Approved funding from City wide Neighbourhood CIL fund to fund the repair and enhancement of Christmas lights infrastructure and additional/replacement Christmas Light Motifs across the city (or otherwise agreed priority sites). And 2. Gave approval that any underspend from the allocated funding is retained as a ringfenced reserve for the future of maintaining the provision of Christmas lights in the city.
Word for word from the decision Portsmouth published for this meeting.Source: democracy.portsmouth.gov.uk
1.1To address the current concerns with 2023/34 Christmas Lights budget concern and provide a definitive response.
1.2This is extremely time sensitive, with procurement and action needing to be in place for September to enable procurement and repairs for early November 2023 when lights are installed for the season.
Recommendations
2.1To request Ward CIL (Community Infrastructure Levy) via the existing Neighbourhood CIL procedure, as outlined within the Draft CIL Neighbourhood Portion Spend Guidance Note to fund the repair and enhancement of Christmas lights infrastructure across the city of Portsmouth (or otherwise agreed priority sites). AND
To request Ward CIL via the existing Neighbourhood CIL procedure, as outlined within the Draft CIL Neighbourhood Portion Spend Guidance Note to fund additional/replacement Christmas Light Motifs across the city (or otherwise agreed priority sites).
OR
1 www.portsmouth.gov.uk - Official Sensitive -
For Cabinet to Approve funding from city wide Neighbourhood CIL fund to fund the repair and enhancement of Christmas lights infrastructure and additional/replacement Christmas Light Motifs across the city (or otherwise agreed priority sites).
And, in either case
2.2For Cabinet to give approval that any underspend from the allocated funding is retained as a ringfenced reserve for the future of maintaining the provision of Christmas lights in the City.
3. Background Infrastructure
3.1Christmas lights provision (including infrastructure) have had limited investment previously and acknowledged by the electrical contractor in 2022/23 as near end of life.
3.2In 2023 we commissioned a report to establish the seriousness of the current infrastructure and lighting problems for Christmas 2023/24. Across the city:
o 139 infrastructure points were deemed as requiring immediate replacement or attention
o 40 infrastructure points were deemed passable condition (unable to confirm either condemned or good status - we anticipate some or all of these units to require replacement for reliable light provision)
o 105 were deemed good condition (requiring no action for 2023/24)
3.3Replacement is estimated at £500 per connection point (please note this could be reduced to £395 for some points but we do not know ahead of commissioning how many, if any would be costed at the lower price) putting costs in the region of a maximum estimate of £89,500.
3.4Details of the location of each of the infrastructure point requiring immediate replacement of attention to maintain previous levels of Christmas Lights coverage (Option A below) are contained in the table in Appendix 1.
4 Background Christmas light provision
4.1Christmas lights have had limited investment previously and acknowledged by the electrical contractor in 2022/23 as near end of life (with many working beyond reasonable expectations). This reflects feedback from contractors in previous years.
4.2All lights are currently allocated specifically to wards and linked to specific infrastructure (although many could be used in other locations or smaller patterns in wards).
2 www.portsmouth.gov.uk - Official Sensitive -
4.3Some lights and infrastructure has been funded from Neighbourhood CIL, or are linked to particular infrastructure which limit where items can be used or prevent them being used in different Wards.
4.4Items (particularly motifs) were removed as unsafe following breakages on site in 2023/24 as one style was deemed unsafe reducing lights in different areas across the city. At the time we extended (using an alternative lamppost provision) or removed lights to maintain maximum provision for each ward.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.