HRA Fire Safety Improvement Programme

Noted Committee 1 paper

Housing and Preventing Homelessness noted this item on Monday 8 March 2021. Below is the council's own wording, with the papers it was decided on.

Item14

Resolved

The Cabinet Member noted the report. The report is for information only and is not subject to call-in.
Word for word from the decision Portsmouth published for this meeting. Source: democracy.portsmouth.gov.uk

Follow this further

Built from Portsmouth's papers

What the report saysPro

Report to Housing and Preventing Homelessness

THIS ITEM IS FOR INFORMATION ONLY (Please note that "Information Only" reports do not require Integrated Impact Assessments, Legal or Finance Comments as no decision is being taken)

Title of meeting: Cabinet member for Housing and Preventing Homelessness

Subject: Fire Safety Improvement Programme

Date of meeting: 8th March 2021

Report by: James Hill - Director of Housing, Neighbourhood and Building Services

Report Author: Steve Groves - Head of Building Maintenance

Wards affected: All

1. Requested by Darren Sanders, Cabinet Member for Housing and Preventing Homelessness

2. Purpose

2.1The Cabinet Member for Housing and Preventing Homelessness has requested a summary of the fire safety improvement programme and investment that is planned for Council owned HRA block of flats.

2.2The report provides an update on work already agreed and new work planned. The report notes the impact of the pandemic on the progress of the programme and sets out the plan to take the work forward.

2.3The report provides information against the following elements of the fire safety programme of work

2.3.1 Section 3 - Fire Safety Strategy 2.3.2 Section 4 - Sprinkler Retrofit Programme 2.3.3 Section 5 - Fire Door Replacement Programme 2.3.4 Section 6 - External Panel Replacement Programme 2.3.5 Section 7 - Resident Engagement

2.4It also includes the blocks that will benefit from the programme and start dates, thus:

1 www.portsmouth.gov.uk THIS ITEM IS FOR INFORMATION ONLY (Please note that "Information Only" reports do not require Integrated Impact Assessments, Legal or Finance Comments as no decision is being taken) 2.4.1. Sprinkler retrofit installations

2021/2022  Ladywood House  Handsworth House

2022/2023  Mill Gate House  Sarah Robinson House  The Underground Car Parks At Grafton Street, Estella Road, Westminster Place And Wingfield Street

2023/2024  Nickleby House  Barkis House  Tipton House  Edgbaston House

2024/2025  Copperfield House  Pickwick House

2.4.2. Fire door replacement

2021/2022  Hale Court  St John's Court  Thorrowgood House

2022/2023  Escur Close (1-47 Odds)  The Ridings (109-155 Odds)  Copperfield House  Pickwick House  Nickleby House  Barkis House

2023/2024  Mill Gate House  Sarah Robinson House  Ladywood House  Handsworth House

2 www.portsmouth.gov.uk THIS ITEM IS FOR INFORMATION ONLY (Please note that "Information Only" reports do not require Integrated Impact Assessments, Legal or Finance Comments as no decision is being taken) 2024/25  Tipton House  Edgbaston House

2.4.3. Panel replacement schemes

2021/2022 Phase One  Ladywood House  Handsworth House  Sarah Robinson House

Phase Two  Westminster Street (1-78)  Wingfield Place (1-71)

2022/2023 Phase Three  Estella Road (1-189)  Grafton Street (2-238)

Phase Four  Hawthorn Crescent (475-522)

3 Fire Safety Strategy

3.1HNB undertake Fire Risk Assessments (FRA) to all relevant properties under the Regulatory Reform (Fire Safety) Order 2005 and implement appropriate fire measures to the common parts of all blocks of flats to minimise the risk of injury or loss of life in the event of a fire.

3.2The FRA is a Type 1 non-destructive survey to the common parts of blocks of flats using the PAS79:2012 template, which is not an intrusive survey. A review of an FRA will be undertaken whenever a significant change has occurred to a block of flats or asset but will not exceed 3 years from the original FRA. A more frequent review will be carried out if deemed appropriate by the surveyor undertaking the original FRA.

3.3The FRAs for higher risk assets such as blocks of flats that are six storeys and above, sheltered blocks, houses in multiple occupation or offices, will be undertaken by appropriately experienced third party registered fire risk assessors. FRA for lower risk assets such as blocks of flats that are five storeys and below, are undertaken by in-house building surveyors who have completed appropriate training to demonstrate their competence.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
HRA Fire Safety Improvement ProgrammeReport 188 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

3 of 3 attended
DS
Councillor Darren SandersCabinet Member, present
CC
Councillor Cal CorkeryOpposition spokesperson, present
SP
Councillor Scott Payter-HarrisOpposition spokesperson, present

More from Portsmouth Housing and Preventing Homelessness

All decisions
MeetingDecisionOutcome
23 Mar 2023 Updated Safeguarding Policy for the Play, Youth and Community Services (PYC)Decision The Cabinet Member: · Approved the policy attached and marked as Appendix A. Approved Open
23 Mar 2023 Update on Housing Revenue Account Asset Management StrategyDecision The Cabinet Member: · Noted the information only report. Noted Open
23 Mar 2023 Private Rental Sector Mediation Pilot for PortsmouthDecision The Cabinet Member: · Noted the information in the report regarding the demand for the mediation service and... Noted Open
2 Feb 2023 Park Homes Pitch Fee Review 2023The Cabinet Member agreed to Option 1: Increase Park Homes pitch fees by 6% from 1April 2023. Agreed Open
2 Feb 2023 Private Sector Housing Fees and ChargesThe Cabinet Member: 1. Approved the proposals for PSH fee adjustments for the city council's mandatory HMO licensing ... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies