DECISION: The Cabinet Member approved the following (1) That 1-3 Angerstein Road be transferred freehold to Vivid Homes (2) That the Director for Housing, Neighbourhoods and Buildings agree an arrangement that ensures Portsmouth has nomination rights to allocate the properties in line with Portsmouth City Council's Allocations Policy. (3) Authority is given to the City Solicitor to complete all necessary legal work to complete this matter
Word for word from the decision Portsmouth published for this meeting.Source: democracy.portsmouth.gov.uk
1.1To update members on the proposed transfer of 1-3 Angerstein Road (Appendix A) to the Portsmouth Community Housing Trust, and
1.2To seek approval to alter the terms of the proposed transfer from the previously agreed member authority, Resources Portfolio 20th December 2018.
Recommendations
It is recommended that the Cabinet Member for Communities and Central Services approves the following;
2.1That 1-3 Angerstein Road be transferred freehold to Vivid Homes.
2.2That the Director for Housing, Neighbourhoods and Buildings agree an arrangement that ensures Portsmouth has nomination rights to allocate the properties in line with Portsmouth City Council's Allocations Policy.
2.3Authority is given to the City Solicitor to complete all necessary legal work to complete this matter.
1 www.portsmouth.gov.uk 3. Background
3.1The premises are held in the general fund portfolio and were previously used for a charitable purpose.
3.2The previous report to the Resources committee 20th December 2018 details the background to the councils housing need and explains the proposed transfer to the Portsmouth Community Housing Trust (PHCT), a Community Land Trust.
3.3Since that earlier decision by the Resources committee negotiations have progressed slowly with PHC. The Councils legal advice at the time was to enter into an agreement for lease, and once the necessary construction had been completed by PHCT, thereafter a long lease. Unfortunately PHCT were unable to carry out the works and spend the funds required under the proposed structure.
3.4To ensure access to funding and the ability to operate these units, PHCT are in the process of applying for Registered Provider Status via Homes England. This process may take up to 18 months.
3.5As an interim measure Homes England and Vivid Homes have agreed to support PHCT through the initial process by funding the work in advance of PHCT achieving Registered Provider Status. This forward funding is backed up by the freehold being transferred to Vivid. On this basis Vivid will then be able to fund the work required.
3.6Vivid and PCHT will enter into a simultaneous agreement that enables the premises to be transferred to the PHCT at a fee to cover Vivid's costs and in the event that PHCT fail to register within two years Vivid will retain ownership and either continue to manage the properties with PCC nomination rights insitu or agree an extension with PHCT.
Reasons for recommendations
4.1PHCT are unable to proceed with the previously approved proposal and would like the Council support to approve this new proposal that allows them to fulfil their ambition to repair and maintain the units.
4.2The proposal demonstrates the Councils ability to work with the community sector and other housing providers to find an equitable solution.
4.3In the event the premises are not transferred the Council will face significant expenditure to repair or demolish the premises.
5. Integrated impact assessment
2 www.portsmouth.gov.uk 5.1 This proposal does not alter the original IIA included in the 2018 report.
Legal implications
6.1The proposal would fall within the competency of the Authority to make and is a practical solution to the problems as articulated in the body of the report. There are no other relevant issues.
7. Director of Finance's comments
7.1The previous report 20th December 2018 approved the recommendation of the transfer of a long leasehold of these properties, it set out that the properties would require significant investment to bring them back into a state that would allow them to generate any income, and furthermore the market value of them is less than the cost to bring them to an operational state or for us to recoup their costs if we were to sell the properties once converted. The Trust are now requesting that instead of a long leasehold that we transfer the freehold
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Queen's Platinum Jubilee EventsRESOLVED that the Cabinet Member agreed to: (i) Note the success of the delivery of the Queen's Platinum Jubilee prog...
Proposed Sister City Link with Cape TownRESOLVED that the Cabinet Member recommended that the Leader of the Council, the Lord Mayor and Lady Mayoress write a...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.