Sea Change (Shore Power and ZEVI update)

Noted Executive 2 papers

Cabinet noted this item on Tuesday 3 October 2023. Below is the council's own wording, with the papers it was decided on.

Item4

Resolved

Noted and recommended that Full Council notes the importance of investing in shore power at Portsmouth International Port (PIP). 2. Noted and recommended that Full Council notes the existing funding for shore power in the capital programme, and the revised funding requirement for shore power. 3. Subject to a satisfactory financial appraisal approved by the Director of Finance and Resources & S.151 Officer, recommended that Full Council approves investing in shore power at a capital cost of £26.1m to be funded as follows: 4. Grant: £18,474,158 5. Prudential Borrowing: £4,625,842 6. Corporate resource: £3,000,000
Word for word from the decision Portsmouth published for this meeting. Source: democracy.portsmouth.gov.uk

Follow this further

Built from Portsmouth's papers

What the report saysPro

Report to Cabinet

Purpose of report

To discuss the proposal of the SEA CHANGE project at the Portsmouth International Port (PIP) and to seek project approval.

Recommendations

2.1Cabinet and Full Council notes the importance of investing in shore power at Portsmouth International Port (PIP).

2.2Cabinet and Full Council notes the existing funding for shore power in the capital programme, and the revised funding requirement for shore power.

2.3Subject to a satisfactory financial appraisal approved by the Director of Finance and Resources & S.151 Officer, Full Council approves to investing in shore power at a capital cost of £26.1m to be funded as follows: • Grant: £18,474,158 • Prudential Borrowing: £4,625,842 • Corporate resource: £3,000,000

Background

3.1Background on the ZEVI Competition

The Zero Emissions Vessels and Infrastructure competition (ZEVI), was announced in February 2023, funded by UK Government, and delivered in

1 www.portsmouth.gov.uk - Official -

Cabinet and City Council

partnership with Innovate UK. As part of ZEVI, the Department for Transport allocated over £80m to 10 projects supported by 52 organisations from across the UK to deliver real world demonstration R&D projects in clean maritime solutions. Projects will take place in multiple locations from the Orkney Isles to the south-west of England, with the Portsmouth Project being the flagship bid demanding 20% of the overall fund.

ZEVI is part of the UK Shipping Office for Reducing Emission’s (UK SHORE).

Focused on clean maritime technologies that can be scaled rapidly to decarbonise the UK’s domestic maritime sector. In March 2022, the Department announced the biggest government investment ever in our UK commercial maritime sector, allocating £206m to UK SHORE, a new division within the Department for Transport focused on decarbonising the maritime sector. UK SHORE is delivering a suite of interventions throughout 2022-2025 aimed at accelerating the design, manufacture and operation of UK-made clean maritime technologies and unlocking an industry-led transition to Net Zero.

3.2Background on SEA CHANGE

The SEA CHANGE (Sustainable Energy and Air Quality Improvement for Coastal Harbours to Achieve Net-zero with Grid Enhancements) project will build and operate a new shore power system serving the 3 largest and busiest berths at PIP.

The system will allow Brittany Ferries vessels and visiting cruise ships to 'plug-in' and therefore switch off their engines whilst at berth. Additionally, the system will support the charging of 2 new hybrid/LNG ferries (provided by Brittany Ferries) that will enter and leave the harbour under electric power, to further reduce CO2 emissions and air pollutant across the port and wider city.

The challenges of multi-vessel shore powering will be met through smart control of hybrid vessel battery charging and smart control of onshore power systems and batteries, real-time telemetry, and communications as well as wider data exchange facilitated by an ecosystem of interoperable digital twins surfacing data for selective, secure sharing. The interplay of shared data between offshore vessels and onshore power equipment will support dynamic, sustainable, balanced energy provision and carbon reporting over time.

The shore power system will support simultaneous powering of multiple vessels, with different onboard AC frequencies, voltages, and different ship-shore connectors. This will require:

• A new 15MVA grid connection (secured), dedicated to shore power. • A dedicated shore power substation at the port, with complex power electronics and real-time control. • A mobile Cable Management System (CMS) at each berth (the plug-in charger). 2 www.portsmouth.gov.uk - Official -

Cabinet and City Council

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Sea Change (Shore Power and ZEVI update)Report 178 KB DownloadRead as text
PDF
Sea Change: Integrated Impact AssessmentReport 61 KB Download

At this meeting

Whole meeting

Who was there

7 of 10 attended
SP
Councillor Steve PittChair, present
SH
Councillor Suzy HortonVice-Chair, apologies
DA
Councillor Dave AshmoreCommittee Member, apologies
KB
Councillor Kimberly BarrettCommittee Member, present
IH
Councillor Ian HolderCommittee Member, present
LH
Councillor Lee HuntCommittee Member, present
HM
Councillor Hugh MasonCommittee Member, present
DS
Councillor Darren SandersCommittee Member, present
GV
Councillor Gerald Vernon-Jackson CBECommittee Member, apologies
MW
Councillor Matthew WinningtonCommittee Member, present

On this subject at Portsmouth

Search all
  1. Sea Change (Shore Power and ZEVI update)This decision
  2. Sea Change (Shore Power & ZEVI update)Noted
  3. 17/00332/FUL - Princes House 32 Kings Terrace Southsea - Change of use of part basement (storage unit 2) to form an artist studio (Class B1C) (report item 9)Refused
  4. 17/00555/FUL - 22 Jessie Road Southsea PO4 0EN - Change of use from purposes falling within a C3 (dwelling house) or C4 (house in multiple occupation) to a seven bedroom/seven person house in multiple occupation (sui generis) (report item 12)Refused
  5. 17/00178/FUL - 103 Manners Road, Southsea PO4 0BD - Change of use from Class C4 (house in multiple occupation) to house in multiple occupation for seven persons (Sui Generis) (Report item 5)Refused
  6. 17/00392/FUL - 26 Manners Road, Southsea PO4 0BB - Change of use from purposes falling within Class C4 (house in multiple occupation) or Class C3 (dwelling house) to 7 bedroom 7 person house in multiple occupation (Sui Generis) (Report item 8)Decided

More from Portsmouth Cabinet

All decisions
MeetingDecisionOutcome
22 Sep 2026 Housing & Social Care Scrutiny Panel review "Portsmouth Homes' compliance with the Transparency, Influence & Accountability Standard (Part of the Consumer Standards) - Response reportThanked the Housing and Social Care Scrutiny Panel for its work in undertaking the review and for the report; and 2. ... Noted Open
22 Sep 2026 Publicising Fly Tipping & Environmental Crime Cases PolicyApproved and adopted the Publicising Fly Tipping and Environmental Crime Cases Policy effective from 23 September 202... Approved Open
21 Jul 2026 Carbon Action PlansNoted the report which is for information and is not subject to call-in. Noted Open
21 Jul 2026 Education, Children & Young People Scrutiny Panel review "Increasing accessibility in Portsmouth's play parks" - Response reportThanked the panel for its work in undertaking the review. 2. Noted and considered the conclusions and recommendations... Noted Open
21 Jul 2026 Treasury Management Outturn Report 2025/2026Noted the actual prudential and treasury management indicators based on the unaudited accounts, as shown in Appendix ... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies