Decision The Cabinet Member for Traffic & Transportation: 1. Noted the contents of the report 2. Noted that the Department for Transport required additional text in the Enhanced Partnership Plan and Scheme. 3. Approved the Enhanced Partnership Plan and Scheme. 4. Approved the implementation of the ... view the full minutes text for item 46.
Word for word from the decision Portsmouth published for this meeting.Source: democracy.portsmouth.gov.uk
1.1This report seeks approval for the implementation of the Enhanced Partnership Plan and Scheme for bus services in Portsmouth as approved by Cabinet on 21 June 2022 and following statutory consultation.
Recommendations
It is recommended that the Cabinet Member for Traffic and Transportation:
2.1Notes the contents of this report;
2.2Notes that the Department for Transport require additional text in the Enhanced Partnership Plan and Scheme;
2.3Approves the Enhanced Partnership Plan and Scheme as attached;
2.4Approves the implantation of the Enhanced Partnership Plan and Scheme from 8 December 2022.
Background
3.1On 4 April 2022, Portsmouth City Council was advised that it had been offered an indicative funding allocation of up to £48,349,526 towards its Bus Service Improvement Plan (BSIP). Funding confirmation is conditional on the submission and implementation of a transformational Enhanced Partnership (EP). On 21 June, Cabinet approved submission of the EP plan and EP scheme by 30 June 1 www.portsmouth.gov.uk 2022. The Department for Transport required some additional text for clarification and an explicit commitment from bus operators to reinvest savings locally. With this agreement, funding has been approved once the EP is implemented. As required, the EP was sent to statutory consultees for comment and only positive responses were received. The final stage in the process is to 'make' the EP by approving its implementation. Once this is complete, funding can be released.
4. Consultation and Engagement
4.1Portsmouth City Council conducted its own research into the views of members of the public and businesses regarding the bus network within Portsmouth, specifically:
• To understand the strengths and weaknesses of local bus travel • Identify the key areas to prioritise in the long and short-term • To measure satisfaction levels of bus users.
4.2These are reflected in the Enhanced Partnership Plan and Scheme and the related Bus Service Improvement Plan (BSIP) for Portsmouth.
Reasons for recommendations
5.1This is the final stage of the process set out in the National Bus Strategy to deliver improvements to the bus network for Portsmouth residents, and so will create benefits for the overall transport system, including reductions in pollution and help deliver zero carbon, make more efficient use of the finite road space available and support improvements across a range of health, community and economic goals.
6. Integrated Impact Assessment
6.1An Integrated Impact Assessment (IIA) was undertaken as part of the development of the BSIP which sets out the strategic aims for the EP and is attached in Appendix B of this report.
Legal implications
7.1The Council, having complied with the statutory requirements of the Transport Act 2000 and having considered whether it is appropriate to make the Enhanced Partnership Plan and Scheme, may by exercising its powers under Section 138G of the Transport Act 2000 may make the Enhanced Partnership Plan and Scheme as proposed.
7.2Once (and if) the decision to make the Enhanced Partnership Plan and Scheme is made, the Council must not later than 14 days after the date on which the
2 www.portsmouth.gov.uk Council made the Enhanced Partnership Plan and Scheme give notice of the making of the Plan and Scheme:
a) in such manner as it considers appropriate for bringing it to the attention of persons in the area, b) to all operators of local services who would, in the opinion of the Council, be affected by the scheme, and c) to a traffic commissioner.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Tertiary Roads Inspection and RepairDecision The Cabinet Member: 1. Approved that the plans and timings of inspections of the tertiary road network are s...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.