1) Noted that the previous decision taken on the 2 February 2021 is no longer deliverable, as the previously agreed terms and conditions that underpinned that decision have now been varied by one of the parties. 2) Approved a new recommendation to dispose of the former Portsmouth Craft and Manufacturing Industries Site, as per the terms agreed and set out in the Cabinet Report 'Cosham Development Sites' 2 February 2021, to be completed as soon as possible to enable the Hampshire & Isle of Wight Fire and Rescue Service to progress with the development of their new Fire Station. 3) Agreed new recommendations for Portsmouth City Council to acquire the existing Police and Fire sites via separate contractual agreements still to be negotiated. 4) Delegated to the Director of Regeneration in consultation with the Leader of the Council and the Section 151 Officer to negotiate and agree terms with Hampshire Constabulary (HC) to secure development through acquisition or via other contractual means, of the existing Cosham Police Station. 5) Delegated to the Director of Regeneration in consultation with the Leader of the Council, and the Section 151 Officer to negotiate and agree terms with Hampshire & Isle of Wight Fire and Rescue service for the acquisition of the existing Cosham Fire Station. 6) Delegated to the Director of Regeneration, the Section 151 Officer and the City Solicitor authorisation to finalise negotiations, prepare and complete the necessary documentation to give effect to 2), 3), 4) and 5) above. 7) Noted that the promoter team remain committed to development principles established by the work of the Cosham Working Group currently being consulted on with the local community, subject to the properties being available to purchase as previously agreed.
Word for word from the decision Portsmouth published for this meeting.Source: democracy.portsmouth.gov.uk
1.1This report updates members on the Cosham land assembly sites that form the intended strategic regeneration area and recommends the immediate disposal of the former PCMI site to Hampshire & Isle of Wight Fire and Rescue service (HIWFR).
1.2This is a deviation from the recommendations previously approved in the Cabinet resolution of the 2nd February 2021.
Recommendations
The Cabinet is asked to;
2.1Note that the previous decision taken on the 2nd February 2022 is no longer deliverable, as the previously agreed terms and conditions that underpinned that decision have now been varied by one of the parties.
2.2Approve a new recommendation to dispose of the former Portsmouth Craft and Manufacturing Industries Site, as per the terms agreed and set out in the Cabinet Report 'Cosham Development Sites' 2nd February 2021, to be completed as soon as possible to enable the Hampshire & Isle of Wight Fire and Rescue Service to progress with the development of their new Fire Station.
2.3Agree new recommendations for Portsmouth City Council to acquire the existing Police and Fire sites via separate contractual agreements still to be negotiated.
2.4Delegate to the Director of Regeneration in consultation with the Leader of the Council and the Section 151 Officer to negotiate and agree terms with Hampshire Constabulary (HC) to secure development through acquisition or via other contractual means, of the existing Cosham Police Station.
1 www.portsmouth.gov.uk 2.5. Delegate to the Director of Regeneration in consultation with the Leader of the Council, and the Section 151 Officer to negotiate and agree terms with Hampshire & Isle of Wight Fire and Rescue service for the acquisition of the existing Cosham Fire Station.
2.6Delegate to the Director of Regeneration, the Section 151 Officer and the City Solicitor authorisation to finalise negotiations, prepare and complete the necessary documentation to give effect to 2.2, 2.3, 2.4 and 2.5 above.
2.7Note that the promoter team remain committed to development principles established by the work of the Cosham Working Group currently being consulted on with the local community, subject to the properties being available to purchase as previously agreed.
Background
3.1The Cabinet report dated 2nd February 2021 entitled Cosham Development Sites sets out the strategic opportunity and rationale behind public sector land assembly in Cosham. The report and agreed recommendations is attached in appendix A.
The Opportunity
3.2The Cosham Opportunity Area has been in discussion with strategic health and blue light partners for a number of years, since having featured as part of the 2012 Local Plan. More recently, it was consulted on as part the Regulation 18, as part of the emerging local plan. The opportunity area has always lacked a vacant site to kick-start the chain and in 2020 the Council, by shelving its own housing plans on the PCMI site in favour of supporting the development of a new Blue light Hub led by the Hampshire Fire and Rescue Service has taken the first steps to realising the wider benefits the opportunity area could offer.
3.3To ensure these benefits were realised, the One Public Estate (OPE) team led by the Council, with the agreement of the Portsmouth Health and Social Care Executive (now Joint Commissioning Board) endorsed the creation of a Cosham Working Group (CWG) chaired by the council to explore the Cosham opportunity (see CWG report in appendix B). The CWG report includes the background to the work of the group and also the terms of reference for the partners engaged in the work of the group.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.