Resolved
RESOLVED that the Joint Committee: 1. APPROVED a one-year extension to the FTZ programme to 30 June 2025; and 2. ACCEPTED and APPROVED the proposed funding reprofile to accommodate the one-year programme extension.
Solent Transport Joint Committee approved this item on Monday 6 March 2023. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED that the Joint Committee: 1. APPROVED a one-year extension to the FTZ programme to 30 June 2025; and 2. ACCEPTED and APPROVED the proposed funding reprofile to accommodate the one-year programme extension.
3.1Solent Transport received £28.759M of funding for the Solent Future Transport Zone (FTZ) programme from Department for Transport (DfT) in March 2020, shortly before the country went into lockdown for the Covid- 19 pandemic.
3.2Solent Transport has made strong progress towards the delivery of its FTZ objectives and considers itself to be one of the leading FTZ programmes.
3.3Solent was the first of the FTZs to reassess its delivery programme in light of the pandemic and its likely effects, it has still made positive advancement against its goals: • setting five new UK aviation firsts, • launching, and operating three rental e-scooter scheme trials, • developing and launching the UK’s first multicity Mobility as a Service (MaaS) app and • launch of Solent-wide bike and e-bike hire scheme.
1 www.portsmouth.gov.uk 3.4. Strong progress has also been made on all other projects within the programme; all of which are scheduled to launch within the next six months.
3.5Solent Future Transport Zone is seen by DfT as delivering against its objectives.
Challenges:
3.6The FTZ programme has however, faced considerable challenges: • External issues such as the COVID19 pandemic, • the UK leaving the EU and the war in Ukraine have all had direct and indirect effects on programme delivery, • the MaaS delivery has also been affected by changes in the rail industry brought on by the creation of Great British Railways: • difficultly in recruiting means the team has never actually reached its full staff allocation
3.7The knock-on effects of these issues on other organisations has limited the ability of third-party organisations, partners, and suppliers to effectively work with us in a timely manner
3.8Uncertainty at national and regional government levels has impacted timely decision making and significantly reduced risk appetite.
3.9Despite these risks overall the programme will still deliver within the original timescales, however the amount of operational testing time that remains available to prove the value and business case of these projects will be much more limited. This may in-turn limit the research value of some of the programme deliverables.
Proposal:
3.10Solent Transport continues to make every effort to create a legacy from FTZ, but the June 2024 timescale would significantly limit the ability for projects to become self-sustainable or establish sufficiently compelling business cases to attract additional income from other sources.
3.11In August 2022 Solent Transport submitted a draft proposal to DfT to explore the idea of securing an extension to the programme timescales (no additional funding was requested as it was made very clear by the DfT that none was available).
3.12In Oct 2022 the DfT wrote to Solent Transport (see Appendix A) to approve the years extension to the current programme (subject to approval through the FTZ governance structure) on the basis that it could be delivered in line with the original budget allocation. 2 www.portsmouth.gov.uk 3.13. A comprehensive financial reprofiling exercise has subsequently been undertaken to recognise and enable the extension of the programme for an additional year.
Funding allocation reprofile to accommodate a one-year extension:
3.14The below table provides a high-level summary of the financial reprofile proposal undertaken to take account of an additional year of programme delivery.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Future Transport Zone (FTZ) ExtensionReport | 142 KB | DownloadRead as text |
Follow Solent Transport Joint Committee at Portsmouth and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 27 Jul 2026 | Devolution Updates.It was agreed that ferries should be considered as part of the wider strategic transport network, even though they ar... | Agreed | Open |
| 27 Jul 2026 | Solent Transport ProgrammeIt was agreed that private e-scooters remain the main concern due to limited regulation and public awareness, and tha... | Agreed | Open |
| 8 Oct 2024 | Minutes of the previous meeting held on 6 March 2023RESOLVED that the minutes of the meeting held on 6 March 2023 be approved as a correct record. | Approved | Open |
| 8 Oct 2024 | Business Plan 2024/25RESOLVED that the Joint Committee AGREED the Draft Business Plan and asked the member authorities to take it through ... | Agreed | Open |
| 8 Oct 2024 | Solent Transport Financial UpdateRESOLVED that the Joint Committee: 1. NOTED the outturn for the 2023/24 revenue budget 2. NOTED the balance in reserv... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.