The Cabinet noted the report which is for information only and is not subject to call-in.
Cabinet noted this item on Tuesday 21 March 2023. Below is the council's own wording, with the papers it was decided on.
Resolved
The Cabinet noted the report which is for information only and is not subject to call-in.
2.1The purpose of this report is to summarise PCC's current contractual and commercial position in relation to the PFI Highways Maintenance Contract.
2.2To note the transfer to the Regeneration Directorate and proposed arrangements to manage the contract.
2.3To note the contract ends on 31 March 2030 and make members aware of the process of contractual Handback.
2.4To note the first steps in preparing for highways maintenance that follows the end of the PFI contract.
3. Information Requested
3.1The PFI contract was entered into in 2004 with Ensign Highways Ltd; a special purpose vehicle to which Colas is appointed to carry out the works. Colas' responsibility under the contact is primarily to repair, maintain, operate and manage 455km of highway network.
3.2This contract will expire on 31 March 2030. 1 www.portsmouth.gov.uk THIS ITEM IS FOR INFORMATION ONLY (Please note that "Information Only" reports do not require Integrated Impact Assessments, Legal or Finance Comments as no decision is being taken)
3.3The PFI contract was drafted around the core principle of up-front capital rehabilitation of the carriageways to save a lifetime of repeated "patch and mend". This approach meant that PCC could deal with the underlying causes of carriageway and footway deterioration (ie bring the road up to an "acceptable" standard as defined in the contract) and then keep them well maintained through a light touch approach for rest of the life of the contract.
3.4The main functions of the PFI that are delegated to Colas, are routine and cyclic maintenance of carriageways, footpaths, kerbs, gulley, drainage runs, roads surface, white lines and more.
3.5This includes winter maintenance, street lighting, street cleansing, maintenance of highway structures, arboriculture and landscape services, surface drainage gullies and pipes and third party claims (accidents). Colas also provide an emergency response, network management and the co-ordination with utilities.
3.6Beyond the initial mobilisation in 2004, during which time Colas set up the compound in Walton Rd and got ready to commence the works, the 25-year contract comprised four parts:
• Core investment period (first 5 years) • Life Cycle Replacement (remaining 20 years) • Operation and Maintenance (throughout the 25-year life of contract) • Handback (last 5 years)
These, and the contract structure, are explained in more detail in Appendix A.
Handback
3.7At the end of the contract, each element of the network shall comply with the Handback Requirements. These are detailed in the contract and cover the condition of everything that Colas has been looking after for the last 25 years.
3.8The contract is very specific as to the requirements for Handback of each component of the network. In simple terms, the network shall be in a condition such that only minor repairs and whole life intervention maintenance are required.
3.9Surveys carried out jointly by Colas and the PCC client team, will take place before the end of the contract to make sure that the condition of the network is adequate and if not, there is time to carry out improvements and repairs.
3.10These surveys start no earlier than 5¼ years (31 Dec 2024) before the end of the contract and no later than 4¾ years (30 June 2025) before the end of the contract. 2 www.portsmouth.gov.uk THIS ITEM IS FOR INFORMATION ONLY (Please note that "Information Only" reports do not require Integrated Impact Assessments, Legal or Finance Comments as no decision is being taken)
Cost and Funding
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
PFI: The Way Forward: Appendix AAppendix | 158 KB | Download |
PDF |
PFI: The Way ForwardReport | 113 KB | DownloadRead as text |
Follow Cabinet at Portsmouth and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 22 Sep 2026 | Housing & Social Care Scrutiny Panel review "Portsmouth Homes' compliance with the Transparency, Influence & Accountability Standard (Part of the Consumer Standards) - Response reportThanked the Housing and Social Care Scrutiny Panel for its work in undertaking the review and for the report; and 2. ... | Noted | Open |
| 22 Sep 2026 | Publicising Fly Tipping & Environmental Crime Cases PolicyApproved and adopted the Publicising Fly Tipping and Environmental Crime Cases Policy effective from 23 September 202... | Approved | Open |
| 21 Jul 2026 | Carbon Action PlansNoted the report which is for information and is not subject to call-in. | Noted | Open |
| 21 Jul 2026 | Education, Children & Young People Scrutiny Panel review "Increasing accessibility in Portsmouth's play parks" - Response reportThanked the panel for its work in undertaking the review. 2. Noted and considered the conclusions and recommendations... | Noted | Open |
| 21 Jul 2026 | Treasury Management Outturn Report 2025/2026Noted the actual prudential and treasury management indicators based on the unaudited accounts, as shown in Appendix ... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.