a) The progress since September 2019 described in paragraph 3.7 was noted in conjunction with the 4-month delay caused by the Covid-19 pandemic; (b) The amended Programme set out in Table 1 (page 4 of the report) was agreed and consultation continues within the rolling programme until a point where RPZs are not wanted or needed by residents in the areas referred to, and; (c) If the work stream set out in Table 1 reaches a point where RPZs are not wanted or needed by residents, the next area to be considered will be the area with the highest priority score shown in Table 2 (page 5).
Word for word from the decision Portsmouth published for this meeting.Source: democracy.portsmouth.gov.uk
1.1The purpose of the report is to provide an update on the progress of the Residents' Parking Programme of Consultation and to recommend adjustments as a result of changes since the reprioritisation report of September 2019.
Within this report, RPZ means Residents' Parking Zone.
Appendix A: Revised Residents' Parking Programme map; a visual representation of this report showing existing RPZs and the areas identified for consultation.
2. Recommendations It is recommended that:
(a) The progress since September 2019 described in paragraph 3.7 is noted in conjunction with the 4-month delay caused by the Covid-19 pandemic;
(b) The amended Programme set out in Table 1 (page 4) is agreed and consultation continues within the rolling programme until a point where RPZs are not wanted or needed by residents in the areas referred to, and;
(c) If the workstream set out in Table 1 reaches a point where RPZs are not wanted or needed by residents that the next area to be considered is the area with the highest priority score shown in Table 2 (page 5).
1 www.portsmouth.gov.uk 3. Background
3.1On the 6 September 2019 a reprioritised Residents' Parking Programme of Consultation was agreed by the Cabinet Member for Traffic and Transportation. The report responded to a Full Council motion passed 16 July 2019 which stated "The Council notes the continuing piecemeal expansion of residents’ parking across the city. It remains concerned that this is being implemented in an unplanned and uncoordinated way. It therefore calls on the Cabinet Member for Traffic and Transportation to draw up and publish a strategic plan for the management of parking in residential and non-residential areas covering a period of at least five years."
3.2This report reiterates the strategy developed for considering requests for new RPZs from across the City, prioritising issues of displacement as part of a rolling programme and setting a priority matrix for evaluating new requests. It remains likely that the Programme will take many years to implement and the precise time will depend on how many areas will require action.
3.3In September 2019 the work was divided into workstreams; one focusing on Southsea parking zones prefixed with "M" and a second focusing on Baffins/Copnor parking zones prefixed with "H".
3.4In addition, it was the intention to appoint consultants to engage with local people within existing parking zones, on how their operation could be improved, however pressure from the other workstreams has meant this has not progressed and with financial pressure caused by the Covid 19 this needs to wait until funding or resources are available.
3.5The consultations within the 'M' workstream were progressed as per the timetable set out in the reprioritisation report of September 2019 until the end of March 2020 when it was effectively stopped by the Covid-19 pandemic.
3.6The 'H' workstream focused on the area identified as HC Kendal Ave with the intention to consult in other areas if there was displacement from a new RPZ in HC. A programme was therefore developed to address displacement if HC was implemented. As with the 'M' workstream, it was proposed that the 'H' workstream consultations would progress until a point was reached where an RPZ was not needed or supported by residents.
3.6.1 The informal survey indicated that most residents would be in favour of an RPZ in HC, and therefore a parking zone was developed and put to formal consultation via traffic regulation order.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Tertiary Roads Inspection and RepairDecision The Cabinet Member: 1. Approved that the plans and timings of inspections of the tertiary road network are s...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.