Recycling Infrastructure Update

Approved Executive 4 papers

Cabinet approved this item on Tuesday 21 February 2023. Below is the council's own wording, with the papers it was decided on.

Item7

Resolved

1) That Cabinet approves the requirement for a new Materials Recovery Facility (MRF) at Chickenhall Lane in Eastleigh and the associated necessary works to the WTS network, as outlined in this report subject to approval by the Director of Finance and Resources to incur expenditure in line with the sum in the approved capital programme. It is additionally subject to continued support for the scheme from tripartite disposal authority partners HCC and SCC, and Hampshire district authorities. 2) That approval be given to procure, spend and enter into the necessary contractual arrangements, in consultation with the City Solicitor and Monitoring Officer, to implement the proposed development of the new MRF and associated works to the WTS network as set out in this report to be funded from prudential borrowing from the Public Works Loan Board. 3) That authority to make the arrangements to implement the scheme, including minor variations to the design or contract, be delegated to the Director of Housing, Buildings and Neighbourhood Services in consultation with the Director of Finance and Resources as appropriate.
Word for word from the decision Portsmouth published for this meeting. Source: democracy.portsmouth.gov.uk

Follow this further

Built from Portsmouth's papers

What the report saysPro

Report to Cabinet

Purpose of report

1.1This report sets out the business case for Portsmouth City Councils capital investment of a 11.52% share in a new materials recovery facility (MRF) at Chickenhall Lane in Eastleigh and associated works at the Waste Transfer Station (WTS) network across Portsmouth, Southampton and Hampshire. This will enable the delivery of a new system (twin stream) for collecting dry recyclable waste across Portsmouth, Southampton and Hampshire that complies with the requirements for consistency in kerbside recycling services set out in the Environment Act 2021. 1.2 The report sets out the benefits to residents with the introduction of twin stream recycling to enable improved recycling at the kerbside.

1.3Hampshire County Council (HCC) have agreed the capital investment required for the MRF and Southampton City Council (SCC) have set aside funding in their capital programme.

Recommendations

2.1That cabinet approves the requirement for a new Materials Recovery Facility (MRF) at Chickenhall Lane in Eastleigh and the associated necessary works to the WTS network, as outlined in this report subject to approval by the Director of Finance and Resources to incur expenditure in line with the sum in the approved capital programme. It is additionally subject to continued support for the scheme from tripartite disposal authority partners HCC and SCC, and Hampshire district authorities.

1 www.portsmouth.gov.uk 2.2 That approval be given to procure, spend and enter into the necessary contractual arrangements, in consultation with the City Solicitor and Monitoring Officer, to implement the proposed development of the new MRF and associated works to the WTS network as set out in this report to be funded from prudential borrowing from the Public Works Loan Board. 2.3 That authority to make the arrangements to implement the scheme, including minor variations to the design or contract, be delegated to the Director of Housing, Buildings and Neighbourhood Services in consultation with the Director of Finance and Resources as appropriate.

Background

3.1PCC as a unitary authority is both a Waste Collection Authority and a Waste Disposal Authority (WDA). As a WDA the Council has a statutory duty for the disposal of municipal waste arisings and recycling in Portsmouth. In order to fulfil this function, it has, in conjunction with its waste disposal partners HCC and SCC, entered into a multi-year waste disposal service contract with Veolia UK Ltd. 3.2 The Waste Disposal Service Contract (WDSC) with Veolia is a Design, Build, and Maintain as well as Service contract, which requires the provision of the necessary infrastructure. 3.3 The MRFs were originally designed to deal with a set specification in terms of inputs to sort: namely plastic bottles, steel and aluminium cans, paper and cardboard. Whilst over time there have been some minor changes to this specification, namely adding aerosols, it is limited in its scope from changing significantly without requiring major refurbishment or replacement to be able to accommodate and sort different material streams. 3.4 In December 2018, the Government published its Resources and Waste Strategy for England (see background document list), which is the mechanism by which it will deliver on the ambition of the 25 Year Environment Plan to leave the environment in a better condition for future generations. 3.5 This was followed up with major consultations in February 2019 and April 2021 on the four key areas where legislative change is proposed: • consistency of recycling collections; • Deposit Return Scheme (DRS) for drinks containers; • Extended Producer Responsibility (EPR) for packaging; and • a plastics packaging tax.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
MRF: Proposed site layoutAppendix 1 5 MB Download
PDF
IIA Recycling InfrastructureAppendix 3 2.1 MB Download
PDF
(i): IIA Recycling InfrastructureAppendix 3 735 KB Download
PDF
Recycling Infrastructure UpdateDecisions 190 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

9 of 10 attended
GV
Councillor Gerald Vernon-Jackson CBEChair, present
SH
Councillor Suzy HortonVice-Chair, present
CA
Councillor Chris AttwellCommittee Member, present
KB
Councillor Kimberly BarrettCommittee Member, present
DS
Councillor Darren SandersCommittee Member, present
LS
Councillor Lynne StaggCommittee Member, apologies
JF
Councillor Jason FazackarleyCommittee Member, present
LH
Councillor Lee HuntCommittee Member, present
SP
Councillor Steve PittCommittee Member, present
MW
Councillor Matthew WinningtonCommittee Member, present

More from Portsmouth Cabinet

All decisions
MeetingDecisionOutcome
22 Sep 2026 Housing & Social Care Scrutiny Panel review "Portsmouth Homes' compliance with the Transparency, Influence & Accountability Standard (Part of the Consumer Standards) - Response reportThanked the Housing and Social Care Scrutiny Panel for its work in undertaking the review and for the report; and 2. ... Noted Open
22 Sep 2026 Publicising Fly Tipping & Environmental Crime Cases PolicyApproved and adopted the Publicising Fly Tipping and Environmental Crime Cases Policy effective from 23 September 202... Approved Open
21 Jul 2026 Carbon Action PlansNoted the report which is for information and is not subject to call-in. Noted Open
21 Jul 2026 Education, Children & Young People Scrutiny Panel review "Increasing accessibility in Portsmouth's play parks" - Response reportThanked the panel for its work in undertaking the review. 2. Noted and considered the conclusions and recommendations... Noted Open
21 Jul 2026 Treasury Management Outturn Report 2025/2026Noted the actual prudential and treasury management indicators based on the unaudited accounts, as shown in Appendix ... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies