Cabinet 1. Noted that the Examination of the Aquind Interconnector Project has started 2. Noted the future timelines for the examination. 3. Agreed that the Council should continue to represent the interests of the people of Portsmouth and maintain its opposition to the proposal.
Word for word from the decision Portsmouth published for this meeting.Source: democracy.portsmouth.gov.uk
Subject: An update on the Aquind Interconnector Project
Report From: The Chief Executive
Report by: Paddy May, Strategy Unit
Wards affected: All
Key decision: NO
Full Council decision: NO
1. Purpose of report 1.1. The purpose of this report is to update Cabinet on the Aquind Interconnector Project, to explain some of the activity that has been undertaken and to highlight the future timeframes.
2. Recommendations 2.1. Cabinet is recommended to: 2.1.1 Note that the Examination of the Aquind Interconnector Project has started 2.1.2 Note the future timelines for the examination 2.1.3 Agree that the Council should continue to represent the interests of the people of Portsmouth and maintain its opposition to the proposal
3. Background 3.1 As previously reported to Cabinet, Aquind are proposing to construct and operate an underground and marine electricity interconnector between the south coast of England and Normandy in France (the AQUIND Interconnector). This interconnector will have capacity to transmit up to 16 million MWh (or 16 TWh) of electricity annually or approximately 5% of Great Britain’s total electricity consumption and 3% of the French total electricity consumption. The technology used will allow the flow of electricity both ways. Aquind are proposing that the interconnector cable will come ashore at Eastney and that the cable will run up through Portsmouth to a converter station in Lovedean. 3.2 Cabinet received reports on the Aquind Ltd proposal at their meetings on 9th July 2019 and 5th November 2019 and there has been a separate MIS Item on Aquind (MIS dated 28/8/20).
Page 1 3.3 At the meeting in July 2019, Cabinet decided the following: - Noted that Aquind are seeking to develop an electricity Interconnector between the UK and France with a converter station in Lovedean. They are proposing to "land" the high voltage DC (HVDC) electricity cable at Eastney and run it up through Portsmouth to the converter station at Lovedean. - Noted that despite representations from Portsmouth City Council that the Aquind proposal should be determined by the relevant local planning authorities (including Portsmouth City Council), the Government has decided that the proposal was a 'Nationally Significant Infrastructure Project' that should be determined by the Secretary of State through the Development Consent Order process. - Agreed to seek the support of Full Council to reinforce the Cabinet's objection to the route of the HVDC cable whilst also working constructively with Aquind and other stakeholders. - Agreed that the Council responds to this proposal in a coordinated way and where possible works with neighbouring councils on any common approaches. - Noted that any additional external costs incurred in the current year associated with the need to make an informed and considered response to the proposal will be met from the Council's Corporate Contingency.
3.4When the project was discussed at Full Council on 16th July 2019 the following motion was unanimously agreed: RESOLVED that Full Council reinforce the Cabinet's objection to the route of the HVDC cable whilst also working constructively with Aquind and other stakeholders.
3.5At the meeting in November 2019 Cabinet resolved that the Council should maintain its opposition to the proposed project and to delegate authority to officers to enable timely responses to be made to the Planning Inspectorate whilst it is undertaking the Examination of the proposal as part of the DCO process.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.