenditure of £ 5.1m, to deliver 6 new properties housing 24 adults with Learning disabilities and/or physical disabilities comprising of four, 4 bed shared flats and two, 4 bed shared bungalows to be held in the Supported Housing Portfolio within the Housing Revenue Account. (2) The Cabinet Member for Housing delegated authority to the Director Housing, Neighbourhood and Building Services in consultation with the Director of Finance and Resources & S151 Officer to amend the composition and spending profile of the proposed schemes in order to meet planning and design requirements and also to agree the use of either grant funding or 141 receipts whilst ensuring that the schemes remain financially viable following any necessary changes. (3) The Cabinet Member for Housing delegates the Director of Housing, Neighbourhood and Building to apply for any grant funding to support the scheme. (Note: for future meetings the Cabinet Member will be referred to as the Cabinet Member for Housing and Preventing Homelessness as announced at full Cabinet on 14 th July 2020 which was after publication of this agenda and report)
Word for word from the decision Portsmouth published for this meeting.Source: democracy.portsmouth.gov.uk
1.1To seek approval from Cabinet Member for Housing to instruct Housing, Neighbourhood and Building's Design Team to deliver a new supported housing development of four, 4 bed flats and two, 4 bed bungalows on the redundant Highgrove Lodge site.
1.2To seek approval of the financial appraisal delivering 6 new properties, this in turn delivers new homes for 24 adults with either learning disabilities and/or physical disabilities within the Supported Housing Portfolio.
Recommendations
2.1That the Cabinet Member for Housing approves Capital Expenditure of £5.1m, to deliver 6 new properties housing 24 adults with Learning disabilities and/or physical disabilities comprising of four, 4 bed shared flats and two, 4 bed shared bungalows to be held in the Supported Housing Portfolio within the Housing Revenue Account.
2.2That the Cabinet Member for Housing delegates authority to the Director Housing, Neighbourhood and Building Services in consultation with the Director of Finance and Resources & S151 Officer to amend the composition and spending profile of the proposed schemes in order to meet planning and design requirements and also to agree the use of either Grant funding or 141 receipts whilst ensuring that the schemes remain financially viable following any necessary changes.
2.3That the Cabinet Member for Housing delegates the Director of Housing, Neighbourhood and Building to apply for any grant funding to support the scheme. 1 www.portsmouth.gov.uk 3. Background
3.1The was a desire in 2016 to deliver a general needs housing scheme on this site, outlining plans and a cost estimate of £2,585,000 were completed and the scheme was detailed in the capital budget from 1st April 2017.
3.2This site then stalled due to it being within flood zone 3 and the original proposal was shelved. The Environment agency have since redrawn their maps and the flood zone has reduced, this alongside the development on the old dairy site gives confidence to a new development going forward. The scheme was reappraised in late 2018 and was identified as an ideal location for a supported housing development.
3.3The location and site are ideally suited to a supported housing development and following the completion of the feasibility study, permission is sought to progress the scheme to deliver supported housing for adults with learning disabilities and/or physical disabilities. As this build delivers new homes across both PCC and the Clinical Commissioning Group (CCG), a working group has been set up comprising of Housing, Neighbourhood and Building Services and colleagues from Adult Social Care and the Clinical Commissioning Group (CCG).
3.4Consultation with ward councillors and portfolio members was completed in March 2020 prior to the Covid-19 pandemic, at this briefing all parties were made aware of the scheme and all expressed support.
3.5A financial appraisal has been completed showing the scheme will deliver savings to the general fund of £96,256 per annum, plus £412,000 to the CCG. The savings are estimated to deliver at 80% in 2023/24 as the supported housing business partner allows a six month building occupation, as it is not viable to move 24 adults simultaneously, therefore the full savings being realised in 2024/25. The building also generates a yearly rental yield of £144,000 to the Housing Revenue Account, based on current rent charges. The savings are generated through reduced care costs, these can be from no longer paying hotel charges by moving to supported living or from the economies of providing care to a number of people within the same home.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Temporary Accommodation Placement PolicyThe Cabinet Member for Housing (1) recognises the important role that temporary accommodation has in supporting peopl...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.