Resolved
DECISIONS 1. The Cabinet approves the second phase of Bike Hangars to be delivered as set out in section 9. 2. The scheme currently in place under an ETRO is make permanent.
Cabinet approved this item on Tuesday 2 November 2021. Below is the council's own wording, with the papers it was decided on.
Resolved
DECISIONS 1. The Cabinet approves the second phase of Bike Hangars to be delivered as set out in section 9. 2. The scheme currently in place under an ETRO is make permanent.
1.1The purpose of this report is to make recommendations for the future Portsmouth City Councils Bike Hangar pilot and to receive approval for a further eight hangars to be installed with funding from the 2021 Capability Fund allocation.
2.1The Cabinet approve the second phase of Bike Hangars to be delivered as set out in section 9.
2.2The scheme currently in place under an ETRO is made permanent.
3.1The lack of safe, secure and high quality cycle parking both at destinations (commercial/retail centres, transport hubs) and at home is a barrier to cycling.
3.2Lack of storage space is a key barrier to cycling in the city; A pilot was designed to enable those residents without this storage space to be able to keep their bike securely, close to home.
3.3The pilot was launched in spring 2021 introducing secure on-road cycle parking in 8 locations in the city
3.4The pilot project goals were to:
• Establish successful template for the wider rollout of secure resident on street cycle parking in Portsmouth • Learn and document potential issues • Demonstrate viability and demand
3.5Funding for the pilot enabled the purchase of nine hangars, installed on eight roads across the city in March 2021:
1. Manners Road x1 2. Lucknow Street x1 3. Eastfield Road x1 4. Addison Road x2 5. Hunter Road x1 6. Clarence Road x1 7. Guildford Road x1 8. Sultan Road x1
The locations were determined by resident requests, and assessment of the degree to which the following criteria were met:
1. Located within high density residential area of Portsmouth 2. Requested by local residents or Cllrs/Portfolio Holder etc. 3. Accommodation on road predominantly without easy access e.g. flat fronted terrace, flats
3.6Following increased numbers of requests, our pilot was developed to test the use of this infrastructure in the city, with a view to a much wider future roll out.
3.7Three providers were chosen with three different approaches to on street hangars. The companies were Falco, Cyclehoop and Cycleworks, and were chosen to for the pilot to understand what would work best in the city. To assess which company to move forward with council officers assessed: • ease of install • council interaction • speed of service • maintenance ability • service user interaction • cost • resident feedback The anecdotal evidence and survey analysis will form the criteria to determine the final product which will be rolled out in the next phases of cycle hangars as set out in the accompanying document. The different types of hangars which were installed can be seen in Appendix (A)
3.86 were installed in front of requestor properties with 3 being placed within the closest vicinity to the requestor.
3.9In July 2021 a survey was sent to all the residents and current users of cycle Hangars to gather feedback from the first 4 months of the trial which will form part of this document. A report was formed from this survey and has been included in appendix (B)
3.10The statutory public consultation was undertaken through an experimental traffic regulation order (ETRO) running for the duration of the trial alongside the online surveys. Residents living within 150 metres of a bike hangar location received consultation documents.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Bike Hangar Pilot Scheme: Phase 1 review and recommendations for Phase 2Report | 1.6 MB | DownloadRead as text |
PDF |
Cab 2 Nov 21 bike hangar Integrated Impact AssessmentReport | 140 KB | Download |
Follow Cabinet at Portsmouth and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 22 Sep 2026 | Housing & Social Care Scrutiny Panel review "Portsmouth Homes' compliance with the Transparency, Influence & Accountability Standard (Part of the Consumer Standards) - Response reportThanked the Housing and Social Care Scrutiny Panel for its work in undertaking the review and for the report; and 2. ... | Noted | Open |
| 22 Sep 2026 | Publicising Fly Tipping & Environmental Crime Cases PolicyApproved and adopted the Publicising Fly Tipping and Environmental Crime Cases Policy effective from 23 September 202... | Approved | Open |
| 21 Jul 2026 | Carbon Action PlansNoted the report which is for information and is not subject to call-in. | Noted | Open |
| 21 Jul 2026 | Education, Children & Young People Scrutiny Panel review "Increasing accessibility in Portsmouth's play parks" - Response reportThanked the panel for its work in undertaking the review. 2. Noted and considered the conclusions and recommendations... | Noted | Open |
| 21 Jul 2026 | Treasury Management Outturn Report 2025/2026Noted the actual prudential and treasury management indicators based on the unaudited accounts, as shown in Appendix ... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.