Agreed to extend the current supported Portsmouth Park & Ride contract up to 26 October 2024 with delegated authority to the Director of Regeneration in consultation with the Cabinet Member for Traffic and Transportation and Section 151 Officer to negotiate with the current contractor; 2. Agreed the increase to the current contract price to an amount identified through the Department for Transport instigated network review process to a maximum increase of £45,000 per annum; 3. Approved the development and implementation by the Transport Service supported by Procurement and Legal Services, of a procurement strategy to re-tender the contract. The process will include review of options for the electrification or hydrogen operation of Park & Ride services, either at point of contract award or over the term of the contract. This process will be informed by the projected impact of recent successful Portsmouth City Council funding applications including South East Hampshire Rapid Transit (SEHRT) and Portsmouth Bus Service Improvement Plan; 4. Approved that pre-procurement activities may commence, including for peer review with fellow councils and soft market testing with operators; 5. Noted that waiver approval will need to be sought from Procurement and Legal Services in respect of the proposed extensions to the contracts set out above, in accordance with the Council's Contracts Procedure Rules.
Word for word from the decision Portsmouth published for this meeting.Source: democracy.portsmouth.gov.uk
The purpose of this paper is to seek agreement to extend the existing Portsmouth Park & Ride contract to October 2024.
Recommendations
It is recommended that the Cabinet Member for Traffic and Transportation:
2.1Agrees to extend the current supported Portsmouth Park and Ride contract up to 26 October 2024 with delegated authority to the Director of Regeneration in consultation with the Cabinet Member for Traffic and Transportation and Section 151 Officer to negotiate with the current contractor;
2.2Agrees the increase to the current contract price to an amount identified through the Department for Transport instigated network review process to a maximum increase of £45,000 per annum;
2.3Approves the development and implementation by the Transport Service supported by Procurement and Legal Services, of a procurement strategy to re-tender the contract. The process will include review of options for the electrification or hydrogen operation of Park & Ride services, either at point of contract award or over the term of the contract. This process will be informed by the projected impact of recent successful Portsmouth City Council funding applications including South East Hampshire Rapid Transit (SEHRT) and Portsmouth Bus Service Improvement Plan; 1 www.portsmouth.gov.uk 2.4 Approves that pre-procurement activities may commence, including for peer review with fellow councils and soft market testing with operators.
2.5Notes that waiver approval will need to be sought from Procurement and Legal Services in respect of the proposed extensions to the contracts set out above, in accordance with the Council's Contracts Procedure Rules.
Background
3.1The Transport Act 1985 outlines the statutory duty and powers of Portsmouth City Council, to consider the provision of bus routes where there are no commercial services. Park and Ride services operate as a mostly tendered provision across other English cities, although some operate services as part of a commercial network in more established operations.
3.2Portsmouth’s Park & Ride service commenced operation on 5 April 2014. It continues to provide a frequent, reliable, high-quality bus link between the Portsmouth Park & Ride site adjacent to the M275 at Tipner and the city centre, with stops for Portsmouth International Port; Charles Dickens birthplace; the City Centre; Nelson Gate; and The Hard for the Historic Dockyard and Gunwharf Quays.
3.3The service operates with passengers parking for free and paying for the bus journey via paper ticket or smart card. Concessionary passes have not been valid for the service during its period of operation. The current return fare is £4 a day for up to five people in a car with a range of reduced fares for regular travel.
3.4The current Portsmouth Park & Ride service (PR1) operates with a daily frequency of every 15 minutes between 7:00 and 19:15 on weekdays, (with later starts at the weekend and earlier finish on Sundays).
3.5Portsmouth Park and Ride service (PR1) has operated on the same contract since 2014 with variations on frequency, stopping arrangements and for local events as requested by the city council to meet passenger demand. This contract has been provided using high quality branded double decker buses. The contract for the Park & Ride service has run past its maximum term of 5 years plus 3 years extension and is now extended to expire in April 2023 through an approved waiver.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Tertiary Roads Inspection and RepairDecision The Cabinet Member: 1. Approved that the plans and timings of inspections of the tertiary road network are s...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.